Installation Guide
Step 2: Commissioning and Configuring the
Installation
ThissectiondescribeshowtousetheSetAppmenusforcommissioningandconfiguringtheinverter
settings.
Menusmayvaryinyourapplicationdependingonyoursystemtype.
To access the Commissioning screen:
Dooneofthefollowing:
l Duringfirsttimeinstallation:UponActivationcompletion,intheSetApp,tapStart Commissioning.
ThemainCommissioningmenuscreenisdisplayed.
l Iftheinverterhasalreadybeenactivatedandcommissioned:
a. IfnotalreadyON-turnONACtotheinverterbyturningONthecircuitbreakeronthemain
distributionpanel.
b.
OpenSetAppandfollowtheinstructionsonthescreen(scantheinverterbar-code;movethe
ON/OFF/PswitchtoPposition(forlessthan5sec)andrelease).
ThemobiledevicecreatesaWi-Ficonnectionwiththeinverteranddisplaysthemain
Commissioningscreen.
Inthemainmenus,tapthemenuredarrows(
›)toperformthesystemcommissioningorconfiguration
task.TaptheBackarrow(‹)toreturntothepreviousmenu.
Thenextsectionsprovidemoreinformationaboutconfigurationoptions(inadditiontoCountry and
LanguageandPairing,describedinStep2:CommissioningandConfiguringtheInstallationonpage34).
Setting Country and Language
1.
FromtheCommissioningscreenselectCountry and Language.
2.
FromtheCountrydrop-downlist,selecttherequiredcountrysetting.
WARNING!
The inverter must be configured to the proper setting in order to ensure that it complies with the
country grid code and functions properly with the country grids.
AVERTISSEMENT!
L'onduleur doit être configuré pour le pays approprié afin d'assurer un fonctionnement convenable
avec le réseau de ce pays.
3. FromtheLanguagedrop-downlist,selectthelanguage.
4. TapSet Language.
Pairing
1.
Fromthemainmenu,selectPairing.
2. TapStart Pairing.
-Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.0
34
Step 2: Commissioning and Configuring the Installation