6583-P Call Us First! DO NOT RETURN TO STORE. For questions on assembly or for general inquiries, you may contact us in the following ways: Call customer service: 1-877-743-3400 AVOID THE WAIT! visit us online at help.backyardproducts.com Submit a help request Answers to frequently asked questions Live chat with an agent Did you enjoy building your shed? WANTE JOIN OUR TEAM AND MAKE UP TO $1,500/WEEK* h pl y si tb er ack all t s ya r din .
(This page intentionally left blank.
ASSEMBLY MANUAL A Backyard Products Company 16583-P 07/11/2019 BRAXTON 12' x 24' (365,7 x 731,5 cm) Actual floor size: 144" x 288" (365,7 x 731,5 cm) KEEP THIS MANUAL FOR FUTURE REFERENCE I M PO RTANT! READ INSTRUCTIONS THOROUGHLY PRIOR TO BEGINNING ASSEMBLY. BEFORE YOU BEGIN • BUILDING RESTRICTIONS AND APPROVALS Be sure to check with local building department and homeowners association for specific restrictions and/ or requirements before building.
IMPORTANT! AN OVERHEAD DOOR IS NOT AVAILABLE FROM YARDLINE! USE INSTRUCTIONS SUPPLIED WITH THE DOOR MANUFACTURER TO FRAME-IN YOUR FRONT WALL DOOR OPENING. **PROVIDE THIS PAGE TO THE DOOR MANUFACTURER** Additional trim required 7' (213,3 cm) Wall Height Threshold Required 12' (365,7 cm) Building Width Kit door opening is: 97" (246,3 cm) Wide x 69" (175,2 cm) High MAX.
TOOLS Required Optional ❑ Phillips Screwdriver ❑ Utility Knife ❑ Shingle Blades ❑ Drill / Driver ❑ 3/8" Drill Bit ❑ #2 Philips Drive Bit ❑ Caulk Gun ❑ Tool Belt/ Nail Pouch ❑ Tin Snips (for drip edge) ❑ Chalk Line ❑ Hammer ❑ Paint Tools ❑ Level ❑ Nail Gun ❑ Pencil ❑ Safety Glasses ❑ Tape Measure ❑ Ladder ❑ Square • gun nails ❑ Gloves or ❑ Sawsall Safety! Always use approved safety glasses during assembly.
ADDITIONAL MATERIALS THIS KIT DOES NOT INCLUDE ANY FOUNDATION OR FLOOR MATERIALS. See page 5 for a CONCRETE FOUNDATION option. See pages 6 to 13 for a WOOD FLOOR framing option. See the FLOOR LEVELING section on page 7 for recommended methods and suggested materials to properly level your framed floor, as this will vary depending on your specific site. COMPLETING YOUR SHED You will need these additional materials: PAINT FOR TRIM ........... 1 Gallon PAINT FOR SIDING (Gallons)................ 4 gal.
CONCRETE FOUNDATION If you choose to install your kit on a concrete slab refer to the diagram below. Attach the sill plates on the foundaton as shown, and continue on to page 13. Treated Sill Plate Sill Tape between sill plate and concrete. D D C 3-1/2" (8,9 cm) B A BLE DOUOORS D 4" (10,2 cm) Sill plates MUST be treated lumber.
WOOD FLOOR MATERIAL LIST (NOT INCLUDED) x29 TREATED 2 x 8 x 144" (5,1 x 20,3 x 365,8 cm) Treated Lumber x9 Minimum 5/8" thick panels.
WOOD FRAME FLOOR LEVELING OPTIONS There are multiple ways to level your floor frame. Our recommended leveling method is shown below. Leveling materials are not included in this kit. PREFERRED METHOD - 4x4 TREATED RUNNERS (Typical for 12' x 24' Kit) Runners are generally 12" (30,5 cm) from ends of floor frame and under seams. • 3" Screws angled into 4x4. • (2) at each point frame and 4x4 touch. Center this Runner Measurement to center of 4x4. 12" (30,5 cm) Fasteners for Frame to 4x4.
LEVEL AND SQUARE FLOOR FRAME Before attaching floor decking, it is important to level and square the floor frame. A level and square floor frame is required to correctly construct your shed. (Floor frame and decking not included.) BEGIN 1 See page 7 for the preferred floor leveling method. 2 Use a level and check that the frame is level before applying floor panels. 3 Check for frame squareness by measuring diagonally across corners. If the measurements are the same, the frame is square.
FLOOR FRAME PARTS REQUIRED: x29 x156 3" (7,6 cm) TREATED 2 x 8 x 144" (5,1 x 20,3 x 365,8 cm) BEGIN 1 Cut 25 floor joists down to 141". 2 Install floor joists 12 on center, as shown. Nail using (3) 3" nails at each location (Fig. A). Use (6) 3" nails at seams (Fig. B). Fig. A HINT: Fig. B 3" (7,6 cm) Nails 12" (30,5 cm) 141" (358,1 cm) 144" (365,8 cm) 3 144" (365,8 cm) Check the floor frame is square by measuring diagonally across the frame corners.
FLOOR PANELS PARTS REQUIRED: x183 2" (5,1 cm) 3/4" GAUGE BLOCK 3/4" x 48" x 96" (1,9 x 121,9 x 243,8 cm) x3 ¸1 GAA BEGIN Install a 48 x 96" panel flush to the outside edges of the floor frame. Use GAA gauge block to maintain 3/4” on floor joist. Secure panel using 2" nails 6" apart on edges and 12” apart inside panel.
FLOOR PANELS PARTS REQUIRED: 3/4" x 48" x 96" (1,9 x 121,9 x 243,8 cm) x3 x188 GAA 2" (5,1 cm) 3/4" GAUGE BLOCK 3 Cut one (1) 48 x 96" panel in half to get two 48 x 48" panels.These panels are cut so that all floor panels are staggered. 4 Install 48 x 48" panel flush to the outside edge of the floor frame and flush to the installed panel. Use GAA gauge block to maintain 3/4” on floor joist. Secure panel using 2” nails 6” apart on edges and 12” apart inside panel.
