1.5 Cautions in Construction Site
Heating and cooling should be thoroughly managed to maintain proper temperature and
humidity in the equipment room, and power supply should not be interrupted to prevent
delay of testing. All racks and equipment should be precisely set horizontally and vertically
and should be firmly installed.
Material Check
Based on the construction plan, thoroughly check the quantity of materials, whether they
conform to standards and if any of them are damaged. The AC/DC power cables,
fluorescent lamps, emergency lights, switches, and electrical conduits for light installation
should conform to standards and electrical properties.
Administrative Issues
y Site access: If the construction site is a restricted or limited access area, take proactive
measures so that construction personnel have no problem accessing the construction
site.
y Consultations: In relation to existing facilities, issues regarding connection work and
test scope should be consulted with the execution office and operation office before