Enphase IQ System Controller 2 Wiring

Installer Memo - North America
1 © 2022 Enphase Energy Inc. All rights reserved. May 13, 2022
Wiring The Rapid Shutdown Switch to IQ System Controller 2
Overview
The Enphase rapid shutdown switch/Enphase system shutdown switch (EP200G-NA-02-
RSD) provides Rapid Shutdown (RSD) capability, as required by NEC standard, for IQ8
Microinverters when used with IQ System Controller 2 (EP200G101-M240US01). The Rapid
Shutdown Switch and IQ System Controller 2 are certified to the UL1741 Photovoltaic Rapid
Shutdown Equipment (PVRSE) requirement.
This special bulletin includes instructions to enable installers to avoid issues with the rapid
shutdown switch wiring and installation. The bulletin covers:
1. When to use the RSD switch with IQ System Controller 2 (EP200G101-M240US01)?
The RSD switch is required and must only be used for IQ8 microinverters. Refer to page 2 of
this bulletin on how to use IQ System Controller 2 with legacy microinverters (IQ6/7 or
M215/250)
2. How to safely wire the RSD switch to the IQ System Controller 2?
Installers MUST ensure that the IQ System Controller 2 is powered off before performing any
wiring. Wiring an energized IQ System Controller 2 is a safety hazard. If the RSD terminals
are inadvertently connected to any other conductive surface while the IQ System Controller 2
is energized the IQ System Controller 2 can be damaged and will require replacement.
Installers must follow the wiring scheme as described in this document. The wiring scheme for
the Rapid Shutdown Switch depicted in the installation guide is incorrect for a small number
of IQ System Controller 2 units manufactured prior to December 8, 2021. Incorrect wiring
prevents IQ System Controller 2 from exiting the rapid shutdown state and from being
commissioned correctly. The installation guides with incorrect wiring scheme have a revision
of 140-00236-02 or lower.
It is recommended that installers remove the terminal block from System Controller before
wiring the jumpers/ cable headers.
3. How to energize IQ System Controller 2 and exit Rapid Shutdown?
Installer must keep the Rapid Shutdown (RSD) switch turned off before energizing the IQ
System Controller 2. If the RSD switch is turned on before energizing the IQ System Controller
2, the IQ System Controller 2 goes into manual override mode, which forces installers to follow
the process to remove the IQ System Controller from manual override mode and leads to
delays during commissioning.

Summary of content (5 pages)