Samsung CDMA BSS: Indoor BTS Installation CDMA Base Station System Indoor BTS Installation Introduction Physical Installation Cabling Initial Testing Completion Appendix A: Indoor BTS installation required tools Appendix B: Indoor BTS installation materials Appendix C: Indoor BTS Installation Record About this Document 1
Samsung CDMA BSS: Indoor BTS Installation Manual Introduction Scope Conventions Required installation materials and tools Required documentation Safety precautions Warning Caution 1
Samsung CDMA BSS: Indoor BTS Installation Manual Scope This document covers the installation procedures for a single rack Indoor Base Transceiver Station (Indoor BTS). Note: This installation must be performed by Samsung qualified service personnel only, using only the tools, supplies, and materials listed in this manual. Any deviation will negate the responsibility of Samsung for operation or condition of this equipment.
Samsung CDMA BSS: Indoor BTS Installation Manual Conventions All measurements provided in this manual are given in metric units, with US units in parentheses: M Unless otherwise specified, lengths are given in millimeters (inches). For example, a length of 600.0 (23.6) means 600.0 mm (23.6 inches). M Weights are given in kilograms (pounds). For example, weight of 450 (992) means 450 kilograms (992 pounds). M Temperatures are given in degrees Celsius (Fahrenheit). For example: temperature of 37.
Samsung CDMA BSS: Indoor BTS Installation Manual Required documentation Before beginning the installation, verify that you have at least the following documents: M Site survey check list (customer-provided). M Site folder (customer-provided). M Samsung GPS System Installation Manual, v1.0. M TDI 24VDC Indoor Power Plant Turn Up and Test Manual.
Samsung CDMA BSS: Indoor BTS Installation Manual Required installation materials and tools BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 For a complete list of installation tools, see "Appendix A: Indoor BTS installation required tools". For a complete list of installation materials, see "Appendix B: Indoor BTS installation materials". Verify that all required tools and materials are present before proceeding to the next section.
Samsung CDMA BSS: Indoor BTS Installation Manual Safety precautions This section specifies the recommended safety precautions to follow when you work with the equipment described in this Installation Manual. This equipment meets the requirements of NFPA 70 (National Electric Code) and UL 1459 (Telephone Equipment). Note: The installation of this equipment is to be performed by Samsung qualified service personnel only, using only the tools, supplies, and materials listed in the manual.
Samsung CDMA BSS: Indoor BTS Installation Manual M Never attempt to install cables or replace surge protectors/ rectifiers with power applied. Verify the customer-provided Service Entrance input breakers are OFF. Observe the “two person” rule. M Do not disconnect AC and DC power connectors under load. Lead-acid batteries A “leak hazard” exists in any area where leadacid batteries are used. Use caution whenever working in the area to prevent and correct any leaks detected.
Samsung CDMA BSS: Indoor BTS Installation Manual Explosive environment . Use caution whenever working in the area to prevent possible combustion fuel vapors. M Do not install or operate in an explosive environment. M Do not install or operate the equipment in the presence of flammable gases or fumes. Operation of any electrical equipment in such an environment constitutes a definite safety hazard.
Samsung CDMA BSS: Indoor BTS Installation Manual Complete the following steps to ensure an assembly containing electrostatic sensitive devices can be safely removed without damage: M Before handling electrostatic sensitive devices, touch a grounded point with your bare hand to dissipate any static charge that may have developed in your body. A ground point can be any bare metal surface, such as the unpainted surface of a rack, that has been grounded.
Samsung CDMA BSS: Indoor BTS Installation Manual Physical Installation Unpacking and moving the rack Unpacking the rack Lifting provisions Mounting the racks – introduction Anchoring the rack on a concrete pad Lay out and drill the mounting holes Anchor the rack Isolation testing Anchoring the rack on a raised floor Layout and drill the mounting holes Anchor the racks Isolation testing on a raised floor BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Unpacking and moving the rack Unpacking the rack Note: Unpack racks one at a time. Do not unpack any crates until you are ready to use their contents. Note: Samsung equipment is packed in wooden crates with foam inserts to protect equipment. Remove the crate from the equipment. Do not attempt to remove the equipment from the crate. Note: Retain packing materials safely until you have completed installing all the equipment.
