Add shims or blocking as necessary to create
a smooth, at surface. Verify that the panel's
span rating meets or exceeds job require-
ments. Soft spots may occur if joist on-center
spacing exceeds panel span rating.
Panels should be installed with the 8' length
perpendicular to support members. When
laying out ooring, make certain that each
panel covers at least two spans and the
panel edges fall at the center of the support.
It may be necessary to trim some panels.
Make sure that the “This side down” stamp
is on the underside. Lay out rows of panels
so that end joints are offset by at least one
on-center spacing of the supports.
Gapping Panels
The panel industry recommends spacing
wood-based panels to allow for the expan-
sion that occurs when they are exposed to
moisture. When installing Weyerhaeuser
ooring, maintain a
1
⁄8" gap at panel ends
and edges. See Figure 3 on page 2.
Weyerhaeuser single-layer ooring is
manufactured with a self-gapping tongue-
and-groove (T&G) prole that automatically
gaps the edges as the oor is assembled.
See Figure 1. A 10d box nail can be used to
gauge the ⅛" gap between panel ends.
These spacing recommendations may not
be adequate for buildings over 80' in length
or width. See the recommendations for
installing temporary
Expansion Joints for
Floors in Large Buildings on page 3.
To help prevent standing water on ooring,
and minimize moisture issues, Weyerhaeuser
Achieving optimum performance with Weyerhaeuser Edge
™
and Edge Gold
™
oriented strand board
(OSB) ooring and Weyerhaeuser sheathing depends heavily on correct installation and panel choice.
End-user complaints can be avoided by choosing an appropriate panel for the application, practicing
quality work, and installing Weyerhaeuser panels according to the techniques recommended here.
Minimize the chance for
accidents by installing
panels with the
textured side up.
Safety
Always make safety a priority on the job site.
Follow all OSHA requirements for proper per-
sonal protection equipment (PPE), fall protec-
tion, forklift safety, and the use of equipment.
Adhere to Weyerhaeuser installation details,
including the installation of safety bracing on
unsheathed oors and roofs.
Consider that wet and/or steeply pitched
sheathing may be slippery. Make sure work-
ers have clean, slip-resistant roong shoes
and use all safety restraints required by
OSHA. To help minimize the chance for
accidents, install panels with the textured
(or screen) side up. Weyerhaeuser sheathing
is stamped “This side down” on the smooth
face to facilitate safe installation.
Storage
Like any wood product, wood-based panels
are at risk of fungal decay or rot if exposed
to repeated wetting or high-moisture
environments. Panels that are exposed to
such conditions may deteriorate, lose
strength, or support mold growth. For these
reasons, protection from these conditions
must be provided.
Keep all building materials dry and out of
standing water prior to installation.
Weyerhaeuser panels should be stored
at least 4" off the ground. During transit
and storage, make sure the panels are
not damaged.
Floors
Laying Panels
Before installing ooring, make sure the
framing underneath is level and not twisted.