Technical data
INSTALLATION INSTRUCTIONS
COMMISSIONING
25
THE FLUE DRAUGHT MUST BE NO LESS THAN 0.02’’WG
AND NOT MORE THAN 0.04’’WG (0.5mm TO 1.0mm). IF
EXCESSIVE FLUE DRAUGHT IS PRESENT, THEN A
STABILISER SHOULD BE FITTED IN THE FLUE SYSTEM.
8. ELECTRICAL TESTS
Electrical warning
THIS APPLIANCE IS SUPPLIED IN COMPONENT AND
SUB- ASSEMBLY FORM. WHILST THE SUB-ASSEMBLIES
THEMSELVES HAVE BEEN TESTED FOR ELECTRICAL
SAFETY AT REDFYRE, IT IS ESSENTIAL THAT THE WHOLE
APPLIANCE IS TESTED WHEN IT IS FULLY ASSEMBLED.
THIS WORK CAN ONLY BE UNDERTAKEN BY A
SUITABLY QUALIFIED ELECTRICIAN TRAINED IN THE
USE OF SPECIALISED EQUIPMENT. THE TEST MUST
INCLUDE;
– EARTH BOND CONTINUITY
– INSULATION RESISTANCE CHECK
– ELECTRICAL INSULATION FLASH TEST
IMPORTANT
IF THERE IS NO MAINS SUPPLY OR THE ABOVE TESTS
CANNOT BE CARRIED OUT, ENSURE THAT A WARNING
LABEL IS ATTACHED TO THE APPLIANCE STATING
THAT IT SHOULD NOT BE USED UNTIL ELECTRICALLY
TESTED BY A SUITABLY QUALIFIED ELECTRICIAN AND
INFORM THE CUSTOMER.