User's Manual

Schedule System Test
Page 136 FlexWave Prism Element Management System 7.1 User Manual
©
2011 ADC Telecommunications, Inc ADCP-77-177 Issue 1July 2011
5 Click the icon to the right of the DATE box to schedule on which date the System
Test will run. If you enter the date manually, use the YYYY/MM/DD format. For
example, to run a System Test on 14 June 2011, enter: 2011/06/14.
6 In the Time box, enter the time that the System Test is to run. Use the 24-hour
timeclock format of HH:MM:SS.
7 (Optional) Use the Recurrence radio buttons to set up a recurring System Test.
To have the System Test recurrence interval be counted by days, select the
Day(s) (1-30) radio button, and then in the corresponding box, enter how
many days should pass between each occurrence of this System Test.
To have the System Test recurrence interval be counted by weeks, select
the Week(s) (1-4) radio button, and then in the corresponding box, enter how
many weeks should pass between each occurrence of this System Test.
8 Click Apply.
NOTE: If you leave either the DATE or TIME parameter empty and then click Apply, Schedule System Test
will not run. However, if you leave both the DATE and TIME parameters empty and then click Apply,
the System Test starts immediately.
The following example has scheduled a System Test for 850 Classic passbands
on 850 Classic DARTs installed in Host1 to occur on 2 April 2011 at 1:00 AM.
This System Test will occur in one-week intervals.