Nova-233 G2 (mBS1105) Outdoor LTE TDD Base Station Installation Guide 04 All rights reserved © Baicells Technologies Co., Ltd.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide About This Document This document is a guidance of Nova-233 genrtation2 (G2) hardware installation for installation personnel, including the preparation of installation tools and supporting materials, the demands for installation environment, installation procedure, cable connection and power on.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide Address: 3F, Bldg A, No.1 Kai Tuo Rd., Haidian Dist., Beijing, PR China, 100085 E-mail: support_cn@baicells.com (Non-North America region) support_na@baicells.com (North America region) Website: http://www.baicells.
Nova-233 G2 (mBS1105) Outdoor LTE TDD Base Station Installation Guide Table of Contents 1. 2. 3. Product Overview ......................................................................................................... 1 1.1 Introduction ........................................................................................................... 1 1.2 Features ................................................................................................................. 1 1.3 Appearance ........
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 3.6.2 Connect GPS Antenna.................................................................................... 15 3.6.3 Connect RF Cable .......................................................................................... 15 3.6.4 Connect Optical Fiber .................................................................................... 15 3.6.5 Connect Ethernet Cable .....................................................................
Nova-233 G2 (mBS1105) Outdoor LTE TDD Base Station Installation Guide List of Figures Figure 1-1 Nova-233 G2 Appearance .......................................................................... 2 Figure 1-2 Nova-233 G2 Interfaces and Indicators ...................................................... 2 Figure 2-1 Installation Space Requirement .................................................................. 9 Figure 3-1 Installation Procedure of Nova-233 G2 ...............................................
Nova-233 G2 (mBS1105) Outdoor LTE TDD Base Station Installation Guide 1. Product Overview 1.1 Introduction Baicells Nova-233 G2 is high performance outdoor micro base station based on LTE TDD technology, which is developed by Baicells. The Nova-233 G2 supports wired backhaul connections to backbone networks, and provides LTE access to user terminals, implemented voice and data service transmissions.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 1.3 Appearance The Nova-233 G2 base station appearance is shown in Figure 1-1. Figure 1-1 Nova-233 G2 Appearance The Nova-233 G2 interfaces and indicators are shown in Figure 1-2.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide The Nova-233 G2 interfaces are described in Table 1-1. Table 1-1 Nova-233 G2 Interface Description Interface Name Description PWR Power interface: +48V (+42V~+60V) DC GPS External GPS antenna, N-female connector. ANT0 External antenna 0, N-female connector. OPT Optical interface, connect to external transmission network, used for data backhaul. ETH RJ-45 interface, used for debug or data backhaul.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide Item Description Receive Sensitivity -100 dBm Synchronization GPS, 1588 V2 Backhaul 1 Optical (SFP) and 1 RJ-45 Ethernet interface (1 GE) MIMO DL 2 x 2 Dimension 227mm (H) x 305mm (W) x 74mm (D) Installation Type Pole, wall Antenna External 17dBi directional antenna Vertical beamwidth: 35° Horizontal beamwidth:65° Downtilt angle: 8.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide Item Description Interface MTBF ≥ 150000 hours MTTR ≤ 1 hour Support remote/local maintenance, based on SSH protocol Support remote maintenance Support online status management Support performance statistics Support failure management Support configuration management Support local or remote software upgrading and loading Maintenance Support log Support connectivity diagnosis Support automatic start and configuration Support alarm reporting S
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide compliance could void the user's authority to operate the equipment. This equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference in a residential installation.
Nova-233 G2 (mBS1105) Outdoor LTE TDD Base Station Installation Guide 2. Installation Preparation 2.1 Support Materials Prepare the following support materials accordingly, as given in Table 2-1. Table 2-1 Support Materials Item Description Power cable < AWG16 e.g. AWG14 Shorter than 100m Power plug The power plug connecting to the electricity supply.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 2.3 Installation Environment 2.3.1 Locational Requirements Environments with high-temperatures, harmful gases, unstable voltages, volatile vibrations, loud noises, flames, explosives, and electromagnetic interference (large radar stations, transmitting stations, transformer substations) are not suitable for the operation of Nova-233 G2, and thus should be avoided.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide Figure 2-1 Installation Space Requirement 2.4 Personnel Requirements The installation personnel must master the basic safe operation knowledge, through the training, and having the corresponding qualifications. 2.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide reliable. Rustproofing the terminals is required. This can be done with rust preventing paint, anti-oxidation coatings, grease, and so on. 2.6 Weatherproof Protection The Nova-233 G2 adopts cold shrink tube for weatherproof protection. Before installing the cold shrink tube, clean up the interface first. The weatherproof protection steps are as follows: 1. Insert cable into cold shrink tube. 2. Tighten the connector. 3.