Samsung CDMA BSS: Indoor BTS Installation Manual Take the four eyebolts from the packing material and install onto the rack being lifted. 3 Have the operator lower the lifting straps to ground level. 4 Snap the hooks of the four straps to the eyebolts. Also fasten guidelines if required. 5 Have the operator lift the straps until they are taut. 6 Personnel should signal the operator to start the lift after they station themselves at the installation site.
Samsung CDMA BSS: Indoor BTS Installation Manual Mounting the racks – introduction Note: When installing the rack, do not tighten the anchor bolts tightly so leveling can be done. Note: Anchoring secures the racks to the floor surface in a physically and electrically safe manner. Proper anchoring provides safety against vibration, shock and other stresses. After the equipment is level, secure the rack with the anchor bolts to the mounting surface.
Samsung CDMA BSS: Indoor BTS Installation Manual Anchoring the rack on a concrete pad BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Lay out and drill the mounting holes Lay out and drill mounting holes in the concrete pad as follows: 1 Determine the number and location of the racks. 2 Mark the floor for each rack, using the template shown in the following illustration: Be sure to mark the locations of both the anchor bolt holes and the feet for each rack.
Samsung CDMA BSS: Indoor BTS Installation Manual Install the insulating bushing, washer, and hex nut set for each rack as shown in the following figure: 5 Insert and tighten an anchor bolt into each of the anchors. 6 Hand tighten the nuts until leveling and isolation testing is complete. 7 Complete the appropriate boxes in the Indoor BTS Installation Record. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Leveling the rack BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Level SBR1 using the following steps: 1 Check the level of SBR1, measuring on two adjacent sides (front and side or rear and side): 2 Adjust the rack level by inserting a #2 Phillips screwdriver into the hole in the foot at the bottom of the rack: 3 Turn the foot clockwise or counterclockwise to adjust the rack’s height.
Samsung CDMA BSS: Indoor BTS Installation Manual Isolation testing BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 The following isolation test should be done on the SBR1 rack to verify proper frame grounding insulation: 1 Connect the negative lead of the DVM to the anchor bolt, and connect the positive lead to an unpainted surface within the rack, as shown in the following figure: 2 Measure the isolation resistance.
Samsung CDMA BSS: Indoor BTS Installation Manual 5 Position the rack so no contact occurs between the anchor bolts and the base of the rack: 6 If contact occurs replace any broken spacers/bushings. 7 Tighten the hex nuts to the correct torque while maintaining the level of the rack. 8 Repeat steps 1 though 7 for SBR2 and SBR3. 9 Complete the appropriate boxes in the Indoor BTS Installation Record. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Anchoring the rack on a raised floor BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Layout and drill the mounting holes Use the following procedure to install a rack on a raised floor: 1 Determine the number and location of the racks. 2 Mark the floor for each rack, using the template shown in the following illustration: Be sure to mark the locations of both the anchor bolt holes and the rack feet.
Samsung CDMA BSS: Indoor BTS Installation Manual 7 Drop a length of threaded rod through one of the drilled holes in the floor surface. 8 Use a plumb bob to ensure that the threaded rod is perfectly vertical. 9 Mark the concrete with the location of the hole to be drilled. 10 BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Anchor the racks Mark the drill bit for a 2-inch drilling depth and drill the hole exactly 2 inches deep.
BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Samsung CDMA BSS: Indoor BTS Installation Manual 6 If you removed any drilled floor panels in order to install the anchors, replace those panels now, with the threaded rods projecting through the holes in the floor panels. 7 Position each rack over the marked locations for the feet, being careful not to damage the feet or the anchor bolts.
Samsung CDMA BSS: Indoor BTS Installation Manual Isolation testing on a raised floor BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 The following isolation test should be done on the SBR1 rack to verify proper frame grounding insulation: 1 Connect the negative lead of the DVM to the anchor bolt, and connect the positive lead to an unpainted surface within the rack, as shown in the following figure: 2 Measure the isolation resistance.
BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Samsung CDMA BSS: Indoor BTS Installation Manual 5 Position the rack so no contact occurs between the anchor bolts and the base of the rack: 6 If contact occurs replace any broken spacers/bushings. 7 Tighten the hex nuts to the correct torque while maintaining the level of the rack. 8 Repeat steps 1 through 7 for SBR2 and SBR3. 9 Complete the appropriate boxes in the Indoor BTS Installation Record.
