HP StorageWorks ESL9000 series tape library pre-installation site survey (April 2003)

Site Survey
13HP StorageWorks ESL9000 Series Tape Library Pre-installation Site Survey
Installation Requirements
Answer the following questions to ensure you are prepared to install the library.
Question
Site Ready?
Yes No
1. Are the correct number of dedicated host SCSI controllers available or on
order (typical installation is one SCSI controller for every two tape
drives)?
2. Has the SCSI ID scheme been reviewed with the customer?
3. Has the equipment location/arrangement been planned (power
source/host/library/cabling)?
4. Is service and traffic clearance provided (ceiling height/sprinkler
heads/cable racks)?
5. Has flooring tile cutout (for cabling, if required) been arranged?
6. Are SCSI cables available or on order?
7. Are SCSI connection kits for forward connectivity available or on order?
8. Are all SCSI cables of the proper length (for HVD 65.6 feet (20 m) or
less, for LVD 32.8 feet (10 m) or less without a SCSI extender module)?
9. Is a dedicated power source with the correct outlet available?
10. The library contains a redundant power supply. Are there two dedicated
power sources with correct outlets available?
11. Is a bypass switch planned?
Note: Only BBM type is approved for use with the library.
12. Is emergency power-off capability provided?
13. Is the power disconnect (breaker panel or bypass switch) located within
sight of the library (This is a National Electric Code requirement)?
14. Is the power source backed up by a generator UPS?
15. Are the temperature and humidity at the installation site controlled?