Dell EMC PowerSwitch S4048T-ON Installation Guide March 2021 March 2021 Rev.
Notes, cautions, and warnings NOTE: A NOTE indicates important information that helps you make better use of your computer. CAUTION: A CAUTION indicates either potential damage to hardware or loss of data and tells you how to avoid the problem. WARNING: A WARNING indicates a potential for property damage, personal injury, or death. © 2018 - 2019 Dell Inc. or its subsidiaries. All rights reserved. Dell, EMC, and other trademarks are trademarks of Dell Inc. or its subsidiaries.
Contents Chapter 1: About this guide........................................................................................................... 5 Related documents............................................................................................................................................................. 5 Chapter 2: The S4048T-ON System...............................................................................................6 Introduction.................................................
Components....................................................................................................................................................................... 26 AC power supply installation...........................................................................................................................................27 AC power supply replacement..................................................................................................................................
1 About this guide This guide provides site preparation recommendations, step-by-step procedures for rack mounting and desk mounting, inserting optional modules, and connecting to a power source. CAUTION: To avoid electrostatic discharge (ESD) damage, wear grounding wrist straps when handling this equipment. NOTE: Only trained and qualified personnel can install this equipment. Read this guide before you install and power up this equipment. This equipment contains two power cords.
2 The S4048T-ON System The following sections describe the Dell EMC S4048T-ON system: Topics: • • • • • • Introduction System status LED display Luggage tag Prerequisites S4048T-ON configurations Introduction The S4048T-ON is a networking switch for campus aggregation and core switching 10 Gbps servers and 40 Gbps optical uplinks to the 40 Gbps switching fabric in the core.
Figure 3. S4048T-ON PSU-side view 1. 2. 3. 4. 5. PSU1 Fan modules RS-232/RJ-45 serial console port PSU2 10/100/1000BaseT Ethernet management port System status You can view system status information using the light emitting diodes (LEDs). LED display The S4048T-ON includes LED displays on both the I/O side and PSU side of the chassis. For LED information, see your third-party operating software documentation.
7. 8. 9. 10. Locator LED QSFP+ LED—top row port Stack ID number QSFP+ LED—bottom row port Table 1.
Figure 5. S4048T-ON PSU-side LEDs 1. 2. 3. 4. Fan LED Management port link LED PSU LED Management port act LED Table 2.
Luggage tag The S4048T-ON system has a pull-out tag, known as a luggage tag, on the same side as the PSUs. Figure 6. S4048T-ON luggage tag 1. Service tag 3. MAC address 2. PPID 4. Express service code Prerequisites The following is a list of system components: NOTE: For more information, see Site Preparations and S4048T-ON Installation.
● Extra fan module, recommended for redundancy ● Extra mounting brackets if installing in a four-post rack or cabinet S4048T-ON configurations You can order the S4048T-ON system in several different configurations. Optional modules and optics are available to order separately.
3 Site preparations The S4048T-ON is suitable for installation as part of a common bond network (CBN). You can install the system in: ● Network telecommunication facilities ● Data centers ● Other locations where the National Electric Code (NEC) applies For more information about S4048T-ON specifications, see Specifications. NOTE: Install the S4048T-ON system into a rack or cabinet before installing any optional components.
● Rack mounting—You may either place the switch on a rack shelf or mount the switch directly into a 19" wide, EIA-310-Ecompliant rack. ● Rack loading—Overloading or uneven loading of racks may result in shelf or rack failure and may damage the equipment or cause possible personal injury. Stabilize the racks in a permanent location before loading begins. Mount the components starting at the bottom of the rack, then work to the top. Do not exceed your rack load rating.
● AC or DC PSU with fan airflow from the PSU to the I/O Be sure to order the fans suitable to support your site’s ventilation. Use a single type of airflow fan in your system. NOTE: DO NOT mix reverse and normal airflows in a single S4048T-ON chassis. For proper ventilation, position the system in an equipment rack or cabinet with a minimum of 5 inches (12.7 cm) of clearance around the exhaust vents. When you install two systems near each other, position the two chassis at least 5 inches (12.
4 NEBS compliance For your system to be network equipment building system (NEBS) compliant, you must follow the instructions detailed in this chapter. To be NEBs compliant, orient your system in the rack so that the air inlet is from the front aisle and the air exhaust is from the rear aisle.
5 S4048T-ON installation To install the S4048T-ON system, Dell EMC recommends completing the installation procedures in the order presented in this guide. Always handle the S4048T-ON and its components with care. Avoid dropping the system or its field replaceable units (FRUs). NOTE: ESD damage can occur if components are mishandled. Always wear an ESD-preventive wrist or heel ground strap when handling the S4048T-ON and its components.