FLOOR PANELS PARTS REQUIRED: 3/4" x 48" x 96" (1,9 x 121,9 x 243,8 cm) x3 6 GAA x183 2" (5,1 cm) 3/4" GAUGE BLOCK Install last three 48 x 96" floor panels on frame, flush to the outside edge of the floor frame and flush to installed panels. Use GAA gauge block to maintain 3/4” on floor joists. Secure panels using 2" nails 6" apart on edges and 12" apart inside panel.
IMPORTANT! STOP! Check the floor frame is level after installing floor panels. Re-level if needed. • The floor should be used as a stable work surface for wall construction. HINT: • Organize your assembly procedure during the build process to avoid over-handling of the walls.
PARTS IDENTIFICATION AND SIZES WOOD SIZE CONVERSION CHART Letter part identification is stamped on some parts. Nominal Board Size RS RS Actual Size 2 x 4 ..............1-1/2" x 3-1/2" (3,8 x 8,9 cm) 1 x 4 .................3/4" x 3-1/2" (1,9 x 8,9 cm) RS 2 x 3 ..............1-1/2" x 2-1/2" (3,8 x 6,3 cm) 1 x 3 .................3/4" x 2-1/2" (3,8 x 6,3 cm) • Check these locations for part stamp. 12x24' GABLE 12' x 24' PARTS LIST WALL INVENTORY YOUR PARTS before you begin.
WALL PANELS & DOORS NOTE: Panel parts are not stamped with part identification.
DOOR PARTS LIST x4 FTA x2 AH x4 NSA 19/32" x 3-1/2" x 41" (1,5 x 8,9 x 104,1 cm) x4 x1 SPA 41-1/2" Door Stiffener (105,4 cm) x5 x4 OO XSA x1 ZJ 19/32" x 2-1/2" x 72" (1,5 x 6,3 x 182,9 cm) x2 ZP 19/32" x 3-1/2" x 72-3/8" (1,5 x 8,9 x 183,8 cm) 19/32" x 3-1/2" x 8-3/8" (1,5 x 8,9 x 16,5 cm) 19/32" x 2-1/2" x 26-5/8" (3,2 x 6,3 x 67,6 cm) 3/16 x 46-1/2 x 48” (0,5 x 118,1 x 121,9 cm) Pegboard Door Backer Board x2 3/8 x 1-5/8 x 69" (1 x 4,1 x 175,3 cm) 69" Door Stiffener (175,3 cm) 1 x 3 x
STOP! You have the opportunity to customize the look of your new Garage by putting the door and window assemblies in any of the locations shown below. = LOCATION INDICATORS Consider the property constraints, privacy requirements and utilization of best views when determining your side door and window locations. Your next step will be to build the door and window assemblies shown below.
DOOR FRAME PARTS REQUIRED: x34 x2 AL 3" (7,6 cm) 2 x 4 x 7" (5,1 x 10,2 x 17,8 cm) x2 QT 2 x 4 x 35" (5,1 x 10,2 x 88,9 cm) x2 YFA 2 x 4 x 68-1/2" (5,1 x 10,2 x 174 cm) x2 AI 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) BEGIN 1 Orient parts on edge on floor as shown. 2 Nail using (2) 3" nails at each location (Fig. A, Fig. B). Fig. B AI 25-1/2" (64,7 cm) 9-1/2" (24,1 cm) 3" (7,6 cm) Nails AI QT AL Fig. A 3" (7,6 cm) Nails YFA QT Flush Flush HINT: HEADER Pre-assembled Fig.
WINDOW FRAME PARTS REQUIRED: x36 x3 AL 3" (7,6 cm) 2 x 4 x 7" (5,1 x 10,2 x 17,8 cm) x6 AO 2 x 4 x 22-1/2" (5,1 x 10,2 x 57,1 cm) x3 PZA 2 x 4 x 38-1/2" (5,1 x 10,2 x 97,8 cm) x6 AI 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) BEGIN 1 Orient parts on edge on floor as shown. 2 Nail using (2) 3" nails at each location (Fig. A). 25-1/2" (64,8 cm) HINT: AL 7" (17,8 cm) Fig. A 12-3/4" (32,4 cm) AO AI AI PZA 38-1/2” (96,2 cm) 3 Repeat steps 1 - 2 to build two more window frames.
TP x4 2 x 4 x 20-1/2" (5,1 x 10,2 x 52,1 cm) x10 AI x104 2 x 4 x 68-1/2" (5,1 x 10,2 x 174 cm) x2 YFA 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) 20 68-1/2" (174 cm) YFA TP 96" (243,8 cm) You have finished building side wall -A-. FINISH RP 20-1/2" (52,1 cm) 96" (243,8 cm) TP Use (2) 3" nails at each connection and (4) 3" nails at seams. Toe-nail at seams.
SOLID WALL OPTION - FRAME PARTS REQUIRED: x2 x8 AI 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) BEGIN 1 Measure and mark locations for two studs AI in chosen 48" wall opening location. Place two AI in 48" wall opening. 2 Secure studs using (2) 3" nails at each location.
WINDOW FRAME PARTS REQUIRED: x36 Window Frame Pre-assembled x3 BEGIN 1 Measure and mark window frame at chosen 48" wall opening. 2 Install window frame using (2) 3" nails at each location.
DOOR FRAME PARTS REQUIRED: x16 x1 3" (7,6 cm) Door Frame Pre-assembled BEGIN 1 Measure and mark frame locations for door frame at chosen 48" wall opening location. Place door frame in 48" wall opening. 2 Check frame studs are at measurements shown and square at bottom. Secure door frame using (2) 3" nails at each location.
3/8 x 48 x 84" (1 x 121,9 x 213,4 cm ) x2 3/8 x 48 x 84" (1 x 121,9 x 213,4 cm ) GAA x2 3/4" GAUGE BLOCK 24 23-7/8" (60,6 cm) BEGIN HERE Page 25 1-1/2" (3,8 cm) You have finished building side wall -A-. 48" (121,9 cm) Flush 48" (121,9 cm) 12" (30,5 cm) 6" (15,2 cm) Primed Side UP Flush 48" (121,9 cm) Flush x384 48" (121,9 cm) Flush 2" (5,1 cm) Flush DO OR 23-7/8" (60,6 cm) To draw panels tight at seams angle nail.
