Installation Manual

www.eaton.com IM02601001E C-13
Conguration Management
Connectors
13 position
connector
GND
L(+)
N(-)
6 position
network
connector
2. If a Modbus network was connected remove the six position network connector.
3. Return the meter to the mounting panel using any hardware removed in previous steps.
4. Reconnect the current sensing (CT or direct connections) wires.
5. If an AUX cable was not used, reconnect the wires to the 13 position connector. Otherwise
plug the wired connector into the meter.
6. Reconnect the Modbus network using the six position Modbus connector.
7. Insert the Ethernet cable into the socket on the new Gateway Card. Be sure to route the
cable away from any high voltage wires. Secure the cable in compliance with local electrical
codes.
8. Take any necessary safety precautions in preparation for restoring power.
9. Turn the power on at the breaker(s).
10. Watch the lights on the back of the Gateway Card. They should all turn off for a few seconds
and then the right (Status) and the left (Power) lights should be illuminated to indicate the
card has power and has started correctly.
11. Power and Status LEDs.