6.6 ft (2 m) Barn Door Hardware 6.
Welcome Guide • English Contents: Before getting started, ensure the package contains the following components: A x1 E4 x4 B x5 F x1 C1 x1 F1 x2 C2 x1 F2 x2 C3 x1 G x5 D x2 G1 x5 E1 x4 H1 x2 E2 x4 H2 x2 E3 x8 3
Tools you will need Tape measure Screwdriver Wrench and socket set Electric drill Level Marking tools Router Drill bit 7/64” (2.8 mm), 1/8” (3 mm), 1/4” (6.5 mm), 5/16” (8 mm), 7/16” (11 mm) IMPORTANT SAFEGUARDS Read these instructions carefully and retain them for future use. If this product is passed to a third party, then these instructions must be included.
Installation Step 1: Track Preparation Keep level 2” (51 mm) minimum on one side of the door Door height + 1.75" (44 mm) Door Door opening Header board (1 x 6 recommended) Floor clearance: Using the dimensions shown will allow for a 3/8” (9.5 mm) space between the door and floor. Floor NOTICE 1. 2. 3. 4. 5. 6. 7. 8. If your door opening DOES NOT have trim going around it, follow the below steps. Using the layout above as reference, position the track where you would like it.
Installation Step 2: Header Board Installation Keep level 2” (51 mm) minimum on one side of the door Door height + 1.75” (44 mm) Door opening Header board (1 x 6 recommended) Floor clearance: Using the dimensions shown will allow for a 3/8” (9.5 mm) space between the door and floor. Floor NOTICE Draw a straight vertical line of at least 3.5” (89 mm), going through the mark that you made for the stud location. 1. Locate and mark the center of the 1 x 6. 2.
Installation Step 3: Track Installation B C3 C1 A G1 G Attaching the track directly to the studs: 1. Using the 5 marks you made, drill a 1/4” (6 mm) pilot hole 1” - 3” (25 - 76 mm) deep on each mark. 2. Slide the washer (G1) over the screw (G) and repeat for all 5 screws. NOTICE If the door is going to stop before the last hole (8” / 20 cm) on either end, then the door stop C1 or C2 will need to be installed onto the rail first. 3. Position the track over the drilled holes. 4.
Attaching the track to the header board: 1. Place the track in the center of the header board and determine where you want it to be installed. Make sure the track is level before making your hole marks. NOTICE 2. Mark locations for all 5 holes. 3. Using the 5 marks you made, drill a 1/4” (6 mm) pilot hole 1” - 3” (25 - 76 mm) deep on each mark. 4. Follow steps 2 through 6 under “Attaching the track directly to the studs”. Installing door stops 1.
D H2 H1 E1 / E2 E3 E4 Installing hanger brackets 1. Starting from the left side of the door, measure in 2” (51 mm) and make a mark. 2. Measure down 1-1/2” (38 mm) and make a mark. 3. Take the hanger bracket and center the top hole over the line intersection. 4. Mark the bottom hole (making sure the center of the bottom hole is 2” (51 mm) away from the door edge). 5. Remove the bracket and drill a 7/16” (11 mm) hole through the door for each bracket hole.
Installation Step 5: Hanging Door D D 1 A H1 2 1. Lift the door onto the track. 2. Turn the anti-jumper discs to where they are now centered on the door edge. 3. Tighten.
Installation Step 6: Installing Floor Guide F1 F 3/4” (19 mm) 1/4” (6 mm) If your door already has a groove in the bottom of the door: 1. With the door at open position, place the floor guide (F) into the center of the groove. (The floor guide should not be sticking outside the edge of the door.) 2. Loosen the back door stop (C2) and slide the door backwards (enough to see the floor guide). 3. Screw the floor guide (F) into the floor using 2 screws (F1). 4.
Step 7: Checking Operation of Door • Slide the door back and forth and make sure it rolls smoothly and isn’t hitting or dragging on anything.