Samsung CDMA BSS: Indoor BTS Installation Manual Cabling Connecting the cables Order of installation Overview of the external connections Rack ground Grounding the SBR1 rack Connecting DC power Unseating the modules Check DC voltage input Connecting the T1 cable Connecting the GPS cables Connecting the customer alarm cable Connecting the BBU/rectifier alarm cable BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Connecting the cables Warning: The installation of cables into the rack must be done in a specific order to avoid damage and electrical shock. Note: Install power and signaling cables separately from main power cables to prevent electronic induction. Leave a minimum gap of 152.4 mm (6 inches) between the data and the main power cables to avoid spurious emissions.
Samsung CDMA BSS: Indoor BTS Installation Manual BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Rack ground Warning: Potential loss of life! The installation of cables onto the racks should begin with grounding the racks. It is extremely important that the cables are installed in this order to avoid electrical shock. Note: If installing more than one rack, ground each rack separately to the main grounding point at the site. Note: The data and power cables must be installed with a minimum of 152.4 mm (6”) separation.
Samsung CDMA BSS: Indoor BTS Installation Manual The routing of the grounding cable under the floor is shown in the following diagram: BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 4 Cut the grounding cable and install a 2-hole grounding lug to the rack end of the grounding cable as shown in the following figure: Note: Coat all surfaces and terminals with anti-oxidant compound before making the connections.
Samsung CDMA BSS: Indoor BTS Installation Manual Fasten the grounding lug to the rack grounding point on the bottom of the rack: 6 Label both ends of the grounding cable. 7 Complete the appropriate boxes in the Indoor BTS Installation Record. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Connecting DC power BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Use the following procedure to connect the DC power cables: 1 Verify that the DC power source is off. 2 Connect the power cables to the DC input terminal block. Attach compression lugs to the input power cables. 3 Check the power switches at the top of the rack to make sure they are switched off.
Samsung CDMA BSS: Indoor BTS Installation Manual Unseating the modules Note: Do not touch the pins or elements on modules. Note: Foreign substances on modules should be completely removed with detergent. Unseat all the modules in the rack, as follows: 1 Put on a wrist strap and connect the other end to a grounding point in the rack: BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 The wrist strap protects modules from damage from electrostatic discharge.
Samsung CDMA BSS: Indoor BTS Installation Manual 3 To unseat a module, pry the ejector handles outward to release the module: 4 Apply pressure evenly to the ejectors and pull the module out until you can feel it unplug from the connector. 5 Leave the module on the shelf, disengaged from the connector. Note: Leave the unseated modules on the shelves, partially out of the rack. Make sure the unseated modules are not contacting the backplane in the rack before performing the power-up procedure.
Samsung CDMA BSS: Indoor BTS Installation Manual Check DC voltage input BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Verify that the correct voltages are present in the rack, as follows: 1 Make sure all power switches are off on the top power shelf, and on each SPD-T module on all racks. 2 Make sure that all modules in all shelves are unseated. 3 Apply power to the racks at the DC distribution panel.
Samsung CDMA BSS: Site Planning Connecting the T1 cable Use the following procedures to connect a T1 cable to the BTS: 1 Run the T1 cable from the customer demarcation to SBR1, securing the cable with tie wraps. 2 Attach the 50-pin male connector to the T1 cable. 3 The cable and connector are described below: Cable description Cable connector BTS connector 25 pair/24 AWG P/N: N-002524WFZ 50-pin, male P/N: DDK/5730500 50-pin, female BSS Version 4, Document V4D0001 release 0.
Samsung CDMA BSS: Site Planning BSS Version 4, Document V4D0001 release 0.5, Site Planning, release 2.
Samsung CDMA BSS: Site Planning 4 Connect the T1 cable to the 50-pin female connector shown in the following illustration. Be sure to secure the male connector with the two spring clips attached to the female connector. Label both ends of the T1 cable. 6 Complete the appropriate boxes in the Indoor BTS Installation Record. BSS Version 4, Document V4D0001 release 0.5, Site Planning, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Connecting the GPS cables The GPS cables are routed using a combination of cable ladders, cable pass-throughs, and cable trays. Cable ties are applied wherever appropriate. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 The routing of the overhead cables is illustrated in the following figure: The procedure for connecting these cables is as follows: 1 Ground the EMP bulkhead with 7.
Samsung CDMA BSS: Indoor BTS Installation Manual The GPS cable connects to the top of the SBR. Connect the GPS jumper cable to the GPS-A N-type female connector shown in the following figure: 5 Label both ends of the GPS jumper cable. 6 Complete the appropriate boxes in the Indoor BTS Installation Record. 7 If a second (backup) GPS antenna is installed, route and connect a second GPS cable. Follow steps 2 through 6 above, but connect the second GPS jumper cable to the GPS-B connector on the SBR.
