In SolarEdge systems, due to the introduction of power optimizers between the PV
modules and the inverter, the short circuit current I
SC
and the open circuit voltage V
OC
hold different meanings from those in traditional systems.
For more information about the SolarEdge system’s string voltage and
current, refer to the
V
OC
and I
SC
in SolarEdge Systems Technical Note
,
available on the SolarEdge website at:
https://www.solaredge.com/sites/default/files/isc_and_voc_in_solaredge_
sytems_technical_note.pdf
To verify proper power optimizer connection:
Measure the voltage of each string individually before connecting it to the other
strings or to the inverter. Verify correct polarity by measuring the string polarity with
a voltmeter. Use a voltmeter with at least 0.1V measurement accuracy.
NOTE
Since the inverter is not yet operating, you may measure the string voltage
and verify correct polarity on the DC wires inside the Safety Switch.
For troubleshooting power optimizer operation problems, refer to
Power Optimizer
Troubleshooting
on page 65.
Chapter 2: Installing the Power Optimizers 25
Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.4