3/8 x 23-7/8 x 84" (1 x 60,6 x 213,4 cm) 2 1 x42 25 Primed side UP 6" (15,2 cm) 12" (30,5 cm) 1-1/2" (3,8 cm) 23-7/8" (60,6 cm) 3-1/2" (8,9 cm) 3/4" Gauge Block BEGIN HERE 3/4" (1,9 cm) For squareness maintain 3/4" measurement along panel edge. Secure the panel using 2" nails 6" apart on edges and 12" apart inside panel. Use GAA as a gauge block to check the 3/4" side measurement on the wall stud. Place 23-7/8"x 84" end panel on frame with primed side facing up.
Primed side UP Secure the panel using 2" nails 6" apart on edges and 12" apart inside panel. 2 48" (121,9 cm) Place 48"x 84" window panel flush to the installed panel. Measure and locate the panel 1-1/2" above the top plate. Use the gauge block to check the 3/4" side measurement on the wall stud.
Primed side UP 48" (121,9 cm) Secure the panel using 2" nails 6" apart on edges and 12" apart inside panel. 2 3/4" (1,9 cm) Place 48"x 84" panel flush to the installed panel. Measure and locate the panel 1-1/2" above the top plate. Use the gauge block to check the 3/4" side measurement on the wall stud.
6" (15,2 cm) Secure the panel using 2" nails 6" apart on edges and 12" apart inside panel. 2 FRAGILE! 48" (121,9 cm) Place 48"x 84" door panel flush to the installed panel. Measure and locate the panel 1-1/2" above the top plate. Use the gauge block to check the 3/4" side measurement on the wall stud.
TP x4 x10 AI x104 2 x 4 x 68-1/2" (5,1 x 10,2 x 174 cm) x2 YFA 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) 20-1/2" (52,1 cm) 29 68-1/2" (174 cm) RP YFA 96" (243,8 cm) TP 96" (243,8 cm) TP Use (2) 3" nails at each connection and (4) 3" nails at seams. Toe-nail at seams.
x1 3/8 x 48 x 84" (1 x 121,9 x 213,4 cm ) x1 3/8 x 48 x 84" (1 x 121,9 x 213,4 cm) 30 48" (121,9 cm) 1-1/2" (3,8 cm) 48" (121,9 cm) 12" (30,5 cm) Flush You have finished building side wall -B-. FINISH 23-7/8" (60,6 cm) Flush Flush 48" (121,9 cm) 6" (15,2 cm) Primed Side UP x2 x374 To draw panels tight at seams angle nail. 48" (121,9 cm) Flush Install panels prime side up 1-1/2" above top plate using 2" nails 6" apart on edges and 12" apart inside panel.
BACK WALL FRAME PARTS REQUIRED: x10 x2 x44 AI x2 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) 3" (7,6 cm) SP 2 x 4 x 48" (5,1 x 10,2 x 121,9 cm) TP 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) At this time, add in any window, door or solid wall frames to the 48" frame openings. Refer to pages 21 - 23 for detailed window, door and solid wall frame instructions. NOTE : Wall shown is a generic image. See page 17 BEGIN 1 Orient parts on edge on floor as shown. 2 Nail using (2) 3" nails at each connection.
BACK WALL PANELS PARTS REQUIRED: x56 GAA 2" (5,1 cm) 3/4" GAUGE BLOCK 3/8 x 48 x 84" (1 x 121,9 x 213,4 cm ) x1 Refer to pages 25 - 28 for detailed window and door panel instructions. NOTE : Wall shown is a generic image. BEGIN 1 Place left 48"x 84" panel on frame and 1-1/2" across top of wall frame. Use GAA as a gauge block to check the 3/4" side measurement on the wall stud. 2 Secure the panel using 2" nails 6" apart on edges and 12" apart inside panel.
BACK WALL PANELS PARTS REQUIRED: x112 2" (5,1 cm) GAA 3/4" GAUGE BLOCK 3/8 x 48 x 84" (1 x 121,9 x 213,4 cm ) x2 NOTE: Wall shown is a generic image. 3 Place 2nd and 3rd 48"x 84" panels on frame as shown and flush with installed panel. Secure panel using 2" nails 6" apart along seam and 12" apart inside panel. 1-1/2" (3,8 cm) Flush 48" (121,9 cm) Flush 48" (121,9 cm) 6" (15,2 cm) Primed side UP 12" (30,5 cm) Flush To draw panels tight at seams angle nail.
FRONT WALL FRAME (Door Header) PARTS REQUIRED: x2 x26 CHC 3" (7,6 cm) 2 x 4 x 16-1/8 (5,1 x 10,2 x 41 cm) x2 TO x1 2 x 4 x 84" (5,1 x 10,2 x 213,4 cm) 7/16" x 3" x 96" (1,1 x 7,6 x 243,9 cm) OSB BEGIN 1 Place (1) TO and (1) CHC end-to-end. Center OSB on top of TO and CHC. OR DO 2 Place another TO and CHC on top of OSB, staggering the seams from the first TO and CHC. Nail using 3" nails in the pattern shown. 3 Flip header assembly over and nail as shown on the other side.
FRONT WALL FRAME PARTS REQUIRED: x36 x10 UY 2 x 4 x 6-1/2" (5,1 x 10,2 x 16,5 cm) 3" (7,6 cm) x20 x2 JYA 3" (7,6 cm) 2 x 4 x 23-7/16" (5,1 x 10,2 x 59,5 cm) x2 YFA 2 x 4 x 68-1/2" (5,1 x 10,2 x 174 cm) x1 x4 AI 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) Pre Assembled Header BEGIN 1 Orient parts on edge on floor as shown. Orient Pre Assembled Header on flat side. 2 Attach 1st end UY to AI door frame stud using (2) 3" screws (Fig. A). Attach 2nd end UY to 1st UY using (2) 3" nails (Fig. A).
FRONT WALL FRAME PARTS REQUIRED: x1 x34 3" (7,6 cm) SP 2 x 4 x 48" (5,1 x 10,2 x 121,9 cm) x2 AI x1 2 x 4 x 78-1/2" (5,1 x 10,2 x 199,4 cm) TP 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) 4 Orient parts on edge as shown. Secure using 3" nails as shown. SP Flush HINT: 3" (7,6 cm) Nails TP 48" (121,9 cm) Flush 96" (243,8 cm) AI AI 78 1/2" (199,4 cm) 11 3/4" (29,8 cm) 11 3/4" (29,8 cm) FINISH You have finished your front wall frame.
