Chapter 3
Before you install
About this chapter
This chapter explains steps to take before installation and contains these sections:
Site planning and construction
on page 51
Planning the network
on page 51
Receiving all shipping and materials
on page 52
Electro static discharge and GR-1089 compliance
on page 52
Safety Recommendations and Warnings
on page 52
Site planning and construction
Before installation, the site planner or installation manager must read the IP-RN 8000 Site Planning
Guide. This guide explains all site requirements that must be met for a successful installation.
These requirements include the following:
Site construction, including the concrete pad or equivalent pad or floor that meets loading
requirements
Power supply
Grounding infrastructure
Backhaul link(s)
Power and backhaul conduits
Antenna configuration
Global Positioning System (GPS) antenna(s)
Primary external lightening/surge protection equipment
Planning the network
The network has to be planned. Network planning includes radio network planning, backhaul
infrastructure planning, and IP address/network planning.