Instructions / Assembly

INSTRUCTIONS
For pipe heights 6" – 15"
(152 mm – 381 mm)
above roof deck
A
D
DRAWN
Always read and observe safety
considerations and published
installation instructions
a. Use this product only in the manner intended
by GAF.
b. If you have installation questions, please contact
GAF Master Flow
®
Technical Services at
1-800-211-9612 or email WarrantyLLBP@gaf.com.
In the unlikely event that accessories or parts are
missing or this product does not function properly,
please contact GAF Master Flow
®
Technical
Services. Do NOT return this rooftop accessory
to retailers or distributors.
c. Install only on roof slopes 3:12–12:12
d. Compatible with Schedule 40 PVC, ABS, and
Steel plumbing pipe inside diameters and may
be used with 6" – 15" (152 mm – 381 mm) tall
pipes (see Figure 1 and Compatibility Chart)
Note: If necessary, taller plumbing pipes can be cut
down to 15” (381 mm) or less.
e. During installation and handling, always wear
appropriate Personal Protective Equipment
(PPE) such as safety glasses, durable work
gloves, hard hats, fall restraints, and other safety
equipment to avoid injury.
Always review and observe all applicable local
building and plumbing codes in your area. Note:
plumbing codes often require plumbing vent pipes
to extend vertically at least 6” (152 mm) above the
roof deck
Compatability Chart
Pivot
Model
Compatible with the Following:
Schedule 40 PVC, ABS,
and Steel Plumbing Pipes
(Pipe Inside Diameters)
Pipe Height
(Above Roof
Deck)
Pivot 1.5
PPBG1.5
1.5" (38.1 mm)
6" – 15"
(152 mm –
381 mm)
Pivot 2
PPBG2
2" (50.8 mm)
Pivot 3
PPBG3
3" (76.2 mm)
Pivot 4
PPBG4
4" (101.6 mm)
Preparation:
1. Install roof deck protection (i.e., underlayment),
such as GAF Deck-Armor
Premium Breathable
Roof Deck Protection, per manufacturer’s published
installation instructions. The roof deck protection
should always be installed leaving at least 6"
(152 mm) of exposed roof deck around the
plumbing pipe.
2. Cut a minimum 24" x 24" (610 mm x 610 mm)
square piece of self-adhering leak barrier, such
as GAF StormGuard
®
Film-Surfaced Leak Barrier,
and center the square over the top of the
plumbing pipe.
3. Cut an “X” in the leak barrier square from one
outside edge of the plumbing pipe to the other,
ensuring the “X” is slightly smaller than the pipe’s
overall width to allow the leak barrier to fit tightly
around the pipe.
4. Remove the release liner on the leak barrier and
lower the leak barrier down around the plumbing
pipe, firmly pressing it in place to the roof deck,
roof deck protection, and up the side of the
plumbing pipe itself. Reference (Figure 3)
for a sample of the completed preparation.
Note: A hand-held roller can be used to help ensure
maximum adhesion of the self-adhering leak barrier.
5. Proceed with shingling up to the plumbing
pipe, following the manufacturer’s published
installation instructions.
Pivot
Installation:
6. Separate the Pivot
cap assembly from its base
flashing assembly.
7. Using the base flashing’s built-in ball/socket pitch
adjustment feature, adjust the Pivot
so that it is
oriented vertically toward the sky. This feature
allows for simple rooftop pitch adjustment from
3:12 12:12.
8. With the “UP” arrow inscribed in the base flashing
pointing towards the roof peak, center and slide
the base flashing down over the plumbing pipe.
The bottom portion of the base flashing must
always sit on TOP of the shingle course below
the plumbing pipe. Use the Pivot
's rooftop pitch
adjustment feature to center the plumbing pipe in
the base flashing and to vertically orient the Pivot
towards the sky.
Note: For additional weather protection, a bead
of asphalt plastic roofing cement (ASTM D4585
Type I or Type II) or polyurethane roofing and flashing
sealant (ASTM C920) can be applied in a ‘U’ shape
pattern underneath the bottom and sides of the
base flashing (Figure 4).
Inside Diameter
Outside Diameter
Sealant applied under bottom
and sides of base ashing.
Leave 1/
4
" (6.4 mm) gap in
sealant under bottom section
to allow for drainage
A A
D D
DRAWN
GAF Roof Deck
Protection
GAF Leak Barrier
at least 24" x 24"
(610 x 610 mm)
square.
Cut over pipe
in an "X" for
tight t
Figure 1
Figure 2
Figure 3
Figure 4