Verify that the gap between modules is less than 4mm on both sides of the front of the modules.
The gap in the back must be less than 5mm. If the gap is larger or varies side to side:
Confirm that both rack rails are properly located within the U volume.
Confirm that both rack rails are properly seated in the rack vertical column.
Verify that the top hanger for the rear of each rack rail is in the middle hole of the marked
U section.
Check the rack vertical columns for bending.
Confirm that the rack is an approved model. See “Location criteria” (page 10).
<4mm
4. Use your fingers to tighten the captive thumbscrew on each side of the module.
5. Repeat steps 2 through 4 to install the rest of the modules into the rack.
6. Once all modules are installed, you can remove the protective film from the front of the base
module.
22 Installing the library