Baicells mBS1100 Base Station Installation Guide V100R001C00 All rights reserved © Baicells Technologies Co., Ltd.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx About This Document This document is a guidance of mBS1100 hardware installation for installation personnel, which includes the preparation of installation tools and supporting material before installation, the demands of installation environment, installation of base station, connection of cable and power on.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Contents 1. 2. 3. 4. Product Overview ....................................................................................................... 1 1.1 Introduction ............................................................................................................... 1 1.2 Features...................................................................................................................... 1 1.3 Appearance ........
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4.2.6 Connect Ground Cable...................................................................................... 19 4.3 Install the Mounting Bracket and Handle ................................................................ 20 4.4 Install GPS Antenna .................................................................................................. 22 4.5 Install on Pole ............................................................
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figures Figure 1-1 mBS1100 Appearance ................................................................................ 2 Figure 1-2 mBS1100 Interfaces.................................................................................... 2 Figure 3-1 Antenna Weatherproofing ......................................................................... 11 Figure 4-1 Installation Procedure of mBS1100 ...............................................
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figure 4-26 Directional Antenna Installation .............................................................. 28 Figure 5-1 LED Indicators ..........................................................................................
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Tables Table 1-1 mBS1100 Interface Description .................................................................... 2 Table 1-2 mBS1100 Interface Indicators ...................................................................... 3 Table 2-1 Shipping List ................................................................................................. 6 Table 2-2 Base Station Accessories ....................................................
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 1. Product Overview 1.1 Introduction Baicells mBS1100 is a high performance outdoor 3.65GHz micro base station based on TD-LTE technology, which is developed by Baicells. The mBS1100 supports wired and wireless backhaul connections to backbone networks, and provides LTE access to user terminals, implemented voice and data service transmissions.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 1.3 Appearance The mBS1100 base station appearance is shown in Figure 1-1. Figure 1-1 mBS1100 Appearance The mBS1100 interfaces are shown in Figure 1-2. Figure 1-2 mBS1100 Interfaces The mBS1100 interfaces are described in Table 1-1. Table 1-1 mBS1100 Interface Description Interface Name Description PWR Power interface: +48V (+42V~+58V) GPS External GPS antenna, N-female connector. ANT1 External antenna 1, N-female connector.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Interface Name Description DATA Gigabit Ethernet interface, external transmission network. MGMT Gigabit Ethernet debug interface. ANT2 External antenna 2, N-female connector. The mBS1100 interface indicators are described in Table 1-2. Table 1-2 mBS1100 Interface Indicators Identity PWR Green RUN Green ALM Red ACT 1.4 Color Status Description Steady On Power On OFF No Power Supply Fast flash: 0.125s on,0.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Item Description Antenna External high gain antenna Overall Power < 65 W Power 48V DC, AC adaptor Weight About 5kg Note: The test method of receiving sensitivity is proposed by the 3GPP TS 36.104, which is based on 5MHz bandwidth, FRC A1-3 in Annex A.1 (QPSK,R=1/3,25RB) standard. 1.4.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Item Description Support automatic start and configuration Support alarm reporting 1.4.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 2. Out-of-Box Audit 2.1 Shipping List Before opening the box, make sure the package is in good condition, undamaged and not wet. During the unpacking, avoid potential damaging impacts from hits or excessive force. Once unpacked, check the contents to see if they are consistent with that in the shipping list shown in Table 2-1.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Note: During the unpacking, if the outer package is damaged or wet, stop unpacking and find the cause. Report the issue to the vendor. For any shortage or damage that is identified, report the local vendor within 10 days. 2.2 Base Station Accessories Table 2-2 shows the accessories of the base station mBS1100.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 3. Installation Preparation 3.1 Support Materials Prepare the following support materials accordingly, as given in Table 3-1. Table 3-1 Support Materials for Installing Base Stations Item Description Power cable < AWG16,e.g., AWG14 Shorter than 1150 feet Antenna RF cable 50 ohm feeder Ethernet cable Outdoor CAT6 Shorter than 330 feet Antenna Omnidirectional, or directional antenna Ground wire 16mm²yellow-green wire 3.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 3.3 Installation Environment 3.3.1 Locational Requirements Environments with high-temperatures, harmful gases, unstable voltages, volatile vibrations, loud noises, flames, explosives, and electromagnetic interference (large radar stations, transmitting stations, transformer substations) are not suitable for the operation of mBS1100, and thus should be avoided.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx arrestor needs to connect to one grounding screw via an M6 screw. Another grounding screw is used for connecting to the reliable outdoor grounding point (earth). The connecting point must be tin-soldered. The connection of the grounding points and the ground bar need to be tight and reliable. Rustproofing the terminals is required. This can be done with rust preventing paint, anti-oxidation coatings, grease, and so on. 3.5 1.