Samsung CDMA BSS: Indoor BTS Installation Manual Connecting the customer alarm cable The customer alarm cable is routed using a combination of cable ladders, cable pass-through, and cable trays. Cable ties are applied wherever appropriate. The procedure is as follows: 1 Route the customer alarm cable from the customer demarcation point to the top of SBR1 2 Attach the 24-pin male Champ connector to the alarm cable according to the customer documentation.
Samsung CDMA BSS: Indoor BTS Installation Manual Connecting the BBU/rectifier alarm cable The BBU/rectifier alarm cable is routed using a combination of cable ladders, cable pass-through, and cable trays. Cable ties are applied wherever appropriate. The procedure is as follows: 1 Route the customer alarm cable from the BBU to the top of SBR1. 2 Attach the 9-pin female AMP connector to the BBU alarm cable.
Samsung CDMA BSS: Indoor BTS Installation Manual Connecting the RF cables RF cables are routed using a combination of cable ladders, cable pass-throughs, and cable trays. Cable ties are applied wherever appropriate. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Connect the jumper cables to the corresponding abg - A connectors for main TX/RX paths and abg -B connectors for diversity RX paths. 6 Label both ends of all cables. 7 Complete the appropriate boxes in the Indoor BTS Installation Record. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Initial Testing Reseating the modules Power-up the rack Power-up the fans Power-up shelves SH-0, SH-1, and SH-3 Power-up the SDP-T modules Power-up the GPS modules Power-up the PAU modules Document the power-up procedure. Power down procedure Power down SBR3 Power down SBR2 Power down SBR1 Final power up procedure BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Reseating the modules Note: Put on a wrist strap and connect the other end to a grounding point on the rack. The wrist strap protects the modules from damage from electrostatic discharge. Caution: Never touch the pins or elements on the modules. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Reseat modules one at a time. Push each module slightly with both thumbs until it is as far into the shelf as it will go. Then press the ejector handles down until they are flush and the latches click into place: BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Power-up the rack Before starting up the system, verify that all the circuit breakers on the power control panel are off, and that the switches on the SDP-T modules are off. Power-up the fans First turn on the fans: 1 Turn on the two FAN circuit breakers on the power control panel.
Samsung CDMA BSS: Indoor BTS Installation Manual BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 2 As you apply power to each shelf, the LED on each module on the left-hand side of that shelf should light: Note: The LEDs on some modules may stay red, because the BTS is not transmitting yet. If the LEDs on all the modules do not light, check the troubleshooting procedure at the end of this chapter.
Samsung CDMA BSS: Indoor BTS Installation Manual If the green LED above a B side shelf circuit breaker does not light, check the troubleshooting procedure at the end of this chapter. 4 As you apply power to each shelf, the LED on each module on the right side of that shelf should light. Note: The LEDs on some modules may stay red, because the BTS is not transmitting yet. If the LEDs on all the modules do not light, check the troubleshooting procedure at the end of this chapter.
Samsung CDMA BSS: Indoor BTS Installation Manual Power-up the GPS modules Power-up the GPS modules as follows: 1 Turn on the GCRU circuit breaker. If the green LED above the GCRU circuit breaker does not light, check the troubleshooting procedure at the end of this chapter. Check the LED at the top of each of the GCRU-A modules. If any LED does not light, check the troubleshooting procedure at the end of this chapter.
Samsung CDMA BSS: Indoor BTS Installation Manual 4 Check the status LEDs for each module. If a GPS system is installed and operating properly, the GPS status LED on one module should be on, and the ALM status LED on the other GCRU-A module should be on. 5 If the GPS status is not correct, check the troubleshooting procedure at the end of this chapter. Power-up the PAU modules Install the PAU modules; they are not shipped in the rack, but are packed separately.
Samsung CDMA BSS: Indoor BTS Installation Manual Power down procedure After all BTS racks have been initially tested, the racks must be powered down to reset the system. Be sure to follow the power down procedure step-by-step. Any deviations may cause damage to the equipment. Power down SBR3 If there is no SBR3 rack, go to the “Power down SBR2” procedure. If an SBR3 rack is installed, use this power down procedure: 1 Turn off the right side PAU power circuit breakers in this order: 5, 4, 3.
