Note: For mounting on a metal roof you may need to cut your cupola
base to fit down over the metal ribs or seams.
Manufacturer is not responsible for weather related damage under severe conditions.
Manufacturer is not responsible for any issues if installed differntly than these specs. Additional anchor rods can be supplied if necessary.
EASY
5
STEP
CUPOLA
INSTALLATION
GUIDE
(Please read Installation Guide thoroughly before starting.)
MARKS
4. Position
Position pieces of 2x4s on sides (shown) to be snug against the
inside walls of the cupola base. Screw them into the roof.
Note: For cupolas 60" and larger it is recommended to install
additional curbing - support on the inside of the cupola base.
1. Determine Your Roof Pitch
Screw two boards together so they pivot. Straddle the roof with
each board as shown, making sure each side is flat against the
roof and the center is at the center of the peak. Mark the boards
& apply another screw. This becomes your cutting template.
2. Mark the Cupola Base
Start cuts at corners and end at center.
be your cutting line. Your base should now be ready to cut.
Draw a centerline on the cupola base as shown. Using your cutting
template, make a line from each corner to the centerline. This will
Optional
Framing
Flashing Detail
3. Prepare Roof -
Decorative (
Recommended)
Prepare Roof -
Ventilation or accessibility
If your cupola will be used for ventilation or accessibility, cut an
opening in the roof, leaving a 5"- 6" minimum around the inside
perimeter of the cupola base, making sure to leave shingles
or other roofing material intact inside cupola base. (Additional
flashing or caulking must be used as illustrated in step #5 )
Cut shingles & sheathing only. Do not cut ridge or rafters.
There is no preparation necessary to your roof if your cupola is to be
installed for decoration only.(Recommended) If a ridge vent is present
the ridge vent where you cupola will sit and replace with cap shingles.
then cut out your cupola base to fit around the ridge vent,or remove
5. Mounting & Assembly
Attach the base to the 2x4s. Once the base is secured to the
roof, use silicone caulk to seal the sides of the base sections.
Leave an area in the 2 lower edges unsealed to allow any water
to drain. Now attach the mid-section to the base, and the top to
the mid-section using the screws (provided) in the pre-drilled
holes. Apply silicone caulk to all exposed screw heads.
Note:
When mounting for Ventilation or Accessiblity you will
want to apply roofing sealant & flashing to seal the sides of the
cupola base to the roof. Leave an area in the 2 lower sides
unsealed to allow any water to drain. Also apply a bead of caulk to