pBS2120 Base Station Installation Guide 01 All rights reserved © Baicells Technologies Co., Ltd.
pBS2120 Base Station Installation Guide About This Document This document is a guidance of pBS2120 hardware installation for installation personnel, which includes the preparation of installation tools and supporting materials before installation, the demands of installation environment, installation of base station, connection of cable and power on.
pBS2120 Base Station Installation Guide Contents 1. 2. 3. 4. 5. Product Overview ......................................................................................................... 1 1.1 Introduction ............................................................................................................... 1 1.2 Features...................................................................................................................... 1 1.3 Appearance .................................
pBS2120 Base Station Installation Guide 1. Product Overview 1.1 Introduction Baicells pBS2120 is a high performance outdoor 3650MHz~3700MHz micro base station based on TD-LTE technology, which is developed by Baicells. The pBS2120 supports wired backhaul connections to backbone networks, and provides LTE access to user terminals, implemented voice and data service transmissions.
pBS2120 Base Station Installation Guide 1.3 Appearance The pBS2120 base station appearance is shown in Figure 1-1. Figure 1-1 pBS2120 Appearance The pBS2120 interfaces and indicators are shown in Figure 1-2. Figure 1-2 pBS2120 Interfaces and Indicators The pBS2120 interfaces are described in Table 1-1. Table 1-1 pBS2120 Interface Description Interface Name ETH/POE+ Description RJ-45 interface, used for data configuration or data backhaul, and PoE+ power supply.
pBS2120 Base Station Installation Guide The pBS2120 interface indicators are described in Table 1-2. Table 1-2 pBS2120 Interface Indicators Identity Color PWR Green ACT Green RUN Green ALM 1.4 Red Status Description Steady On Power On OFF No Power Supply Steady On The cell is activated. OFF The cell is not activeated. Fast flash: 0.125s on,0.125s off The board is loading. Slow flash: 1s on,1s off The board is normal. OFF No power input or board fault Steady On Hardware alarm, e.
pBS2120 Base Station Installation Guide 1.4.
pBS2120 Base Station Installation Guide 2. Out-of-Box Audit Before opening the box, make sure the package is in good condition, undamaged and not wet. During the unpacking, avoid potential damaging impacts from hits or excessive force. Once unpacked, check the contents to see if they are consistent with that in the shipping list shown in Table 2-1. Table 2-1 Shipping List No.
pBS2120 Base Station Installation Guide 3. Installation Preparation 3.1 Support Materials Prepare the following support materials accordingly, as given in Table 3-1. Table 3-1 Support Materials for Installing Base Station Item Description Ethernet cable Outdoor CAT6 Shorter than 100m (330 feet) Ground cable 16mm²yellow-green wire 3.2 Installation Tools The following tools are needed during the installation.
pBS2120 Base Station Installation Guide 3.3 Installation Environment 3.3.1 Locational Requirements Environments with high-temperatures, harmful gases, unstable voltages, volatile vibrations, loud noises, flames, explosives, and electromagnetic interference (large radar stations, transmitting stations, transformer substations) are not suitable for the operation of pBS2120, and thus should be avoided. Places prone to have impounded water, soaking, leakage, or condensation, should also be avoided.
pBS2120 Base Station Installation Guide The ground wire adopts yellow-green wire that is no smaller than 16 mm². Grounding principle: as near as possible. The eNodeB connects to the reliable outdoor grounding point (earth) through one ground screw. The connection of the grounding points and the ground bar need to be tight and reliable. Rustproofing the terminals is required. This can be done with rust preventing paint, anti-oxidation coatings, grease, and so on. 3.
pBS2120 Base Station Installation Guide cause interference, and (2) This device must accept any interference, including i nterference that may cause undesired operation of the device. Le présent appareil est conforme aux CNR d' Innovation, Science et Développement économique Canada applicables aux appareils radio exempts de licence.
pBS2120 Base Station Installation Guide 4. Base Station Installation 4.1 Install on Pole Required diameter of the pole: 40mm ~ 100mm. 1. As the following figure, assemble the bracket for pole installation, and fasten screws. 2. Mounting bracket installs is complete as shown in the following figure. 3. Fit the base station assembled bracket to the pole, pass the omega through the threaded rods, and then fasten the two nuts.
pBS2120 Base Station Installation Guide 4. Adjust base station to proper angle and fasten the screws. 4.2 Install on Wall The wall must bear four times of the base station weight. 1. Fit the base station on the wall, and mark the drilling locations. 2. Drill four 12mm diameter and 80mm depth holes in the wall by following the marked locations. 3. Check the up/down direction of the installation rack, and then fix the base station to the wall using M8*80 expansion screws. 4.
pBS2120 Base Station Installation Guide open the wiring cavity. 2. Connect the Ethernet cable to ETH interface in the wiring cavity. 3. Lay Ethernet cable along the wire groove, and stretch out the wiring cavity from ETH hole. 4. The other end of the Ethernet cable connects to the PoE power adaptor. 4.3.2 Connect Ground Cable Make the grounding cable according the actual situation of the installation site.
pBS2120 Base Station Installation Guide 5. Power On Power on the pBS2120, and the indicators will light up, as shown in Figure 5-1. Figure 5-1 LED Indicators The explanation of the indicator signal is given in Table 5-1. Table 5-1 pBS2120 Indicator Description Identity PWR ACT RUN Color Status Description Steady On Power On OFF No Power Supply Steady On The cell is activated. OFF The cell is not activated. Fast flash: 0.125s on,0.125s off The board is loading.