Hitachi Universal Storage Platform VM Installation Planning Guide FASTFIND LINKS Document Organization Product Version Getting Help Contents MK-97RD6679-00
Copyright © 2007 Hitachi Data Systems Corporation, ALL RIGHTS RESERVED Notice: No part of this publication may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying and recording, or stored in a database or retrieval system for any purpose without the express written permission of Hitachi Data Systems Corporation (hereinafter referred to as “Hitachi Data Systems”).
Contents Preface ................................................................................................... v Safety and Environmental Notices......................................................................... vi Intended Audience .............................................................................................. vi Product Version.................................................................................................. vii Document Revision Level ..........................
Power Specifications and Requirements............................................................ 2-13 Power Specifications and Power Supplies ................................................... 2-13 Breaker Configurations ............................................................................. 2-15 Power Connection .................................................................................... 2-16 Input Voltage and Input Frequency ...........................................................
Preface This document provides installation and configuration planning information for the Hitachi Universal Storage Platform VM (USP VM) storage system. Please read this document carefully to understand the installation requirements for the Universal Storage Platform VM, and maintain a copy for reference.
Safety and Environmental Notices Federal Communications Commission (FCC) Statement This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial environment.
Product Version This document revision applies to Universal Storage Platform VM microcode 60-02-0x and higher. Document Revision Level Revision MK-97RD6679-00 Date November 2007 Description Initial release, supersedes and replaces MK-97RD6079 Changes in this Revision • Added information on the 750-GB hard disk drive (Table 2-2, Table 2-8). Document Organization The following table provides an overview of the contents and organization of this document.
Document Conventions The term “Universal Storage Platform VM” refers to all models of the Universal Storage Platform VM storage system, unless otherwise noted. This document uses the following icons to draw attention to information: Icon Meaning Description Note Calls attention to important and/or additional information. Tip Provides helpful information, guidelines, or suggestions for performing tasks more effectively. Caution Warns the user of adverse conditions and/or consequences (e.g.
Getting Help If you need to call the Hitachi Data Systems Support Center, make sure to provide as much information about the problem as possible, including: • The circumstances surrounding the error or failure. • The exact content of any error message(s) displayed on the host system(s). • The service information messages (SIMs), including reference codes and severity levels, displayed by Storage Navigator. The Hitachi Data Systems customer support staff is available 24 hours a day, seven days a week.
x Preface Hitachi Universal Storage Platform VM Installation Planning Guide
1 Planning for Installation This chapter describes the requirements and procedures for planning to install the Universal Storage Platform VM.
Responsibilities The responsibilities for installation planning are shared by the customer and the Hitachi Data Systems account team. The required installation planning tasks must be scheduled and completed to ensure successful and efficient installation of the Universal Storage Platform VM. Customer Responsibilities You are responsible for: • Performing the installation planning tasks described in this document.
Installation Planning Tasks The customer is responsible for performing the following tasks, with assistance as needed from the Hitachi Data Systems account team, to prepare for installation of the Universal Storage Platform VM storage system: 1. Read this document carefully to understand the installation requirements for the Universal Storage Platform VM. You will use the information in this document to determine the specific requirements for your installation. 2.
Installation Planning Checklist Complete the checklist below (online or hardcopy) to verify that all installation requirements for the Universal Storage Platform VM have been met. Successful completion of this checklist (Yes is checked for all entries) will ensure smooth and efficient installation of the Universal Storage Platform VM. Definition of terms: Data center: The room at the customer site in which the Universal Storage Platform VM will be installed.
Installation Planning Checklist Yes No Safety Is the data center equipped to protect equipment from fire? Is the data center free of hazards (e.g., cables that obstruct access)? Delivery Is the receiving area adequate for equipment delivery and unloading? (overall height: 84 in, 2.
1-6 Planning for Installation Hitachi Universal Storage Platform VM Installation Planning Guide
2 Installation Requirements This chapter provides the installation requirements for the Universal Storage Platform VM storage system. Safety Requirements Delivery Requirements Storage Requirements Facilities Requirements Physical Specifications and Requirements Power Specifications and Requirements Environmental Specifications and Requirements Operational Requirements Note: The general information in this chapter is provided to assist in installation planning and may not be complete.
Safety Requirements The safety requirements for Universal Storage Platform VM installation are: • Safety regulations: The data center must comply with all applicable safety regulations, standards, and requirements. • Fire protection: The data center must have an operational fire protection system. • Hazards: The data center must be free of hazards (e.g., cables on the floor that obstruct access).
Delivery Requirements The customer site must accommodate the delivery and movement of the equipment to the installation location in the data center. The delivery requirements for Universal Storage Platform VM installation are: • Dimensions: The loading bay, hallways, doors, elevators, and stairs must be large enough to allow the delivered equipment to be moved to the installation location. The shipping crate dimensions are: Height: 84 inches (2.
