Installation Guide

ADORN® Mortarless
Stone Veneer
INSTALLATION INSTRUCTIONS
TOOLS NEEDED FOR INSTALLATION:
Safety glasses
Gloves
Ear Plugs
Dust Mask
Measuring Tape
Caulking gun
Utility Knife
Hammer
Must be corrosion resistant with a 3/8" minimum head diameter and 1/8" shank.
The length will vary and needs to be able to penetrate the studs to a depth of 1".
NCP recommends the use of quality exterior construction nails or screws.
NCP is not responsible for the corrosion resistance of fasteners. Treated lumber may react
with metal or coating of fastener. Determine compatibility when selecting fasteners.
FASTENERS
Level
Proper sized screws or nails
Drill
Saw with masonry blade
ADORN® Mortarless Stone Veneer can be used on new or existing construction.
ADORN® is nailed or screwed onto the wall; therefore no brick ledge is required.
ADORN® is limited to a height of 30ft with a normal building design.
Heights may be increased when specified by a structural engineer and approved by
building officials.
Maintain a 2 clearance from hard surfaces such as pavement and patio surfaces.
When a section of wall wraps over the top of the roof, this is called a floater. Extra
support is needed in this area prior to the installation of Adorn.
RESTRICTIONS
Safety first
is the number one priority with any construction project. Always wear safety
glasses and gloves when handling Adorn and a dust mask when cutting.
ADORN® is designed to install over 7/16 or greater OSB or plywood sheathing attached to wood or metal studs.
Two layers of code-approved weather-resistive barrier (WRB) must be installed for exterior installation. Typical WRBs are
Grade D building paper or #15 felt. Housewrap may be used as an inner layer.
All wall penetrations, doors, and windows should be sealed using self-adhesive flashing properly wrapped and lapped per
the flashing manufacturers instructions.
If treated wood is used, use 30lb felt or building paper.
The factory edge of ADORN® panels should be used in all areas where the edge is visible.
PREP WORK
ADORN® Install Guide
Step 1:
Install standard house
wrap over project area.
Step 2:
Add an additional layer of weather-
resistant barrier (WRB) such as 15 lb
felt over the house wrap.
Step 3:
Begin installing ADORN®
Flat with fasteners.
Step 4:
Continue to stagger flats on
top of each other, working
your way up.
Step 5:
Finish your install by using
ADORN® accessories such as
corner stones, sills and
outlet boxes.
Pro Tip: Use a 2x4 at the base to line up
flats for a level install.
Cutting is often a key part of the installation.
You can use a chop saw, circular saw, wet or dry saw, or a grinder with a diamond blade.
Take all necessary precautions when cutting, use safety glasses, gloves, and dust mask.
CUTTING