Operator Manual
SECTION 4 - MACHINE OPERATION
3121678 – JLG Lift – 4-15
Tie Down
WHEN TRANSPORTING THE MACHINE, THE BOOM MUST BE FULLY LOWERED INTO
THE BOOM REST.
1. Remove all loose items from the machine.
2. When transporting an 800S/860SJ a step-deck or single-
drop trailer is required. To avoid damage to the platform and
to obtain proper weight distribution, load the machine onto
the trailer as follows;
a. Position the boom over the front wheels.
DO NOT SWING THE BOOM WHIT THE MACHINE POSITIONED ON A TRAILER. TIPOVER
MAY RESULT
b. Place the boom in the stowed position with the turnta-
ble locked.
DRIVE AND STEER CONTROLLERS WILL BE REVERSED WHEN THE BOOM IS POSI-
TIONED OVER THE FRONT WHEELS.
c. Drive it onto the trailer with the boom and platform
positioned towards the truck.
3. Secure the chassis and the platform using straps or chains of
adequate strength.