RBS Installation Instructions RBS 2409 INSTALLATION INSTRUCTION
Copyright © Copyright Ericsson AB 2007. All rights reserved. Disclaimer No part of this document may be reproduced in any form without the written permission of the copyright owner. The contents of this document are subject to revision without notice due to continued progress in methodology, design and manufacturing. Ericsson shall have no liability for any error or damage of any kind resulting from the use of this document.
Contents Contents 1 Introduction 1 1.1 Revision Information 1 2 Preconditions 1 3 Tools and Instruments 3 3.1 Tools for Installation 3 4 Installation Procedure 3 4.1 Unpacking RBS 4 4.2 Installing the RBS 4 4.3 Attaching the RBS 6 4.4 Installing DC power 8 4.5 Connecting Cables 8 4.6 Replacing Front Cover 9 4.7 Testing the Installation 10 4.
RBS Installation Instructions 41/1531-LZA 701 0001 Uen D 2008-04-23
Preconditions 1 Introduction This document provides instructions for installing an RBS 2409. The RBS 2409 can be installed either on a wall, or hanging from a ceiling. Both stand-alone and master-extension configurations are possible. Target Group The target group for this instruction is personnel involved in the installation of an RBS. Technicians working on Ericsson products or systems must have the necessary training and competence required to perform their work correctly. 1.
RBS Installation Instructions • Completed and approved record prepared during site preparation • Site Installation Documentation, specific for the site (prepared by the Installation Engineering department) • Setting IDB Parameters, 46/1543-LZA 701 0001 • Verifying RBS Installations at Site, 11/1532-LZA 701 0001 General Preconditions Before starting site work, ensure the following: • Site access permission has been received • Ordered RBS, equipment, specified tools and other necessary facilities
Installation Procedure 3 Tools and Instruments This section contains lists of all tools and instruments recommended for the complete installation of the RBS. 3.1 Tools for Installation Table 1 4 Basic Tools for Installation Description Specification Drilling machine – Screwdriver Torx: T10 Knife – Screws for installation 4 screws for plate, and 2 screws for adapter Installation Procedure This section describes the installation procedure for the RBS.
RBS Installation Instructions Unpacking the RBS Installing the Wallplate Installing the Ceiling Bracket Attaching the RBS Installing DC Power Connecting Cables Replacing Front Testing the Installation Performing Concluding Routines P018294B Figure 1 4.1 Installation Flowchart Unpacking RBS Unpack the RBS on-site. To avoid damage, the RBS must not be unpacked elsewhere and then transported to site. Ensure that the correct material has been delivered.
Installation Procedure 4.2.1 Installing the Wall Plate 1. Place the wall plate in a vertical position where the RBS is to be located. Up Make sure the hole for the cable cover is facing upwards. P018100A 2. Install the wall plate and secure it in position. Note: Depending on the wall, it may be necessary to drill holes for the screws. 4.2.2 Installing the Wall Plate on a Ceiling Bracket (Optional) 1. Place the ceiling bracket in the position where the RBS is to be located. 2.
RBS Installation Instructions 5. Attach the plate and secure it. P018103A 4.3 Attaching the RBS 1. Insert and press a screwdriver in the upper hole to release the front cover, and slide the cover down 75 mm. 2. Detach the cable cover without releasing the screw.
Installation Procedure 3. Attach the RBS in its position and press it down. Make sure the hole on the bracket and the hole on the RBS are aligned (see 2 in figure to right).
RBS Installation Instructions 4.4 Installing DC power 1. Install the PSU-AC-41 in the position where it is to be located. Note: Depending on the wall, it may be necessary to drill the holes for the screws. P018111B 4.5 Connecting Cables Following interfaces in the RBS 2409 are available: • Ethernet (transmission) • DC power • External Antenna (optional) • Y-link (if using extension RBS) • Configuration (Configuring the RBS or the STN) 1.
Installation Procedure 2. Connect the ethernet cable and attach the cable cover. 3. Close the front cover, by sliding it up until there is a clicking sound. 4.6 Replacing Front Cover 1. Insert and press a screwdriver in the upper hole to release the front cover, and slide the cover down 75 mm.
RBS Installation Instructions 2. Loosen the captive screws on both sides to release the front cover, using a hand or a Torx 10 screwdriver. 3. Align the upper edge of the new front cover with the two marks on the rear cover, and slide the cover up all the way. Tighten the captive screws fingertight or tighten them properly using a Torx 10 screwdriver. 4.7 Testing the Installation The RBS is now ready for verification of the site installation.
Installation Procedure Table 2 Objects to Be Recycled or Disposed of After RBS Installation Item Sort or Recycle? Cable insulation from crimping, brazing or welding Sorted with plastics Packing chips Foam Polystyrene Bubble plastic Cable tie clippings Paper and wood Paper recycling Waste metal from cable ladders Recycled or sorted as metals Pieces of cable Nuts, bolts, washers and screws Note: 4.8.
RBS Installation Instructions Check the following: 5. The modified Site Installation Documentation has been handed over to the person responsible for the site. 6. The RBS is powered up if the surrounding temperature changes between hot and cold and the RBS installation is not (1) completed within 48 hours. (1) See document 12 OK Verifying RBS Installations at Site.