Samsung CDMA BSS: Indoor BTS Installation Manual Turn off the shelf power circuit breakers for the 3 Vout B Side in this order: SH-2, SH-1, SH-0. 6 Turn off the shelf power circuit breakers for the 3 Vout A Side in this order: SH-2, SH-1, SH-0. 7 Turn off the two FAN circuit breakers. 8 Complete the appropriate boxes in the Indoor BTS Installation Record. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Final power up procedure To prepare the Indoor BTS for commissioning, repower all the racks using the procedures described in the section "Power-up the rack" earlier in this chapter. After all racks are powered, complete the appropriate boxes on the Indoor BTS Installation Record. The Installation Manager must sign-off on the installation at this point. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Power-up troubleshooting Follow the procedures in this section to resolve any problems encountered during initial power-up. Fan power-up problem 1 Follow this procedure to resolve problems with initial power-up of the fans: Did the fan circuit breaker trip (snap back to off)? M If yes, go to step 2. M If no, go to step 9. 2 Turn off all input power to the SBR rack. 3 Disconnect the two 27 Volt power leads from the rear of the fan rack.
Samsung CDMA BSS: Indoor BTS Installation Manual 17 Problem exists in power control panel. Resolve fault, or replace power control panel, then go to step 20. 18 Is red Fail LED on the fan rack on? M If yes, go to step 19. M If no, go to step 20. 19 Problem exists in fan rack. Resolve fault, or replace fan rack, then go to step 20. 20 Return to the rack power up section of this chapter and repeat the procedure to power the fan.
Samsung CDMA BSS: Indoor BTS Installation Manual 15 Unseat and reseat any module whose LED is off. If LED does not light after the module is reseated, replace the module. 16 Repeat step 15 until all module LEDs are on, then go to step 24. 17 Check power output on rear of power control panel for correct voltage output to the shelf. 18 Is voltage to shelf correct? M If yes, go to step 19. M If no, go to step 23. 19 Check power input connection to shelf backplane for correct voltage.
Samsung CDMA BSS: Indoor BTS Installation Manual M If no, go to step 16. 2 Turn off all input power to the SBR rack. 3 Disconnect all GCRU power leads from the rear of the power control panel. 4 Turn on input power to the SBR rack. 5 Reset the GCRU circuit breaker to on. 6 Did the circuit breaker trip again? M If yes, go to step 7. M If no, go to step 8. 7 A short circuit exists in the power control panel. Resolve fault, or replace power control panel, then go to step 25.
Samsung CDMA BSS: Indoor BTS Installation Manual 22 Unseat then reseat the GCRU module with incorrect status indication. 23 Do status LEDs on GCRU modules indicate correct status? M If yes, go to step 25. M If no, go to step 24. 24 Replace GCRU module with incorrect status indication. Then go to step 25.
Samsung CDMA BSS: Indoor BTS Installation Manual M If no, go to step 15. 15 Check main input power to power control panel. 16 Is main input power present? M If yes, go to step 17. M If no, go to step 18. 17 Problem exists in power control panel. Resolve fault, or replace power control panel, then go tostep 23. 18 Restore main input power, then go to step 23. 19 Is LED on PAU module on? M If yes, go to step 23. M If no, unseat then reseat PAU module.
Samsung CDMA BSS: Indoor BTS Installation Manual Completion Complete all documentation BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Complete all documentation BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 Before leaving the site, verify that all customer documentation has been properly filled out. Use black or blue ink pen only. If documentation is not properly filled out, the installation crew will be sent back to the site to complete documentation.
Samsung CDMA BSS: Indoor BTS Installation Manual Clean-up Clean-up the work area before leaving. M If refuse was present in the work area before you began installation, take the refuse with you. BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation Manual, release 2.0 M Sweep the floor.
Samsung CDMA BSS: Indoor BTS Installation Manual Appendix A: Indoor BTS installation required tools CDMA BSS version 4, Indoor BTS Installation Manual, release 2.0 Hand tools SN# Vendor name / part # Assigned Unit price Notes tech. ID Tool description WSD SN# Manufacture Manufacture PN# 1 Kit in Xtra Rugged Rota Tough Case / 2023555 H500 Jensen JTK-96 Jensen Tools / JTK96 $552.00 2 Kit in Xtra Rugged Rota Tough Case / 2023555 H501 Jensen JTK-96 Jensen Tools $552.
