HP StorageWorks 4x00/6x00/8x00 Enterprise Virtual Array Updating Product Software Guide XCS 6.110 (5697-6782, June 2007)

Figure 9 Controller Events (Initialized sys tem) window
d. Check the Severity eld to determine if any unexpected C ritical events
have occurred.
If Critical events have occurre d, p erform the steps outlined in the corrective action codes to
correct the problems. In some cases, it may be necessary to call your HP-authorized service
repr esentative to xtheproblem.
3. Verify that no changes to the storage system congura tion are in p rogress. For example, you should
not be in the process of creating a virtual disk. Conguration changes should not be made within 48
hours before beginning the upgrade. Proactive event notication can be used to alert you if a critical
event occurs d u ring the 48 hours before the upgrade.
NOTE:
The leveling process does not impact the upgrade. If leveling is in progress, the upgrade
can be performed. The leveling will be suspended during the upgrade and resumed
when the upgrade is complete.
Ensure you suspend any processes or applications that may change the storage system
conguration, such as backups and snapshot creation or deletion. Stop any HP Storage
System Scripting Utilit y scripts that are scheduled to run automatically.
Preparing an HP Continuous Access EVA environment for
upgrading
Estimated time to com plete: Varies depending on replication con guration
When to perform: As close as possible to the upgrade
When upgrading an EVA in an HP Continuous Access EVA environment, the following requirements must
be met. See HP StorageWorks Continuous Access EVA administrator guide for more information.
38
Pre-upgrade tasks