Installation Instructions
STEP FOUR - Secure Deck Panels to Posts
• Slide bottom channel of pre-cut panel on to lower
clip. (Dia. #7)
• Insert clips into top channel of panel on each end.
• Using(4)-#8x3/4″TEKscrews,attachtheupper
2-clips to the post.
• Using(8)-#8x3/4″TEKscrews,securetheupper
and lower clips to the panel.
STEP FIVE-CutandInstallTopandBottomRailSnaps
• Measure between posts at the top and bottom.
(Dia.#8)
• Cuttop&bottomsnapcovers1/16″lessthan
opening.
• Clean cut areas and apply touch-up paint on all
exposed metal.
• Snap each rail snap over the corresponding rail
channel until properly seated. (Dia. #9)
STEP SIX - Install Support Legs
• Foropeningsgreaterthan4′,installsupportlegs
under center of bottom rail (Dia. #10)
• Slide support leg under bottom rail and mark.
• Installtwodeckscrewsatlocationofsupportleg,
install support leg over screws.
• Using(1)-#8x3/4″TEKscrews,securethesupport
leg to bottom rail. (Dia. #11)
STEP SEVEN - Install Stair Panels
• Hold stair panel against posts and adjust for equal
end spacing (Dia. #12)
• Mark the panel at 4 locations of post connection.
• Miter cut panel at marked locations and place panel
inopening.Cutrail1/16″lessthanopening.
• Mark posts for location of bottom rail clips.
• Removepanelandinstallclips.(Dia. #13)
• Clean cut areas & apply touch-up paint on exposed
metal.
• Placecutpanelbetweenposts,pushrailonto
bottomclips,placeclipsintoupperchannel,attach
clips to post and secure panel to all clips as per
Step 4. (Dia. #7)
• Miter cut and install top and bottom rails as per
Step 5. (Dia. #8 & #9)
ALUMINUM PICKET RAILING
Installation Instructions
Videos available at www.williamsrailing.com
SUGGESTED TOOLS:
IMPORTANT NOTE:
Actual Picket Panel Sizes Are As Follows:
6′Panels=69.43″
8′Panels=91.31″
3″postsarerequiredtoreach6′&8′lengths
NOTE: IF INSTALLING POST LIGHTING, WIRING MUST BE INSTALLED PRIOR TO
SECURING POSTS TO DECK/STAIR SURFACE AND INSTALL IN TOP RAIL SNAPS.
It is the responsibility of the installer to meet all local code requirements
andobtainallrequiredbuildingpermits.Theinstallershoulddetermineand
implement appropriate installation techniques for each installation situation.
Williams Architectural Products or its reseller shall not be held responsible
for improper or unsafe installations.
www.williamsrailing.com
©2017WES,LLC.AllRightsReserved.Version1.2
Cordless Drill
Pencil
3/8″HexDriverBit
Safety Glasses
MiterSawW/Non-FerrousBlade
Level
TapeMeasure
#2Sq.DriverBit
3/16″DrillBit