8.6. Commissioning
Important:-Repeater should not be connected to Power without
termination at the antenna ports. The termination can be carried out
either by the antenna connection as well as a dummy load or the 50
terminated connection of a measuring instrument (Power Meter,
Spectrum analyzer with appropriate PAD)
1. Plug the power cable to the AC mains and switch ON the unit.
2. Once the repeater is ON, the LEDs will not glow under normal condition.
3. The UL Align indication LED and DL align indication LEDs will blink for
adjusting the DL gain and UL gain automatically.
4. Review the intended coverage area according to the site installation plan.
Measure & monitor signal level at various points within and around the
perimeter of the coverage area with a mobile handset loaded with NET
engineering software and the SIM card of cellular operator.