Page 0 of 11 EXD 8.5-001 PV Module User Manual_REV.
INDEX 1. Introduction for this User Manual .................................................................................................................................... 2 2. General ............................................................................................................................................................................ 2 2.1 Applicable Products..........................................................................................................................
1. Introduction for this User Manual This Manual contains information regarding the installation, maintenance and use of the series solar modules manufactured by Heliene Inc. All instructions should be read and understood before attempting installation. Failure to follow these safety instructions could result in personal injury or property damage. Installation and operation of solar modules require specialized skills, and only professional personnel can engage in the work.
3. Module Specification 36M Electrical Values The rated electrical values at Standard Test Conditions (STC) of Heliene Modules can be found in the table below. The Electrical characteristics are within +/- 10% of the indicated values of ISC, VOC, and PMAX under STC (irradiance of 1000W/m2, AM 1.5 spectrum, and a cell temperature of 25°C (77°F)). 36P Peak Rated Power Pmpp(W) 185 180 175 170 Maximum Power Voltage Vmpp(V) 20.2 19.62 19.2 18.93 Maximum Power Current Impp(A) 9.43 9.3 9.22 9.
4. Safety Precaution 5. Précautions de Sécurité 4.1 Warnings: Before unpacking, installing, wiring, operating or maintaining Heliene Modules, responsible personnel should read and understand all safety precautions. Each modules produces a continuous current (DC) when exposed to sunlight or other light source. Contact with any of the electrically active parts, such as terminals of the modules, can result in injury or death weather module is connected or not. 5.
. Transport/Unpack/Storage of PV Modules 6.1 Transportation and General Rules Heliene recommend the modules be stored in its original packaging strapped to pallets until they reach the destination of installation site. Do not remove any strapping or packaging materials if the modules require secondary transportation/long-term storage. Do Not transport modules in an upright position, only transport them in box strapped to pallet as supplied by Heliene Inc. on a level surface.
.3 Installation Method 7.3.1 General The module is considered to be in compliance with UL 1703 only when the module is mounted in the manner specified by the mounting instructions below. A module with exposed conductive parts is considered to be in compliance with UL 1703 only when it is electrically grounded in accordance with the instructions presented below and the requirements of the National Electrical Code.
For Rooftop installation: Ensure to comply with all local building codes. Freestanding modules turn a Class B rooftop into a Class C rooftop. Use appropriate corrosion-proof fastening materials. Top or Bottom clamping methods will vary and are dependent on the mounting structures. Follow mounting guidelines recommended by the PV racking Suppliers. 7.3.3 Electrical Installation All wiring should be performed by registered installer and comply with local codes ®ulations.
Module connectors Brand Model Physical Appearance Website Multi-Contact PV-KBT4/6LL (Male) PV-KST4/6LL (Female) http://ec.staubli.com Lumberg LC4-CP30 (Female) LC4-CP31 (Male) http://www.lumberg.com Zhejiang Jiaming Tianheyuan Photovoltaic Technology (JMTHY) PV-JM601 http://en.jmthy.com Zhejiang Jiaming Tianheyuan Photovoltaic Technology (JMTHY) PV-JM608 http://en.jmthy.com Zhejiang Jiaming Tianheyuan Photovoltaic Technology (JMTHY) PV-JM601A http://en.jmthy.
Grounding All module frames and mounting racks must be accordance with CEC, NEC and applicable local codes. It is recommended that modules be grounded. For grid connected modules in U.S and Canada: All PV modules must be grounded by electrical connection from the module frames to the ground. A UL-listed grounding lug or UL approved clamp is to be used. Connect modules frames to each other using cables with cable lugs. All connections on the conductive connection must be fixed.
7.6 Warranty If your installation does not work properly, please inform your installer immediately. Qualified professionals should be advised to avoid any electrical shock or loss of life due to high voltage of the array. If you need necessary replacement in the event of accelerated deterioration of the module, please go to: https://www.heliene.com/contact to fill out your RMA Submission/Warranty Inquiry, a responsible personnel will reach out to you within 48 hrs. 8.