FRONT WALL PANELS PARTS REQUIRED: x23 GAA 2" (5,1 cm) 3/4" GAUGE BLOCK x1 3/8 x 11-1/4 x 48" (1 x 28,6 x 121,9 cm) BEGIN 1 Place one header panel onto wall frame as shown. 2 Use the guage block GAA to mark the 3/4" measurement on the wall stud. Locate the panel 1-1/2" above the top plate. Secure panels to frame using (2) 2" nails 6" apart. For squareness maintain 3/4" measurement along panel edge.
FRONT WALL PANELS PARTS REQUIRED: x22 GAA x1 3/8 x 11-1/4 x 48" (1 x 28,6 x 121,9 cm) 2" (5,1 cm) 3/4" GAUGE BLOCK 1 3 Place the second header panel onto wall frame as shown. 4 Locate the panel 1-1/2" above the top plate. Secure panels to frame using 2" nails 6" apart. Flush Primed side UP 6" (15,2 cm) To draw panels tight at seams angle nail.
FRONT WALL PANELS PARTS REQUIRED: x2 TP x4 Temporary Support 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) Offset Offset LEFT x1 3" (7,6 cm) x86 2" (5,1 cm) RIGHT 3/8 x 23-7/8 x 84" (1 x 60,7 x 213,4 cm) x1 3/8 x 23-7/8 x 84" (1 x 60,7 x 213,4 cm) 5 Place 23-7/8" x 84" panels 1-1/2" above frame flush to installed panels. Nail left and right panels using 2" nails 6" apart along edges and 12" apart inside panel. 6 Stack and attach (2) TP as temporary braces using 3" screws into wall framing as shown.
SIDE WALL -A- INSTALLATION PARTS REQUIRED: x2 x42 TP 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) x4 BEGIN 1 3" (7,6 cm) Temporary Brace Center side wall -A- on floor. x50 2" (5,1 cm) 3" (7,6 cm) TP 3" (7,6 cm) Screw ENSURE 1-1/2" MEASUREMENT IS AT TOP. 2 Use TP as temporary bracing. Secure using (2) 3" screws. 1-1/2" (3,8 cm) CE 2 NT (731,588" ER c ON m) FL OO D O O R R 3 Nail along bottom of side wall panels using 2" nails 6" apart (Fig. A). Fig. A Angle nail to hit floor frame (Fig. B).
BACK WALL INSTALLATION PARTS REQUIRED: x18 3" (7,6 cm) x26 x2 2" (5,1 cm) 2" (5,1 cm) x13 1-1/2" (3,8 cm) BEGIN 1 Center back wall on floor. 1-1/2" (3,8 cm) BACK WALL D O O R ENSURE 1-1/2" MEASUREMENT IS AT TOP. 2" (5,1 cm) Screw 2 Secure top and bottom of back wall using (1) 2" screw into top and bottom plate (Fig A). BE SURE TOP OF WALL FRAMES ARE FLUSH. Fig. A Flush BACK WALL Same Measurement Nail side wall panel to back wall stud using 1-1/2" nails 6" apart (Fig B). Fig.
SIDE WALL -B- INSTALLATION PARTS REQUIRED: x1 x13 TP 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) x2 x38 1-1/2" (3,8 cm) Temporary Brace 2" (5,1 cm) x46 3" (7,6 cm) 2" (5,1 cm) BEGIN 1 Center side wall -B- on floor. ENSURE 1-1/2" MEASUREMENT IS AT TOP. CE 1-1/2" (3,8 cm) NT ER ON FL OO R OR DO 2 Secure top and bottom of side wall using (1) 2" screw into top and bottom plate (Fig A). BE SURE TOP OF WALL FRAMES ARE FLUSH.
FRONT WALL INSTALLATION PARTS REQUIRED: x4 2" (5,1 cm) BEGIN 1 Remove temporary brace. Center front wall on floor as shown. OR DO ENSURE PANEL CORNERS ARE FLUSH. 2 Secure top and bottom of wall using (1) 2" screw into top and bottom plates (Fig. A). Flush 2" (5,1 cm) Screw Flush Flush 2" (5,1 cm) Screw Fig.
FRONT WALL INSTALLATION PARTS REQUIRED: x8 3 x8 x26 2" (5,1 cm) 3" (7,6 cm) 1-1/2" (3,8 cm) Nail lower edge of panels to floor using 2" nails 6" apart. Angle nail to hit floor frame (Fig. C). 2" (5,1 cm) Nails 6" (15,2 cm) Angle nail to hit floor frame. 6" (15,2 cm) 1-1/2" (3,8 cm) Nails Fig. C m) 6" 5,2 c (1 4 Nail front wall panels to side wall studs using 1-1/2" nails 6" apart (Fig. D). Fig. D Secure front wall to floor using 3" nails (Fig. E).
EAVE WALL SQUARING PARTS REQUIRED: x3 x8 TP 3" (7,6 cm) Temporary Brace 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) BEGIN 1 Assemble two TP’s with edges flush to 144” length using (3) 3” screws as shown (Fig. A). At the middle stud (Fig. C) install brace flush under top plate at each end using (1) 3” screw (Fig. A). 2 Measure from end of brace (inside wall panel) 61” (154,9 cm) and mark a vertical line on brace (Fig. A and B). 3 Locate a TP in approximately the position shown in Fig.
WALL DOUBLERS PARTS REQUIRED: x2 x2 x6 x96 STL 3" (7,6 cm) 2 x 4 x 44-1/2" (5,1 x 10,2 x 113 cm) UL 2 x 4 x 92-5/8" (5,1 x 10,2 x 235,3 cm) TP 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) BEGIN 1 Orient parts on top of wall frames. Secure from top using (2) 3" nails spaced every 24" (Fig. A). 92-5/8" (235 cm) 3" (7,6) cm Nails Fig.
