Powering up and commissioning the BTS
9
1. Power up the site and check the LEDs.
2. Commission the BTS.
Check list
DC power cables are connected and the cable clamp is in place.
Connector seals are firmly in place.
All cables are connected according to the configuration.
BTS external cables or cables between the modules on different plinths are routed via
cable entries.
Connector seals are firmly in place.
1. Remove connector seal from OPT1 connector in ESMB/C.
2. Remove protective cap from optical transceiver and insert it into OPT1 in ESMB/C.
3. Route optical cable through cable entry.
4. Uncover the connector. Pull back the optical cable connector seal to uncover the
connector.
5. Remove protective plugs.
6. Clean connectors with 99% alcohol and swabs.
7. Connect optical cable to optical transceiver in ESMB/C.
8. Push connector seal firmly.
9. Repeat steps 1-8 to connect optical transceiver and optical cable to OPT1 of FXxx.
10.Ensure all connector seals are properly installed.
Note: For commissioning the BTS, see Commissioning Flexi Multiradio BTS GSM/EDGE document
and Quick Guide for Flexi Multiradio BTS GSM/EDGE Commissioning
To avoid cabling rework, check that the unit powers on before tying down the cables.