Nova-233 G2 (mBS1105) Outdoor LTE TDD Base Station Installation Guide 3. Base Station Installation 3.1 Unpacking Before opening the box, make sure the package is in good condition, undamaged and not wet. During the unpacking, avoid potential damaging impacts from hits or excessive force. Once unpacked, check whether the quantity are consistent with the packing list. 3.2 Installation Procedure The installation procedure of Nova-233 G2 is given in Figure 3-1.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide devices. Avoid interference from other transmitting antennas to the GPS antennas. Should be installed within 45 degrees to the lightning rod. The GPS has been assembled before packing, the only installation step is to fix the GPS mounting bracket on the base station using the M4 x 14 screws. 3.4 Install on Pole Required diameter of the pole: 40mm ~ 100mm.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 3. As the following figure, hung the two pins on the base station bracket to the installation bracket, push the base station until the hook block to the base station bracket. 4. Tighten two screws on the top of the bracket using cross screwdriver to complete the installation.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 3.5 Install on Wall The wall must bear four times of the base station’s weight. 1. Take apart the assembled installation bracket kit to get the installation bracket. 2. Fit the bracket on the wall, and mark the drilling locations. Caution: The arrow of the installation bracket must be upward. 3. Drill two 10mm diameter and 70mm depth holes in the wall on the marked locations, and insert the expansion pipes. 4.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide The label should be paste after the cable laying. Optical fiber laying requirement: The circling and twisting is forbidden during the laying. The binding on the turning is forbidden. The pulling and weigh down the optical fiber is forbidden. The redundant optical fiber must enwind the dedicated device. Grounding laying requirement: The grounding cable must connect to the grounding point.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 3. Lay optical fibers along the wire groove, and stretch out the wiring cavity from OPT hole. The redundant fiber should wind neatly. 3.6.5 Connect Ethernet Cable 1. Connect the Ethernet cable to ETH interface in the wiring cavity. 2. Lay Ethernet cable along the wire groove, and stretch out the wiring cavity from ETH hole. 3.6.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 6. If the outlet is outdoors, place the power adaptor in a water proof box. After the cable connection is complete in the wiring cavity, tighten the screws on the cover to close the wiring cavity using M4 cross screwdriver. 3.6.7 Connect Ground Cable Make the grounding cable according the actual situation of the installation site.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide that the antenna top falls within the 45 degrees safety angle towards the lightening rod, as shown in Figure 3-3. In principle, no lightening rod can be welded to pole (no metal object is allowed within 1m of the horizontal direction of the omnidirectional antennas), when installing the omnidirectional antennas.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide 3.7.2 Install Directional Antennas 1. First, assemble the antennas, as shown in Figure 3-5. Figure 3-5 Assembling Procedure of Directional Antennas 2. To install it on the iron tower, use a pulley to transport the antenna assembled to the platform on the iron tower, as shown in Figure 3-6. Following the safety rules when working at these heights. Figure 3-6 Transportation the Antennas in the Height 3.
Nova-233 G2 Outdoor LTE TDD Base Station Installation Guide Figure 3-7 Directional Antenna Installation 4. When the base station has been installed in a proper position, connect all the cables and wires. 5. Run tests, then seal and weatherproof all the connections after the testing has successfully completed. Refer to 2.6 Weatherproof Protection.
Nova-233 G2 (mBS1105) Outdoor LTE TDD Base Station Installation Guide 4. Power On Power on the Nova-233 G2, and the indicators will light up, as shown in Figure 4-1. Figure 4-1 LED Indicators The explanation of the indicator signal is given in Table 4-1. Table 4-1 Nova-233 G2 Indicator Description Type Color PWR Green RUN ALM ACT Status Meaning ON Have power input OFF No power input Fast blink: 0.125s on, 0.