RAFTERS PARTS REQUIRED: x24 x1 x26 2" (5,1 cm) 6 x 24" (15,2 x 60,9 cm) TP 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) Temporary Support XYA 2 x 4 x 81-7/8" (5,1 x 10,2 x 208 cm) BEGIN 1 x288 Place two rafters (XYA) in the corner of back and side walls as shown. Rafters contact at peak. You will build TWO rafter assemblies with ONE gusset. You will build ELEVEN rafter assemblies with TWO gussets. 144" (365,8 cm) Fit base of rafters in corners of back wall.
RAFTER INSTALLATION PARTS REQUIRED: x11 x48 x2 2-Gusset Pre assembled 3" (7,6 cm) 1-Gusset Pre assembled BEGIN 1 On both 24’ walls, measure and mark center-locations for all 2-Gusset Rafters (Fig. A). 2 Install all 2-Gusset Rafters using (2) 3" screws angled into top plate as shown in (Fig. B). 3 Install both 1-Gusset Rafters flush to the outside edge of wall panel, using (1) 3” screw (Fig. C).
GABLE PANELS PARTS REQUIRED: x2 x24 x4 TTA 2 x 4 x 23" (5,1 x 10,2 x 58,4 cm) x2 x2 BEGIN 1 Place center gable panel on TTA primed side up as shown. Nail panel using 1-1/2" nails. 2 Place left and right panels on TTA flush to center gable panel. Nail panel using 1-1/2" nails.
GABLE PANELS PARTS REQUIRED: x8 x96 x2 Gable Assembly 4 Center gable assembly on back wall. Nail using 2" nails 6" apart as shown. 5 From inside, toe-nail gable connectors TTA using 3" nails. Flush & Center at peak 6" (15,2 cm) 6" (15,2 cm) 2" Nails (5,1 cm) 6 3" Screws (7,6 cm) Repeat STEPS 4 - 5 to install gable panels at opposite side. FINISH You have finished installing your gable panels.
ROOF PANELS PARTS REQUIRED: GAA x1 x1 48" x 39-3/4" (121,9 x 101,0 cm) x4 2" (5,1 cm) 3/4" GAUGE BLOCK 39-3/4" x 96" (101,0 x 243,8 cm) Roof panels may cause serious injury until securely fastened. Note: all roof panels need to be installed with the rough side up (painted grid lines). Measure up 33-3/8" from the bottom of front, 3rd, 7th, 11th and back rafters. Mark a line across each rafter (Fig A). BEGIN 1 Place the 47-7/8" x 39-3/4" panel flush to the rafter marks.
ROOF PANELS PARTS REQUIRED: x1 x1 48" x 39-3/4" (121,9 x 101,0 cm) 4 x4 GAA 2" (5,1 cm) 3/4" GAUGE BLOCK 39-3/4" x 96" (101,0 x 243,8 cm) Place 2nd 96" x 39-3/4" roof panel flush to the rafter marks and flush to the installed panel. Use the 3/4" gauge block GAA to center panel over the rafter (Fig B). Secure panel using (2) 2" nails in the corners. Panel will overhang 6-1/2" (Fig D). 3/4" (1,9 cm) Fig. B Gauge Block Two Nails Panel overhang 5 Fig.
ROOF PANELS PARTS REQUIRED: x58 x1 7/16 x 48 x 96" OSB (1,1 x 121,9 x 243,8 cm OSB) 6 2" (5,1 cm) GAA Keep spacing between the center of each rafter and secure using (2) 2" nails into each rafter (Fig. F). Fig.
ROOF PANELS PARTS REQUIRED: x264 x2 3/4" GAUGE BLOCK 7/16 x 48 x 96" OSB (1,1 x 121,9 x 243,8 cm OSB) 8 2" (5,1 cm) GAA Place 2nd upper 48" x 96" panel flush to installed panels. Two Nails Use the 3/4" gauge block GAA to center panel over the rafter (Fig B). Secure panel using (2) 2" nails in the corners as shown. Repeat STEP - 8 to install 2nd upper 48" x 96" panel. Panel should be 3/8" from the outside edge of the end rafter (Fig. E).
BACK WALL GABLE TRIM PARTS REQUIRED: x1 x24 2" (5,1 cm) YRL 19/32" x 3-1/2" x 88-1/2" (1,5 x 10,2 x 224,8 cm) x1 YRR 19/32" x 3-1/2" x 88-1/2" (1,5 x 10,2 x 224,8 cm) BEGIN 1 Install back gable trim YRL and YRR flush to top of roof panel and flush at peak using 2" finish nails as shown (Fig. A, Fig. B). Flush Fig. B Flush to top of panel Roof Panel YRL YRR 2" Finish Nails (5,1 cm) Fig. A CE SPA SPA LY CE EN V DE FINISH You have finished installing your back gable trim.
FRONT GABLE OVERHANG PARTS REQUIRED: x1 x12 ULL 2" (5,1 cm) 19/32" x 3-1/2" x 88-1/8" (1,5 x 10,2 x 223,8 cm) x1 ULR x2 19/32" x 3-1/2" x 88-1/8" (1,5 x 10,2 x 223,8 cm) TQA Angled End 2 x 4 x 88-1/8" (5,1 x 10,2 x 223,8 cm) BEGIN 1 Place ULL on top of TQA. Ensure parts are flush along edge and at angled end. Secure using 2" screws as shown (Fig. A, Fig. B).. Flush Fig. A Flush TQA Primed side DOWN Flush ANGLED END ULL Primed side DOWN Fig.
FRONT GABLE OVERHANG PARTS REQUIRED: x10 x10 2" (5,1 cm) 3" (7,6 cm) Left Overhang Assembly x1 Right Overhang Assembly x1 BEGIN 1 Install front left and right overhang assemblies flush to top of roof panel using (5) 2" finish nails and flush at peak (Fig. A, Fig. B). Fig. A Flush Fig. B ULL 2" (5,1 cm) Finish Nails 2 Working from inside, screw through roof rafter into gable overhang 2 x 4 TQA. Use (5) 3" screws spaced apart evenly as shown.
EAVE SOFFITS PARTS REQUIRED: x10 x80 ROS 1" (2,5 cm) 4/4 x 5-1/2" x 57-15/16" (2,5 x 14,0 x 147,2 cm) BEGIN 1 Install 1st ROS under roof panel, tight against wall panels and flush to back edge of gable overhang using 1" screws (Fig. A). 2 Install ROS same as first ROS; with ends flush to the installed soffit boards. 1" Screws (3,2 cm) Fig. A Flush Tight against wall ROS x5 Space screws evenly ROS x5 3 Repeat STEPS 1 - 2 on opposite side. FINISH You have finished installing your soffits.
