Operator's Manual
![](/manual/toro/30789/2-1-operator-s-manual-english/images/img-10.png)
Reach in and rotate by-pass valve on
transmission (Fig. 10) counterclockwise 1/2 to 1 turn.
Opening the valve opens an internal passage in the
pump, thereby bypassing transmission oil. Because
fluid is by-passed, the machine can be pushed
without damaging the transmission.
80"22 5",5&
*(41&
DUPE OLD FIGURE 10
Lift machine over shipping braces and push
machine off pallet.
Close by-pass valve by rotating it clockwise until it
is securely seated. Do not exceed 5 to 8 ft-lb (7 to 11
Nm). Do not start engine when valve is open.
!
Since battery is not filled with electrolyte or
charged, bulk electrolyte with 1.260 specific gravity
must be purchased from a local battery supply outlet.
&"1 2"'&38 (/((,&2 ".% 14##&1 (,/5&2
6)&. 6/1+*.( 6*3) &,&$31/,83& ".% $)"1(&
3)& #"33&18 *. " 6&,,5&.3*,"3&% 0,"$& 2/
("2&2 01/%4$&% 6)*,& $)"1(*.( $". %*22*9
0"3& *.$& 3)& ("2&2 "1& &70,/2*5& +&&0
/0&. ',"-& ".% &,&$31*$", 20"1+2 "6"8
'1/- 3)& #"33&18 / ./3 2-/+& "42&"
-"8 1&24,3 *' 3)& ("2&2 "1& *.)",&% .0,4(
$)"1(&1 '1/- &,&$31*$", /43,&3 #&'/1& $/.9
.&$3*.( 3/ /1 %*2$/..&$3*.( $)"1(&1 ,&"%2
'1/- #"33&18 0/232
Remove filler caps from battery and slowly fill each
cell until electrolyte is just above the plates. Install filler
caps.
Connect a 3 to 4 amp battery charger to the battery
posts. Charge the battery at a rate of 3 to 4 amperes for
4 to 8 hours.
When battery is fully charged, disconnect charger
from electrical outlet and battery posts.
Remove filler caps and slowly add electrolyte to
each cell until level is up to fill ring. Install fill caps.
!
Install battery and secure with hold down strap and
wing nuts (Fig. 2). Remove tape over ends of each
cable.
Slide the red, positive battery cable (Fig. 2) onto
positive battery post and tighten nut securely.
Slide the black, negative battery cable (Fig. 2) onto
negative battery post and tighten nut securely.
Coat both battery connections with either Grafo
112X (skin-over) grease, Toro Part No. 505Ć47,
petroleum jelly or light grease to prevent corrosion and
slide rubber boot over positive terminal
(Fig. 2).
Install the instrument cover and lock the two
latches.
Disengage seat support rod and pivot downward.
Pivot seat down and push lynch pin through seat latch
stud. Flip wire end of pin over latch stud (Fig. 11).
*(41&
8.$) 0*.
DUPE OLD FIGURE 11
!
/3& Ball joints are not required for all implements;
refer to implement operator's manual for requirements.
Thread jam nut fully onto right hand ball joint.
Screw ball joint into right hand push arm until
center of ball joint is 2Ć3/8 inches (60 mm) away from
front of push arm (Fig.12). Do not tighten jam nut.