Samsung CDMA BSS: Indoor BTS Installation Manual WSD SN# Manufacture Manufacture PN# SN# Vendor name / part # 18 4" Adjustable Wrench H518 Cresent AT14V N/A Grainger / 6C181 19 6" Adjustable Wrench H519 Cresent AT16V N/A Grainger / 6C179 20 6" Adjustable Wrench H519 Cresent AT16V N/A Grainger / 6C179 21 6" Adjustable Wrench H519 Cresent AT16V N/A Grainger / 6C179 22 8" Adjustable Wrench H520 Cresent AT18V N/A Grainger / 6C176 23 8" Adjustable Wrench H521 Cresent AT18V
Samsung CDMA BSS: Indoor BTS Installation Manual CDMA BSS version 4, Indoor BTS Installation Manual, release 2.0 ID Tool description Assigned Unit price Notes tech. Manufacture Manufacture PN# 45 Tap and Die Set H543 Vermont American 21749 Jensen / 146-190 $113.60 46 Cripper RJ11 and CAT 5 H544 AMP 2-231652-8 Jensen / 80-522 $111.20 47 Cripper RJ11 and CAT 5 H545 AMP 2-231652-8 Jensen / 80-522 $111.20 48 Cripper RJ11 and CAT 5 H546 AMP 2-231652-8 Jensen / 80-522 $111.
Samsung CDMA BSS: Indoor BTS Installation Manual ID Tool description Assigned Unit price Notes tech. Manufacture Manufacture PN# 74 Desolder Tool H572 Jensen 7874J Jensen / 983-300 $9.60 75 Desolder Tool H573 Jensen 7874J Jensen / 983-300 $9.60 76 Diagonal Cutters Insulated H574 Crescent $0.00 77 Diagonal Cutters Insulated H575 Crescent $0.00 78 Diagonal Cutters Insulated H576 Crescent $0.00 79 Assorted Bit Set, 118-039 H577 Jensen 950039 Jensen / 118-039 $31.
Samsung CDMA BSS: Indoor BTS Installation Manual CDMA BSS version 4, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual WSD SN# Manufacture Manufacture PN# Manufacture SN# Vendor name / part # 16 1/2" Hammer Drill P416 Milwaukee 5378-20 897A700032220 Jensen / 306-378 $166.50 4-28-00 17 1/2" Hammer Drill P417 Milwaukee 5378-20 897A799501852 Jensen / 306-378 $166.50 4-28-00 18 1/2" Hammer Drill P418 Milwaukee 5378-20 897A700020947 Jensen / 306-378 $166.50 4-28-00 19 Tool Kit Kart 300lb capacity P419 800 Jensen / 901-800 $148.
Samsung CDMA BSS: Indoor BTS Installation Manual CDMA BSS version 4, Indoor BTS Installation Manual, release 2.0 Miscellaneous tools Vendor name / part # Unit price$ 088TZUA142 Hutton / omo p14snz03p2aa $99.00 TA280SLK 088TZUA167 Hutton / omo p14snz03p2aa $99.00 WSDWT503 Motorola TA280SLK 088TZU8764 Hutton / omo p14snz03p2aa $99.00 TalkAbout Two-way Radio WSDWT504 Motorola TA280SLK 088TZUA140 Hutton / omo p14snz03p2aa $99.
CDMA BSS version 4, Indoor BTS Installation Manual, release 2.
CDMA BSS version 4, Indoor BTS Installation Manual, release 2.0 Samsung CDMA BSS: Indoor BTS Installation Manual Unit price$ WSD SN# Manufacture Manufacture PN# 48 Parts Box (Large) M494 Infinate Divider System T900 Jensen / 352-902 $7.00 49 Parts Box (Large) M495 Infinate Divider System T900 Jensen / 352-902 $7.00 50 Parts Box (Large) M496 Infinate Divider System T900 Jensen / 352-902 $7.00 51 Parts Box (Medium) M497 Infinate Divider System T600 Jensen / 352-602 $4.
Samsung CDMA BSS: Indoor BTS Installation Manual Appendix B: Indoor BTS installation materials Part description Specification Part # Qty per site Responsible party Notes CDMA BSS version 4, Indoor BTS Installation Manual, release 2.0 GPS equipment GPS antenna 58532A (Symmetricomm) 1 STA GPS coaxial cable 50ohm,PE,BK,D:10.8mm,RG-214/U 3802-000188 180 ft SEC GPS connector N-MALE 935 62137AA 4 SEC GPS arrestor 3402.17,K,Huber+Suhner,DC2.
