Installation Guide
© 2016 IronRidge, Inc. All rights reserved. Visit www.ironridge.com or call 1-800-227-9523 for more information.
1
Installation
Tools Required: tape measure, chalk line, stud nder, roong bar, caulking gun, driver with 1/4” bit and 7/16”
hex socket.
Locate rafters and snap vertical and horizontal lines
to mark ashing locations. Drill 1/4” pilot holes, then
ll with roong manufacturer’s approved sealant.
Rafter
FM-FF2-MAN REV 1.0
2
Slide ashing, between 1st and 2nd course, so the
top is at least 3/4” above the edge of the 3rd course
and the bottom is above the edge of the 1st course.
3
Line up pilot hole with ashing hole and insert lag
bolt with bonded washer through ashing. Tighten
lag bolt until fully seated.
4
Place Cap onto ashing in desired orientation for
E/W or N/S rails and rotate 180 degrees. FlashFoot
2 is now installed and ready for IronRidge XR Rails.
5
Attach rails to either side of the open slot using
bonding hardware. Level rail at desired height, then
torque to 250 in-lbs (21 ft-lbs).
1st course
2nd course
3rd course
1st course
2nd course
3rd course
Structural Certication
Designed and Certied for Compliance with the International
Building Code & ASCE/SEI-7.
Water Seal Ratings
Water Sealing Tested to UL 441 Section 27 “Rain Test” and
TAS 100-95 “Wind Driven Rain Test” by Intertek.
Ratings applicable for composition shingle roofs having slopes
between 2:12 and 12:12.
UL 2703
Conforms to UL 2703 Mechanical and Bonding Requirements.