Storage Requirements If the delivered equipment needs to be stored after delivery and prior to installation, the storage location must meet the environmental requirements for the Universal Storage Platform VM (see Table 2-1). Table 2-1 Environmental Specifications for Storage Shipping & Storage* Parameter Temperature °F (°C) Relative Humidity (%) *4 Low High 5 (-25) 140 (60) 5 – 95 Max.
Facilities Requirements The customer site must meet the following facilities requirements: • General: The data center must be fully operational (e.g., power, air conditioning, cabling, fire protection system). • Floor: The data center must have a tiled raised floor. • ESD: The data center must provide adequate protection from electrostatic discharge (ESD). • Electrical interference: The data center must provide adequate protection from electrical/radio frequency interference.
Physical Specifications and Requirements Figure 2-1 shows a physical overview of the Universal Storage Platform VM.
Dimensions and Weight Figure 2-2 shows the dimensions of the single-rack configuration. Figure 2-3 shows the dimensions of the twin-rack configuration. Table 2-2 lists the dimension and weight specifications for the Universal Storage Platform VM components.
TOP VIEW 1046 mm 601 mm 601 mm TBD FRONT VIEW 2001 mm Figure 2-3 2-8 Physical Dimensions: Twin-Rack Configuration Installation Requirements Hitachi Universal Storage Platform VM Installation Planning Guide
Table 2-2 Component Specifications: Weight and Dimension Dimension (mm) Model Number Weight (kg) Width Depth Height DKC615I-5 70 445 800 438 DKC-F615I-B2 80.5 445 647 522 DKC-F615I-SBX 13 445 800 84 DKC-F615I-LGAB 11 — — — DKC-F615I-PLUC 2.0 — — — DKC-F615I-PHUC 4.0 — — — DKC-F615I-PLEC 1.5 — — — DKC-F615I-PHEC 2.5 — — — DKC-F615I-UC0 3.2 — — — DKC-F615I-UC1 2.1 — — — DKC-F615I-EXC0 6.2 — — — DKC-F615I-SX 1.2 — — — DKC-F615I-S4GQ 0.
Service Clearance, Floor Cutout, and Floor Load Rating This section specifies the service clearance requirements (a + b) for the Universal Storage Platform VM storage system, based on the floor load rating and the clearance (c), and the required floor cutouts for cabling. • Figure 2-4 shows the service clearance and floor cutout requirements for the single-rack configuration. Table 2-3 shows the floor load rating and clearance requirements for this configuration.
a *1 (Unit : mm) B *1 601 Rear 125 1100 195 65 125 62 215 575 65 482 125 1050 3250 355 835 DKC615 1050.00 457 200 or more 63 90 601 G 1100 Front 74 61.5 482 601 c *1 Front Floor cutout area for cables Screw jack DKC615 Caster Service clearance G Figure 2-4 Grid panel (over 450mm x 450mm) Service Clearance and Floor Cutouts: Single Rack Notes: 1. Clearance (a+b) depends on the floor load rating and clearance (c). See Table 2-3 for floor load rating and clearance requirements.
*1 a 195 125 b 1220 215 195 *1 (Unit: mm) Rear 1100 215 65 65 125 575 150 150 3250 835 655 655 835 1050 DKC515 63 90 90 G G 1050 63 200 or more 1100 601 74 457 457 74 Front 61.5 482 482 585 61.5 585 c *1 10*2 DKC615 Floor cutout area for cables DKC615 Screw jack Caster Service clearance G Figure 2-5 Grid panel (over 450mm x 450mm) Service Clearance and Floor Cutouts: Two Racks Notes: 1. Clearance (a+b) depends on the floor load rating and clearance (c).
Power Specifications and Requirements This section describes the power specifications and requirements for the Universal Storage Platform VM storage system: • Power Specifications and Power Supplies • Breaker Configurations • Power Connection • Input Voltage and Input Frequency • Circuit Breakers and Plugs Power Specifications and Power Supplies Table 2-5 lists the power specifications for the Universal Storage Platform VM, including inrush current, leakage current, input current, and steady curr
Primary Rack Secondary Rack DKU-R1 PDU DKU PS PS30 ×15 PS31 PS20 ×15 PS21 PS10 ×15 PS11 PS00 ×15 PS01 PDU DKU PS DKU-R0 PS30 ×15 PS31 PS20 ×15 PS21 PS30 ×15 PS31 PS10 ×15 PS11 PS20 ×15 PS21 PS00 ×15 PS01 PS10 ×15 PS11 PS00 ×15 PS01 PDU PDU DKC PDU PS11 ×15 PS31 PS20 ×15 PS21 PS10 ×15 PS11 PS00 ×15 PS01 Power Cable (AC Input 1) CL2 PS12 PS21 DKC PS PS22 Power Cable (AC Input 2) PDU DKU-R2 PS30 PDU CL1 PDU DKU-R3 Power Cable (AC Input 1) Po
Breaker Configurations For both racks, AC power is supplied to each power distribution unit (PDU) from the breaker. Figure 2-7 and Figure 2-8 show the breaker configurations for the primary and secondary racks, respectively. DKU-R1 DKU-R0 DKU-R0 PDU (1φ/20A) PDU (1φ/20A) PDU (1φ/20A) PDU (1φ/20A) DKC DKC Regardless of the number of disk chassis, the number of 20A breakers is the same.
