Introduction
The OSMAC Satellite is designed for installation on a substantial concrete foundation with embedded conduit of various
diameters to enable power, eld and earth ground wiring to be routed into the cabinet. A mounting bolt positioner and
basic mounting hardware components are included with each satellite. Additional materials required to complete the
installation must be obtained separately. A material list can be compiled by reading through the instructions completely
prior to starting the installation.
CAUTION: For your protection and the safety of the product user, comply with all Caution and Warning Statements
within this document. All installation practices must comply with all applicable national and/or local electrical and
construction codes.
Foundation Construction
1. Prepare a hole for the foundation
Figure 1
Wood Form
See *Note
Concrete
Mounting Bolt w/ Hex Nuts
(Typical 4 Places)
2" (51mm) Max
6" (15.2cm)
Mounting Bolt
Positioner
30"
(76cm)
30"
(76cm)
2"
(51mm)
Taper
Plastic Cabinet Base Area
Metal Cabinet Base Area
Mounting Bolt Positioner
3" (76mm) Conduit - Field
(32 Stations Each)
3/4" (19mm) Conduit
Earth Ground
3/4" (19mm) Conduit
AC Power
and wiring conduit using the
minimum recommended dimensions
shown in Figure 1.
*Note: Refer to local electrical
codes for required depth of buried
wiring.
2. Trench to the foundation site as
required for each wiring run.
3. Position the straight and sweep
elbow conduit sections in the
foundation hole as shown. Tape
the conduit ends to seal out dirt.
Backll soil to form a 6" (15.2cm)
foundation depth. Conduit should
not extend more than 2" (51mm)
above the nished top surface of the
foundation.
4. Prepare the sides of the foundation
hole with wood forms.
5. Prepare the mounting bolt positioner
with the 5/16" x 4-1/2" bolts and
nuts (provided) as shown in Figure 1.
The threads should extend 2"
(51mm) from the top surface of the
bolt positioner.
6. Pour concrete into the formed
foundation hole. Press the mounting
bolt positioner into the concrete
until it is ush and level with the
foundation surface and aligned with
the conduit.
7. Finish the concrete with a level at
area (16" x 16" [41cm x 41cm]). To
prevent pooling at the base of the
pedestal, add a slight taper away
from the cabinet base contact area.
Allow the concrete to suciently
harden before continuing.
8. Remove the hex nuts from the
mounting bolts. Place the pedestal
on the pad ensuring all bolts pass
though the holes provided. Install a
at washer and a hex nut on each
bolt and tighten securely.