● ● ● ● One 2-hole UL-certified GND lug L-bracket Two flat head screws to attach the lug to the bracket Two pan head screws to attach the assembly to the chassis Supply the following: ● A wire that complies with your local electrical codes in size and color. The wire is typically 14 AWG colored green or green with a yellow stripe ● An antioxidant compound—Dell EMC recommends NOALOX 4 or equivalent ● A crimping tool ● A thread-locker compound—Dell EMC recommends Threadlocker Blue 242 or equivalent 1.
b. 2—GND lug c. 3—Attached ground wire 3. Attach the assembly to the S4048T-ON chassis: a. Apply the thread-locker compound to the two pan head screws. b. Attach the GND lug and bracket assembly to the two-hole chassis ground connector nuts on the PSU side. Tighten the screws to ensure torque between 3–5 inch/lbs. Figure 9. S4048T-ON PSU-side ground a. 1—Pan head screws b. 2—L-bracket CAUTION: Take care not to damage the attached ground wire as you proceed to install the switch.
Align and seat the back flange rail pegs in the back vertical post flange. This illustration shows how the pegs appear in both the square and unthreaded round holes. 2. Align and seat the front flange pegs in the holes on the front side of the vertical post. 3. Repeat this procedure for the second rail. 4. To remove each rail, pull on the latch release button on each flange ear and unseat each rail. Figure 10.
1. Slide the plunger bracket rearward until it clicks into place and secure the bracket to the front post flange with two user-supplied screws, item 1. 2. Slide the back bracket towards the post and secure it to the post flange with two user-supplied screws, item 2. 3. Repeat this procedure for the second rail. Figure 12. Two-post center-mount configuration Four-post threaded configuration CAUTION: To be NEBS Earthquake Z4-compliant, you must remove the tool-less latch castings described in Step 1. 1.
1U two-post installation You can install the switch in 1U front-rack, four-post or two-post configurations. The following is an example of a front-rack configuration. For the 1U two-post flush or center configurations, slide the system into the rails in the same manner as the four-post configurations. 1U front-rack installation Configure the rails that are attached to the system: 1. Attach the inner chassis members switch rails to the system, items 1 and 2.
2. Attach the end of the wire to the rack-end GND lug. a. Coat the bare end of the wire with an antioxidant compound. b. Insert the end of the wire into the lug. c. To secure the connection, crimp the lug end. Figure 15. Ground wire and GND lug a. 1—Ground wire b. 2—GND lug 3. Install the second GND lug, in compliance with NEC guidelines, at the desired location to ground the switch. a. Ensure that the rack mating surface is clean. b. Bring any bare metal to a bright finish. c.
Optic removal Remove an optic by pushing the tab on the optic and sliding the optic from the port. When removing optics with direct attach cables (DACs) from the port, pull the release tab firmly and steadily. Before pulling the release tab, you may need to gently push the optic into the port to ensure it is seated properly. Do not jerk or tug repeatedly on the tab. Split ports The S4048T-ON supports splitting a single 40G QSFP+ port into four 10G ports using one of the supported breakout cables.
| | | | | | | | | | +----------------------------------------------+ Your system comes with ONIE installed.
To assign an IP address to the management interface, eth0, and verify the network connectivity, use the ifconfig eth0 command, as shown. ONIE:/ # ifconfig eth0 10.11.53.33/16 Verify the network connection with ping. ONIE:/ # ping 10.11.8.12 PING 10.11.8.12 (10.11.8.12): 56 data bytes 64 bytes from 10.11.8.12: seq=0 ttl=62 time=1.357 ms 64 bytes from 10.11.8.12: seq=1 ttl=62 time=0.
6 Power supplies The S4048T-ON ships with two power supply units. The system supports AC or DC power supplies with two air-flow directions—from the I/O side to the PSU side and from the PSU side to the I/O side. Two PSUs are required for full redundancy, but the system can operate with a single PSU. The PSUs are field replaceable. When running with full redundancy—two power supply units installed and running, you can remove and replace one PSU without disrupting traffic.
WARNING: Prevent exposure and contact with hazardous voltages. Do not attempt to operate this system with the safety cover removed. CAUTION: Remove the power cable from the PSU before removing the PSU. Also, do not connect the power cable before you insert the PSU in the chassis. NOTE: To comply with the GR-1089 Lightning Criteria for Equipment Interfacing with AC or DC Power Ports, use an external surge protection device (SPD) at the AC or DC input of the switch.
NOTE: The PSU slides into the slot smoothly. Do not force a PSU into a slot as this action may damage the PSU or the S4048T–ON chassis. NOTE: If a PSU fails, you must replace the entire unit. There are no field serviceable components in the PSU. To request a hardware replacement, see Dell Support. NOTE: If you use a single PSU, install a blank plate in the other PSU slot.
7 Fans The S4048T-ON comes from the factory with two PSUs and four fan modules installed in the chassis. The fan modules and the power supplies, which have integrated fans, are hot-swappable. NOTE: To run the system, the four fan slots must have operating fan units. If you do not install a module in each slot, the system shuts down in one minute. In addition to the power supply modules, you can order and install fan modules separately. The system supports two airflow direction options.