Power Connection The AC power input for the Universal Storage Platform VM has a duplex PDU structure. This duplex structure enables the entire rack to remain powered on in the event that power is removed from one of the two power distribution panels (PDPs). • Direct connection to power. Figure 2-9 shows the power connections when the AC input lines are connected directly to the power facility. • Power connection through UPS.
Primary Rack PDP2 Secondary Rack DKU-R1 UPS1 PDU (1φ/20A) UPS2 PDU (1φ/20A) PDU (1φ/20A) DKU-R0 DKU-R3 PDU (1φ/20A) DKC PDU (1φ/20A) PDU (1φ/20A) DKU-R2 Branch Distribution Box To UPS PDP1 To UPS To PDP AC Input Line PDP: Power Distribution Panel Figure 2-10 To PDP For the AC input power, connect one of the duplexes PDUs to the UPS and the other one to the PDP.
Input Voltage and Input Frequency Table 2-6 lists the input voltage and input frequency requirements for the Universal Storage Platform VM.
Environmental Specifications and Requirements The environmental specifications and requirements for the Universal Storage Platform VM include: • Temperature, Humidity, and Altitude • Heat Output, Power Consumption, and Air Flow • Loudness • Vibration and Shock Temperature, Humidity, and Altitude Table 2-1 specifies the temperature, humidity, and altitude requirements for the Universal Storage Platform VM. The recommended operational room temperature is 21–24°C (70–75°F).
Heat Output, Power Consumption, and Air Flow Table 2-8 lists the power consumption and heat output specifications and the air flow requirements for the Universal Storage Platform VM. These data generally apply to both 60-Hz and 50-Hz storage systems. The Universal Storage Platform VM requires less power and puts out less heat than the Hitachi TagmaStore® Network Storage Controller, so the air flow requirements are decreased.
Loudness The acoustic emission values [loudness in dB(A)] for the Universal Storage Platform VM storage system are: Front/rear = 65 dB(A) Both sides = 65 dB(A) Vibration and Shock Table 2-9 lists the vibration and shock tolerance data for the Universal Storage Platform VM. The USP VM can be subjected to vibration and shock up to these limits and still perform normally.
Operational Requirements The operational requirements for the Universal Storage Platform VM include: • LAN connection (or RJ-11 analog phone line) for Hi-Track® The Hi-Track maintenance support tool monitors the operation of the Universal Storage Platform VM, collects hardware status and error data, and transmits this data via LAN (or modem) to the Hitachi Data Systems Support Center.
A Units and Unit Conversions Table A-1 provides conversions for metric and standard (U.S.) units of measure associated with the Hitachi Universal Storage Platform VM storage system. For information on physical and logical storage capacity values on the USP VM storage system, see Convention for Storage Capacity Values. Table A-1 Conversions for Metric and Standard (U.S.) Units of Measure From Multiply By: To Get: British thermal units (BTU) 0.251996 Kilocalories (kcal) British thermal units (BTU) 0.
A-2 Units and Unit Conversions Hitachi Universal Storage Platform VM Installation Planning Guide
Acronyms and Abbreviations A ASTM ampere American Society for Testing and Materials BED BS BTU back-end director basic (power) supply British thermal unit °C ca CHA degrees Celsius cache channel adapter (another name for front-end director) dB(A) DKA DKC DKU decibel (A-weighted) disk adapter (another name for back-end director) disk controller disk unit ESD electrostatic discharge FCC FED Federal Communications Commission front-end director g GB acceleration of gravity (9.
LW long wavelength m mA max. MB mm ms meter milliampere maximum megabyte (see Convention for Storage Capacity Values) millimeter millisecond NEMA National Electrical Manufacturers Association PB PDP PDU PS sec.
Hitachi Universal Storage Platform VM Installation Planning Guide
Hitachi Data Systems Corporate Headquarters 750 Central Expressway Santa Clara, California 95050-2627 U.S.A. Phone: 1 408 970 1000 www.hds.com info@hds.com Asia Pacific and Americas 750 Central Expressway Santa Clara, California 95050-2627 U.S.A. Phone: 1 408 970 1000 info@hds.com Europe Headquarters Sefton Park Stoke Poges Buckinghamshire SL2 4HD United Kingdom Phone: + 44 (0)1753 618000 info.eu@hds.