Installation Guide
Table Of Contents
- Dell EMC PowerSwitch N3200-ON Series Installation Guide
- About this guide
- N3200-ON Series switch
- Site preparations
- N3200-ON Series switch installation
- Unpack
- Rack or cabinet hardware installation
- Ground cable
- Desktop
- N3208PX-ON ceiling-mount switch installation
- N3208PX-ON wall-mount switch installation
- Standard bracket two-post installation
- Two-post five-inch-offset switch installation
- Two-post flush-mount switch installation
- Wall- or ceiling-mount switch installation
- One RU ReadyRails installation
- Optics installation
- Switch start-up
- After switch placement
- Switch replacement
- External power adapter
- Power adapter holder assembly
- Wall or ceiling installation
- DIN rail installation
- Single-EPA and switch four-post installation
- Single-EPA and switch two-post center-mount installation
- Single-EPA and switch two-post front-mount installation
- Dual-EPAs two-post front-mount installation
- Dual-EPAs two-post center-mount installation
- Power supply
- Fans
- Management ports
- Installation using ONIE
- Specifications
- Dell EMC support
1. Locate the ceiling mount tray, ceiling anchors, and 32 mm (1.26 in) M4 screws that are included with your switch.
2. Using the ceiling mount tray as a template, hold the tray on the ceiling where you want to mount the switch. Mark the four
mounting hole locations with the pencil.
3. Drill four holes into the ceiling at the pencil marks.
4. Install the four ceiling-anchors into the ceiling.
5. Attach the ceiling mount tray to the ceiling by drilling the 32 mm (1.26 in) M4 screws into the ceiling anchors.
6. Slide the switch into the ceiling mount tray.
7. Line up the two mushroom-heads on the switch to the ceiling mount tray hook cutouts until the switch locks into place.
8. Fix the switch to the ceiling mount tray using two screws on each side.