Fan module installation The fan modules in the S4048T-ON are field replaceable. Module slot 1 is on the left side of the chassis, module slot 2 is in the middle of the chassis, and module slot 3 is on the right side of the chassis. CAUTION: DO NOT mix airflow directions. All fans must use the same airflow direction—reverse or normal. If you mix the airflow direction, to avoid damage to the switch, you must correct the mixed airflow. 1. Take the fan module out of the shipping box. 2.
4. Replace the filter with a new filter of the same size. 5. Repeat for the remaining modules that need the filter replaced.
8 Management ports Besides the 10 GbE and 40 GbE switch ports, the S4048T–ON system provides several ports for management and storage. NOTE: The output examples in this section are for reference only. Your output may vary. Topics: • • • RS-232 console port access Micro USB-B console port access USB storage mount RS-232 console port access The RS-232 console port is on the PSU-side of the S4048T-ON chassis. Figure 21. S4048T–ON PSU-side view 1. PSU1 3. RS-232/RJ-45 serial console port 5.
● No flow control Micro USB-B console port access The Micro USB-B console port is on the I/O side of the switch. NOTE: The S4048T-ON switch uses the Silicon Labs CP2109 USB-B chip. To find the correct USB-B universal asynchronous receiver-transmitter (UART) driver, see https://www.silabs.com/products/development-tools/software/ usb-to-uart-bridge-vcp-drivers. Figure 22. S4048T-ON I/O-side view 1. Forty-eight 10G Base-T ports 3. Micro USB-B console port 2. Six QSFP+ ports 4.
For internal storage: Disk /dev/sda: 15.8 GB, 15829303296 bytes 255 heads, 63 sectors/track, 1924 cylinders Units = cylinders of 16065 * 512 = 8225280 bytes Device Boot /dev/sda1 Start 1 End 1925 Blocks Id System 15458303+ ee EFI GPT For USB storage: Disk /dev/sdb: 30.9 GB, 30942946304 bytes 64 heads, 32 sectors/track, 29509 cylinders Units = cylinders of 2048 * 512 = 1048576 bytes Device Boot Start End Blocks Id System 3. Mount the device /dev/sdb to the /mnt/usb directory.
9 Specifications This chapter lists the S4048T–ON specifications. CAUTION: Operate the product at an ambient temperature not higher than 113°F (45°C). CAUTION: Lithium Battery Caution: There is a danger of explosion if the battery is incorrectly replaced. Replace only with same or equivalent type of battery. Dispose of the batteries according to the manufacturer's instructions. NOTE: For RoHS information, see Restricted Material Compliance.
Table 5. AC power requirements Parameter Specifications Power supply 100–240 VAC 50/60 Hz. Maximum current draw per system 7.1 A @ 550 Watts 3.4 A @ 550 Watts Maximum power consumption 550 Watts. Typical power consumption 338 Watts. Table 6. DC power requirements Parameter Specifications Minimum/maximum input voltage range -40.5V/ -48V/ -60V Input power at full load −40.5V/970W −48V/930W −60V/ 950W, without fan. −40.5V/980W −48V/940W −60V/ 960W, with fan. Input current at full load −40.
Figure 23. Canadian Department of Communication Statement European Union EMC Directive Conformance Statement This product is in conformity with the protection requirements of EU Council Directive 2004/108/EC on the approximation of the laws of the Member States relating to electromagnetic compatibility. Dell EMC cannot accept responsibility for any failure to satisfy the protection requirements resulting from a nonrecommended modification of this product, including the fitting of non-Dell EMC option cards.
Korean Certification of Compliance Figure 26. Korean Certification of Compliance Figure 27. Korean Package Label Safety Standards and Compliance Agency Certifications ● ● ● ● ● ● ● ● CUS UL 60950-1, 2nd Edition CSA 60950-1-03, 2nd Edition EN 60950-1, 2nd Edition EN 60825-1, 1st Edition EN 60825-1 Safety of Laser Products — Part 1: Equipment Classification Requirements and User’s Guide EN 60825-2 Safety of Laser Products — Part 2: Safety of Optical Fibre Communication Systems FDA Regulation 21CFR 1040.
Immunity ● ● ● ● ● ● ● ● ● ● EN 300 386 EMC for Network Equipment EN55022, Class A EN 55024 EN 61000-3-2 Harmonic Current Emissions EN 61000-3-3 Voltage Fluctuations and Flicker EN 61000-4-2 ESD EN 61000-4-3 Radiated Immunity EN 61000-4-4 EFT EN 61000-4-5 Surge EN 61000-4-6 Low Frequency Conducted Immunity Product Recycling and Disposal You must recycle or discard this system according to applicable local and national regulations.
10 Dell EMC support The Dell EMC support site provides a range of documents and tools to assist you with using Dell EMC equipment and mitigating the impact of network outages. Through the support site you can obtain technical information regarding Dell EMC products, access software upgrades and patches, download available management software, and manage your open cases. The Dell EMC support site provides integrated, secure access to these services. To access the Dell EMC support site, go to www.dell.