Samsung CDMA BSS: Indoor BTS Installation Manual Part description Specification Pressure terminal 2-hole YA6CL-2TC14-E2 (6 AWG) Earth braid Wire: 3.5 mm, L:220, 2H (d2:4.5), green Screw-taptite Screw-taptite M4X10L PWH + S,C black Qty per site Responsible party Notes 4 STA additional contract EN75-10853A 8 SEC 6003-000216 34 SEC 1 STA 6 Sprint 1 STA Part # Bulkhead for RF and GPS RF arrestors Huber & Suhner (7/16 F to 7/16 F) 3400.41.
Samsung CDMA BSS: Indoor BTS Installation Manual Part description Specification Hilti anchor bolt assembly kit HSLI M12 Part # Qty per site Responsible party Kit # 96901831 1 STA Notes Contents of Hiliti kit: Threaded rod M12X125, SLTD, SS, A4-70 4 STA Nut, hex M12, SS 4 STA Washer M12, SS 4 STA Sleeve M12X40, SS 4 STA Coll, section M12 4 STA Expansion sleeve M12, SS 4 STA Cone M12, SS 4 STA Plate washer M12, SS 4 STA Hilti bolt Isolation bushing Bushing for the M
Samsung CDMA BSS: Indoor BTS Installation Manual Part # Qty per site Responsible party EP75-00199B 2 SEC Electrical tape (green) 3M Scotch 054007-10851 1 (roll) STA Electrical tape (black) 3M Scotch 054007-06132 1 (roll) STA Electrical tape (red) 3M Scotch 054007-10810 1 (roll) STA Part description Specification Side cover assembly W:543,L:1637,T:18.5,AL,CHROMATE Cable tie (black) 7,874 IN 1 (100 ea per pack) STA Cable tie (white) 7.
Samsung CDMA BSS: Indoor BTS Installation Manual BSC installation materials (for each BSC 0-11) Part description Specification Part # Qty per unit Responsible party 4 ea (160 ft) STA 5 SEC 10 STA 2 EA (30 FT) STA Notes DC power materials DC power cable CV 600V, 6-AWG Ring pressure terminal 1hole (BSC) YA6CL4-BOX Pressure terminal 2-hole (BBU) YA6CL-2TC14-E2 (6AWG) T831-50012K CDMA BSS version 4, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Part description Specification Part # Qty per unit Responsible party Notes Copper-coated plain washer ID : 8.3 T853-16004A 36 SEC MGB Copper-coated spring washer ID : 8.
Samsung CDMA BSS: Indoor BTS Installation Manual Part description Specification Part # Qty per unit Responsible party Coll, section M12 4 STA Expansion sleeve M12, SS 4 STA Cone M12, SS 4 STA Plate washer M12, SS 4 STA Bushing for the M12 4 STA 3 X 8 1/2 X.25 2 Hilti bolt isolation bushing Mounting plate Anchoring bolts and mounting for 2" thick slab or thinner CDMA BSS version 4, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Part description Specification Part # Qty per unit Responsible party Hex bolt Blt, hex. M16X30L, ZPC3, SM20C 6011-000102 4 SEC Plain washer d2:16.3,ZPC3,SM20C T855-10007A 4 SEC Bottom bracket fixing Door EMI block 86.
Samsung CDMA BSS: Indoor BTS Installation Manual SBGR installation materials Part description Specification Part # Qty per site / per unit Responsible party 2 STA CDMA BSS version 4, Indoor BTS Installation Manual, release 2.0 GPS equipment GPS antenna 58532A (Symmetricomm) GPS mast 'U' bolt assembly (galvanized) M12x 70L, center:56 D813-10002B 4 SEC GPS coaxial cable 50ohm, PE, BK, D:10.8mm, RG214/U 3802-000188 360 ft SEC GPS connector N-male 935-62137AA 6 SEC GPS arrestor 3402.
Samsung CDMA BSS: Indoor BTS Installation Manual Specification Part # Qty per site / per unit Responsible party Ground cable 2-AWG / E156879 TBD 2 ea (30 ft) STA Ground cable 6-AWG 2 ea (20 ft) STA Pressure terminal 2-hole YA2CL2NT14E2 6 STA Pressure terminal 2-hole YA6CL-2TC14-E2 (6AWG) 6 STA Earth braid WIRE:3.5MM, L:220, 2H (d2:4.