EAVE FASCIA PARTS REQUIRED: x2 x44 2" (5,1 cm) 3/8 x 3 x 43-1/8" (1 x 7,6 x109,5 cm) x6 3/8 x 3 x 83-1/2" (1 x 7,6 x 212,1 cm) BEGIN 1 Install 1st 83-1/2" fascia board flush to roof panel and flush to edge of 2x4 gable overhang using 2" finish nails (Fig. A). 2 Install two additional 83-1/2" and one 43-1/8" fascia boards as shown. Fig.
BACK GABLE TRIM ENDS PARTS REQUIRED: x4 BEGIN 1 Fasten back gable trim ends to ROS using (1) 3" screw on both sides (Fig. A). Fig. A Gable trim 3" (7,6 cm) Screw ROS FINISH You have finished securing your gable trim ends.
FRONT GABLE FASCIA PARTS REQUIRED: x12 2" (5,1 cm) x2 YRL 19/32" x 3-1/2" x 88-1/2" (1,5 x 10,2 x 224,8 cm) x2 YRR 19/32" x 3-1/2" x 88-1/2" (1,5 x 10,2 x 224,8 cm) BEGIN 1 Install YRL and YRR flush to the top of the gable (Fig. A). Use 2" finish nails spaced evenly as shown (Fig. B). Fig. A YRL Flush 2" Finish Nails (5,1 cm) YRR Flush Flush CE VE DE CE SPA SPA NLY Fig. B FINISH You have finished installing your front gable trim.
CORNER TRIM PARTS REQUIRED: x8 x64 2" (5,1 cm) 3/8" x 3" x 83-1/2" (1 x 7,6 x 212,1 cm) BEGIN 1 Place 83-1/2" corner trim on front wall flush under gable panel corner notch and flush along side wall panel edge (Fig. A, Fig. B). Secure using 2" finish nails evenly spaced (Fig. B, Fig. C). 2 Fit 2nd 83-1/2" corner trim flush to top of installed front corner trim and along edge (Fig. A, Fig. B). Secure using 2" finish nails evenly spaced (Fig. B, Fig. C). Fig. B Fig. A Flush Flush Flush Fig.
DOUBLE DOORS PARTS REQUIRED: x4 x4 x36 FTA 19/32" x 3-1/2" x 8-3/8" (1,5 x 8,9 x 16,5 cm) 3/4" (1,9 cm) Double Door NSA 19/32" x 3-1/2" x 41" (1,5 x 8,9 x 104,1 cm) x2 BEGIN 1 On outside of double door, locate FTA flush to edge of window opening and upper door trim, as shown. Secure FTA from back side (inside) of door using 3/4" screws. 2 On outside of double door, locate NSA flush to edge of each FTA, as shown. Secure NSA from back side (inside) of door using 3/4" screws.
DOUBLE DOORS PARTS REQUIRED: x40 3/4" (1,9 cm) x2 4 Place window in window opening on inside of door. Seal window using high-quality exterior caulk before installing. Secure window using 3/4" screws. You must caulk completely around window frame to validate your warranty. Use a paintable exterior rated caulk. 3/4" (1,9 cm) Screws 5 ide Ins Secure upper and lower horizontal door trim from back using 3/4" screws at locations shown.
DOUBLE DOORS PARTS REQUIRED: x36 x4 OO 2" (5,1 cm) 69" Door Stiffener (175,3 cm) x4 SPA 41-1/2" Door Stiffener (105,4 cm) 6 Place door OO 1-1/2" down from top of door panel and at 3/4" mark. Secure OO using (5) 2" screws. 7 Place (2) parts SPA at measurements, square and flush to installed OO. Secure each SPA using 2" screws.
DOUBLE DOOR HINGES PARTS REQUIRED: x12 x4 x12 Washer 2" (5,1 cm) 5/16" (0,8 cm) BEGIN 1 Locate hinges on front side of LEFT double door as shown. Center hinges on door trim and flush hinge at edge of trim. Pre-drill lag screw location using a 1/8" drill bit (Fig. A). 2 Secure hinges using 2" lag screws with washers (Fig. B). Press edge of hinge flush to edge of trim DOOR TOP VIEW Door trim edge 2" (5,1 cm) Lag Screw and Washer Fig. B Flush Center Fig.
DOUBLE DOOR HINGE BOARDS x10 PARTS REQUIRED: x2 2" (5,1 cm) ZP 19/32" x 3-1/2" x 72-3/8" (1,5 x 8,9 x 183,8 cm) BEGIN 1 Measure up 72-3/8" from the bottom of panel on both sides and mark. 2 Install ZP at the 72-3/8" mark and flush to panel (Fig. A) door opening using 2" finish nails as shown (Fig. B, C). Fig. B ZP ZP 72-3/8" (183,8 cm) 2" Finish Nails Level Fig. C Fig. A Flush ZP FINISH You have finished installing your hinge boards.
DOUBLE DOORS PARTS REQUIRED: Pre-Assembled Double Doors x8 x2 XSA 2" (5,1 cm) Temporary Support 1 x 3 x 69-3/4" (2,5 x 7,6 x 177,2 cm) BEGIN 1 Set double doors facing up. Separate doors 3/8" apart and flush at top. 2 Place XSA across top and bottom of doors and fasten using 2" screws.
DOUBLE DOORS PARTS REQUIRED: x1 TP Temporary Support 2 x 4 x 96" (5,1 x 10,2 x 243,9 cm) x12 3" (7,6 cm) Lag Screw x12 Washer 5/16" (0,8 cm) x4 3" (7,6 cm) Wood Screw 3 Attach temporary support TP as a ledger board 1" below top of floor decking using 3" wood screws (Fig. A). 4 Center doors in door opening (Fig. B). Pre-drill holes for lag screws using a 1/8" drill bit. Screw hinges into wall supports using 3" lag screws with washers as shown. Fig.
