Installation Guide
x24
1-1/2" (3,8 cm)
x2
2 x 4 x 24" (5,1 x 10,2 x 61 cm)
RL
TEMPORARY SUPPORT
x2
2 x 4 x 75-1/4" (5,1 x 10,2 x 191,1 cm)
ECA
43
GABLE PANELS
PARTS REQUIRED:
x2 x2 x2
Primed
side up
Primed
side up
Primed
side up
1-3/4"
(4,5 cm)
1-1/2"
(3,8 cm)
1-1/2"
(3,8 cm)
1-1/2"
(3,8 cm)
Nails
RL (on at)
RL
RL
RL
ECA
ECA
You will build TWO assemblies. Orient RL and ECA on at as shown.
Place LEFT front gable panel as shown and secure using 1-1/2" nails.
2
1
BEGIN
3
4
5
Place second RL as shown. Place MIDDLE front gable panel ush to installed left panel. Ensure panels are ush.
Secure panel to installed RL using 1-1/2" nails. Place second RL as shown under MIDDLE panel and secure using
using 1-1/2" nails.
Place RIGHT front gable panel ush to installed middle panel. Ensure panels are ush.
Secure to RL using 1-1/2" nails.
Repeat Steps 1-4 to build second gable panel.
You have nished assembling your gable panels.
FINISH
6
Flush
Flush
Maintain
Flush
Maintain
Flush
1-3/4"
(4,5 cm)
1-1/2"
(3,8 cm)
Nails
1-1/2" (3,8 cm)
Nails