Samsung CDMA BSS: Indoor BTS Installation Manual Part description Specification Part # Qty per site / per unit Responsible party Copper-coated spring washer ID: 6:3 CU PLT, plain T855-17003A 8 SEC Notes T1 materials T1 cable (MSC-BSC) 25 twisted pair - 24 AWG 10 ea (140 ft) STA BSC-MSC T1 cable (BSC-BTS) 25 twisted pair - 24 AWG 8 ea (140 ft) STA BSC-BTS T1 Centronics connector Amphenol 50 pin 20ea Anchoring bolts and mounting for 6" thick slab or thicker CDMA BSS version 4, Indoor
Samsung CDMA BSS: Indoor BTS Installation Manual Part description Specification Part # Qty per site / per unit Responsible party 229631 2 tubes STA Notes Anchoring bolts and mounting for 2" thick slab or thinner CDMA BSS version 4, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Part # Qty per site / per unit Responsible party Electrical tape (black) 3M Scotch 054007-06132 1 (roll) STA Electrical tape (red) 3M Scotch 054007-10810 1 (roll) STA Part description Specification CDMA BSS version 4, Indoor BTS Installation Manual, release 2.0 Electrical tape (white) Cable tie (black) 7,874 IN 1 (100 ea per pack) STA Cable tie (white) 7.
Samsung CDMA BSS: Indoor BTS Installation Manual BSC installation materials Part description Specification Part # Qty per site Responsible party W: 543, L: 1637, T: 18.5, AL, chromate EP75-00199B 2 SEC Miscellaneous materials CDMA BSS version 4, Indoor BTS Installation Manual, release 2.
Samsung CDMA BSS: Indoor BTS Installation Manual Appendix C: Indoor BTS Installation Record Site name: Customer name: Samsung qualified technicians responsible: Date completed: Note: When installing less than 3 racks, mark “N/A for “Date”, and initial in the appropriate space. Note: Date and initial each step as it is completed. Task Description Date CDMA BSS Version 4, Indoor BTS Installation Manual, release 2.0 Required documents All required documents present and accounted for.
Samsung CDMA BSS: Indoor BTS Installation Manual Task Description Date Unpacking the racks SBBR Damaged goods? o Yes o No All equipment present? o Yes o No SBER1 Damaged goods? o Yes o No All equipment present? o Yes o No SBER2 Damaged goods? o Yes o No All equipment present? o Yes o No BBU Damaged goods? o Yes o No All equipment present? o Yes o No Site preparation CDMA BSS Version 4, Indoor BTS Installation Manual, release 2.0 Site prepared according to the template.
Samsung CDMA BSS: Indoor BTS Installation Manual Task Description Date Anchor brackets installed, and rack anchored. Cable pipe installed. SBER2 Rack placed at installation position. Anchor brackets installed, and rack anchored. Cable pipe installed. Isolation test the racks SBBR Rack isolated from ground. SBER1 Rack isolated from ground. SBER2 Rack isolated from ground. Leveling the racks SBBR Rack level and secured. SBER1 Rack level and secured. SBER2 Rack level and secured.
Samsung CDMA BSS: Indoor BTS Installation Manual Task DC power check Description Date Verify correct DC input voltage T1 cable Cable installed and labeled. GPS cable Cable installed and labeled. Customer alarm cable Cable installed and labeled. BBU alarm cable Cable installed and labeled.
Samsung CDMA BSS: Indoor BTS Installation Manual Task Description Power-up SH-0 SH-0 power-up successful Power-up SH-1 SH-1 power-up successful Power-up SH-2 SH-2 power-up succesful Power-up SDP-T modules SDP-T modules power-up successful Power-up PAU modules PAU module power-up successful Date Power down SBBR All modules powered down in correct order. SBER1 All modules powered down in correct order. SBER2 All modules powered down in correct order.
Samsung CDMA BSS: Indoor BTS Installation Manual About this Document Document history Samsung CDMA Base Station System Version 4 Indoor BTS Installation Manual Date Release Author 2.0 AHF/JTC Notes © Copyright 2000 Samsung Telecommunications America, Inc. Approvals Approved by: Bijan Nowroozi, 07 Dec 00 Trademarks The various trademarks used in this document are the property of their respective owners. Our policy is to maintain up-to-date publications of the highest possible quality.