DOUBLE DOOR WEATHERSTRIP PARTS REQUIRED: x1 x5 Weatherstrip 3/8" x 1-5/8" x 69" (1 x 4,1 x 175,3 cm) BEGIN 1 With left door closed and working from inside, place 1-5/8" x 69" weatherstrip flush to top (Fig. A) and edge (Fig. B) of OO. 2 Flush weatherstrip to edge of OO (Fig. B). Secure weatherstrip using 1" screws into door panel (Fig. B). Weatherstrip Fig. B Flush Fig.
DOUBLE DOOR WEATHERSTRIP PARTS REQUIRED: x2 3 x20 2" (5,1 cm) XSA 1 x 3 x 69-3/4" (2,5 x 7,6 x 177,2 cm) Install two XSA weatherstrips using 2” finish nails, as shown (Fig. A). Fig. A Door Flush Wall Frame XSA TOP VIEW INSIDE OF DOOR 2" (5,1 cm) Finish Nails x20 XSA XSA Flush Flush FINISH You have finished installing your weatherstripping.
DOUBLE DOOR REINFORCEMENT PARTS REQUIRED: x2 BEGIN 1 x36 3/16 x 46-1/2 x 48” (0,5 x 118,1 x 121,9 cm) Pegboard Door Backer Board Fig. A Place 46-1/2" x 48" backer board flush to door frame (Fig. A, Fig. B). 1-1/4" Screws (3,2 cm) Secure backer board using 1-1/4" screws into door frame as shown. INSIDE OF DOOR Fig. B Flush Flush INSIDE OF DOOR 2 1-1/4" (3,2 cm) Flush Flush Flush Repeat STEP 1 to install backer board on other door frame.
DOUBLE DOOR HARDWARE PARTS REQUIRED: x2 BEGIN Handles come packed with lag screws or hex bolts. Customer can use either option. 1 Measure and mark locations of door handles as shown. Pre-drill for lag screws using an 1/8" drill bit. 2 Fasten handles using screws provided (Fig. A). 1-3/4" (4,4 cm) 1-3/4" (4,4 cm) 35-3/4" (90,8 cm) Lag Screw 2" (5,1 cm) Fig.
DOUBLE DOOR HARDWARE PARTS REQUIRED: x1 x6 1-1/2" (3,8 cm) Latch and screws BEGIN 1 Measure and mark both locations for door latch parts as shown. Pre-drill holes for screws using an 1/8" drill bit. 2 Install door latch and strike plate as shown. Strike plate is flush to the outside edge of door (Fig. A). Center Center 39-1/2" (100,3 cm) Flush Fig. A FINISH You have finished installing your decorative door latch.
DOUBLE DOOR HARDWARE PARTS REQUIRED: 5/16" (0,8 cm) Drill Bit x2 x8 1" (2,5 cm) BEGIN 1 Place top bolt onto OO in open position with bolt ends 3/8" (1 cm) down from frame. Bolt is open when loop is contacting base (Fig A). Mark and pre-drill holes for screws. 2 Install bolt using screws supplied and drill 5/16" (0,8 cm) hole deep enough for bolt to slide into. 3 Place bottom bolt onto OO in open position with bolt ends 1/2" (1,3 cm) up from floor. Bolt is open when loop is contacting base (Fig B).
GABLE & DOUBLE DOOR FRONT TRIM PARTS REQUIRED: x2 x2 x2 x44 HAB 19/32" x 3-1/2" x 53" (5,1 x 10,2 x 134,6 cm) 2" (5,1 cm) ERL 19/32" x 3-1/2" x 69-15/16" (5,1 x 8,9 x 177,6 cm) ERR 19/32" x 3-1/2" x 69-15/16" (5,1 x 8,9 x 177,6 cm) BEGIN 1 Install two HAB over door trim using 2" finish nails level and flush to top door hinge board (Fig. A). HAB HAB CENTER Flush LEVEL 2" (5,1 cm) Finish Nails Fig.
COLLAR TIES PARTS REQUIRED: x5 x30 TP 3" (7,6 cm) 2 x 4 x 96" (5,1 x 10,2 x 243,9 cm) BEGIN 1 Locate collar tie TP on back of 3rd rafter from the door wall as shown. Check collar tie is level and flush to roof panel. 2 Secure collar tie to rafter using (3) 3" nails at each end. 3" (7,6 cm) Nails Roof panels hidden for clarity. 11th Rafter Flush 9th Rafter 7th Rafter 5th Rafter HINT: For best appearance, install collar tie on back side of rafter.
STOP CHOOSE YOUR UNIVERSAL DOOR OPENING DIRECTION Right Hand or Left Hand RIGHT HAND DOOR UNIVERSAL DOOR SWINGS OPEN TO THE RIGHT LEFT HAND DOOR UNIVERSAL DOOR SWINGS OPEN TO THE LEFT 78
SINGLE DOOR PARTS REQUIRED: x5 3" (7,6 cm) UNIVERSAL DOOR Right x1 BEGIN Fig. A 1 Carefully cut bottom wall frame 2 x 4 flush with door frame using a saw (Fig. A). Be careful not to cut into floor panel! 2 Center door in wall panel opening. Hold door in position and keep level. 3 Measure Gap (Fig. B) between door trim and wall panel as shown. Hold door in position and keep level. Hinge-board must overhang wall panel at measurement shown (Fig. C).
SINGLE DOOR - TRIM PARTS REQUIRED: x2 19/32" x 3 x 26-5/8" (1,5 x 7,6 x 67,6 cm) x1 x1 x28 AH 3/4" (1,9 cm) x9 2" (5,1 cm) GEA 19/32" x 3 x 39-3/8" (1,5 x 7,6 x 100 cm) ZJ 19/32" x 3 x 72" (1,5 x 7,6 x 183 cm) BEGIN 1 Attach upper and lower horizontal door rail AH using (4) 3/4" screws from inside of door (Fig. A, B). 2 Reinforce the door trim using 3/4" screws through door panel into trim (Fig. A). Locate screws as shown in Fig. B.
SINGLE DOOR STIFFENER & WEATHER STRIP PARTS REQUIRED: x1 x2 x20 OO x6 2" (5,1 cm) 2" (5,1 cm) 69" Door Stiffener (175,3 cm) XSA 1 x 3 x 69-3/4" (2,5 x 10,2 x 177,2 cm) BEGIN 1 Center OO vertically on door in the door opening (Fig. A) 1" from edge of door (Fig. B). Secure using (6) 2" screws through outside trim into OO (Fig. B) Fig. A Center OO in door opening. Fig.
SINGLE DOOR HARDWARE PARTS REQUIRED: x2 1-1/2" (3,8 cm) x1 1/2" (13 mm) Drill Bit 1/4" (6 mm) Drill Bit BEGIN 1 Measure and mark location of hole on outside of right door as shown (Fig.A). Pre-drill pilot hole using 1/4" dril. Pre-drill through hole using 1/2" drill. Keep drilled hole square to trim to avoid breaking edge of door stiffener. Fig. A TOP VIEW 1-3/4" (4,4 cm) 35-3/4" (90 cm) 1-3/4" 3,8 cm 2 Insert handle in hole and secure using 1-1/2" (3,8 cm) screws (Fig. B).
WINDOWS AND WINDOW TRIM PARTS REQUIRED: x12 x3 BEGIN 1 Seal window using high-quality exteriorgrade caulk before installing (Fig. A). 2 Attach window using (4) 1-5/8" screws as shown. Ensure window is level. 3 Repeat Steps 1-2 to install other windows. Fig. A 1-5/8" (4,1 cm) Screws Caulk behind frame near edge.
WINDOW TRIM PARTS REQUIRED: x6 x6 5 x48 ROR 2" (5 cm) 19/32" x 2-1/2" x 28-1/2" (1,5 x 6,3 x 72,4 cm) AZ 19/32" x 2-1/2" x 30-1/8" (1,5 x 6,3 x 76,5 cm) Place trim pieces ROR and AZ centered on window frame (Fig. A). Attach using 2" finish nails. Nail into window frame and studs behind. You must caulk completely around window frame to validate your warranty. Use a paintable exterior rated caulk. CENTER OF WINDOW ROR 23-1/8" (58,7 cm) AZ Fig.
GABLE VENTS PARTS REQUIRED: x8 1" (2,5 cm) Vent x2 BEGIN 1 Position VENTS in front and back gables as shown and secure using 1" screws. (Seal vent using high-quality paintable exterior caulk.) FINISH 2 Your gable vents are now installed.
HOOK & EYE PARTS REQUIRED: x2 Eye ¸1 Hook BEGIN 2 Install hooks 2" up from bottom edge of panel (Fig.A). Swing door open to locate eye and install as shown. 2" Fig. A Eye Hook FINISH You have finished installing your hook and eye. 86 Install hook 2" up from bottom of panel edge into solid 2x4 framing.
PAINT & CAULK - NOT INCLUDED - • Use acrylic latex caulk that is paintable. Caulk at all horizontal and vertical seams, between the trim and walls, and all around the door trim. • Use a high quality exterior acrylic latex paint. When painting your building, there are a few key areas that can be easily overlooked that must be painted: • Bottom edge of all siding and trim • Inside of doors and all 4 edges Note: Prime all un-primed exterior wood before painting.
SHINGLES - NOT INCLUDED • Follow directions provided by manufacturer and these instructions. Familiarize yourself with a 3-Tab Shingle. Notch SHINGLE NAIL PATTERN 1" (2,5 cm) 1/2" (1,3 cm) Sealing Strip Notch 1" (2,5 cm) Half A Rain Slot Full Rain Slot NAILS NEVER DRIVE FASTENERS INTO OR ABOVE SEALING STRIPS. BEGIN 1 Install first starter row upside down and color up with a 1" overhang at back and bottom of roof panel. Use (4) nails per shingle.
SHINGLES continued... 2 2 Beginning at front of shed, install first row of shingles with notch at 1" past roof edge or flush with drip edge. Roof Deck FRONT OF SHED 1" (2,5 cm) Notch - or - BACK OF SHED Flush with starter row. Drip Edge Flush with starter row. Notch 3 Install second row of shingles flush at top of first row's rain slots. Ensure 1" overhang or flush to drip edge at front, stagger each row. FRONT OF SHED BACK OF SHED Bend in roof 1" (2,5 cm) Notch Flush with rain slots.
SHINGLES continued... 5 Continue installing rows of shingles to the peak. At the peak make sure there is a maximum of 5" or less to the rain slot, as shown below. If shingles overlap at ridge cut to peak with a utility knife. Cut Off. 5" (12,7 cm) MAX. CUT Top of rain slot. 5" (12,7 cm) or less. • If more than 5" to rain slot you must install another row of shingles. 6 Repeat steps 1 - 7 to shingle the opposite side of your roof. Trim shingles at ridge.
SHINGLES - RIDGE CAP • You will finish off the top of the roof with a ridge cap made from shingles. Cut shingles into THREE pieces. Hint: Use cut-off pieces first. 2" (5,1 cm) 2" (5,1 cm) 2" (5,1 cm) 2" (5,1 cm) 2" (5,1 cm) 2" (5,1 cm) Score shingle, then snap-off angled cut. Weather Seal 2 Top of slot. 48 to 52 Pieces Install first ridge cap flush to shingles at front, as shown. (1) Nail per side through weather seal. Flush 3 Install second ridge cap 5" back, as shown.
SHINGLES - RIDGE CAP continued... 4 Continue installing ridge cap to back of roof. BEGIN 5 Make sure there is 4" between the shingle-color and edge of shingles. 4" (10,2 cm) 6 Trim cap off flush to shingles When you have 4" minimum of shingle color cut one piece to cap your roof. Cut at top of rain slot. Cap 7 Install flush to shingles. Flush to shingles (2) Nails per side. FINISH 8 You have finished your ridge cap.
(This page intentionally left blank.
(This page intentionally left blank.
LIMITED CONDITIONAL WARRANTY* Backyard Storage Solutions, LLC warrants the following: 1. Every product is warranted from defects in workmanship and manufacturing for 1 year. 2. All accessories, hardware and metal components are warranted for 2 years. 3. All Oriented Strand Board (OSB) is warranted for 2 years 4. Siding and Trim is warranted for 10 years. 5. Solar Shed windows are warranted for 1 year. 6. Cedar lumber is warranted for 15 years. 7. Preserved Pine is warranted for 10 years. 8.