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4. Base Station Installation 4.1 Installation Procedure The installation procedure of mBS1100 is given in Figure 4-1. Figure 4-1 Installation Procedure of mBS1100 4.2 Connect Cable 4.2.1 Structure of Cable Connection The wire connection relationship of the mBS1100 is shown in Figure 4-2.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figure 4-2 mBS1100 Wire Connection Structure The description of the connection serial number is shown in Table 4-1.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4.2.2 Connect GPS Antenna 1. Connect the ground wire of GPS lightning arrestor to the lightning arrestor, and fasten it, as shown in Figure 4-3. Figure 4-3 Connect the Ground Wire of GPS Lightning Arrestor 2. Connect one end of the GPS RF cable to the GPS lightning arrestor, as shown in Figure 4-4. Figure 4-4 Connect the GPS RF Cable to the GPS Lightning Arrestor 3. The connection point of RF cable needs to be weatherproofed.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4. Connect the GPS RF cable to the GPS antenna lightning arrestor. It is necessary for the GPS antenna interfaces to be weatherproofed. Refer to 3.5 Weatherproof Protection for more detail. The connection is complete shown in Figure 4-6. Figure 4-6 Connect GPS RF Cable 4.2.3 Connect RF Cable 1. Connect the RF cable to the ANT1 and ANT2 interface of the mBS1100. 2. It is necessary for the ANT1 and ANT2 interfaces to be weatherproofed.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figure 4-8 Separate the Ethernet Weatherproof Connector 2. Slide the weatherproof connector components in turn. A click should be heard to ensure that the RJ45 connector has clip into the slot of weatherproof connector, as shown in Figure 4-9. Figure 4-9 Install the Ethernet weatherproof Connector 3. Connect the weatherproof connector to the base station’s DATA interface, and fasten it.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4.2.5 Connect Power Connector The weatherproof connector is adopted for power cables. First, you need to assemble the power weatherproof connector. In the accessories for base station, the output end of the power adaptor has red and black power cord, where the red power cord is +48V, and the black power cord is 0V. The output voltage is 48V DC. The connection relationship of the power cord and the power connector is shown in Figure 4-11.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figure 4-12 Disassemble the Power weatherproof Connector 2. Slide the weatherproof connector parts 1, 2 and 3 in turn. 3. Unscrew the compression screw of the fourth part of the power connector with a T-15 torx screw driver, as shown in Figure 4-13 . Figure 4-13 Unscrew the compression screw 4. Insert the red power cable (48V) into terminal A, and insert the black power cable (0V) into terminal B, as shown in Figure 4-14.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 5. Tighten the power cord in the socket by using T-15 torx screw driver to crimp the threads, ensure the power cable crimping tight. 6. Screw parts 1, 2, and 3 respectively. The assembly of the power connector is complete. 7. Connect the power connector to the PWR interface of the base station and fasten it. 8. Weatherproof the power connector. Refer to 3.5 Weatherproof Protection for more detail.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx to the grounding screw of the device, as shown in Figure 4-17. Figure 4-17 Connect GPS Lightning Arrestor Grounding Cable 2. Unscrew another grounding screw, connect one end of the ground cable to the grounding screw of the device, as shown in Figure 4-18. Figure 4-18 Ground Cable Complete 3. The other end of the ground cable needs to connect to a good ground (earth). 4.3 1.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figure 4-19 Install the Mounting Bracket 2. Use the M6*12 socket head screw to fix the handle on right side of the mBS1100, as shown in Figure 4-20. Figure 4-20 Install the Handle 3. Figure 4-21 shows what it looks like when the installation of rack and handle is done.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figure 4-21 Installation of Mounting Bracket and Handle Completed 4.4 Install GPS Antenna Installation requirements on the GPS antenna: No major blocking from buildings in the vicinity. Keep the rooftop buildings a distance away from the GPS. Make sure the space atop within 90 degrees (at least 45 degrees) is not blocked by any buildings. Avoid installing the GPS in the vicinity of any other transmitting and receiving devices.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 3. Fit the GPS mounting bracket 1 on the GPS mounting bracket 2 with an M4 screw according to the required angle. 4. Fit the GPS antenna on the GPS mounting bracket 1 with an M4 screw. Vertical installation is required. 5. Installation complete.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4.5 Install on Pole Required diameter of the pole: 30mm ~ 125mm. 1. The two U type clamps pass through the mounting brackets on both sides of the base station. Then the omegas pass through the threaded rods of the U type clamp, and fasten them with M8 nuts. 2. Hold the assembly up to the pole. Attach the two omegas to the threaded rods with M8 nuts.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4.6 Install on Wall 1. Put the base station on the wall to install, and mark the drilling locations. 2. Drill four 10mm diameter and 70mm depth holes in the wall by following the marked locations. 3. Check the up/down direction of the installation rack, and then fix the base station to the wall using M8*80 expansion screws. 4.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx (no metal object is allowed within 1m of the horizontal direction of the omnidirectional antennas), when installing the omnidirectional antennas. Instead, an independent lightening rod should be settled between the two poles, where the lightening rod must be high enough to keep all antennas under its protection cover.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 4.7.2 Install Directional Antennas 1. First, assemble the antennas, as shown in Figure 4-24. Figure 4-24 Assembling Procedure of Directional Antennas 2. To install it on the iron tower, use a pulley to transport the antenna assembled to the platform on the iron tower, as shown in Figure 4-25. Following the safety rules when working at these heights. Figure 4-25 Transportation the Antennas in the Height 3.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Figure 4-26 Directional Antenna Installation 4. When the base station has been installed in a proper position, connect all the cables and wires. 5. Run tests, then seal and weatherproof all the connections after the testing has successfully completed. Refer to 3.5 Weatherproof Protection.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx 5. Power On Power on the mBS1100, and the indicators will light up, as shown in Figure 5-1. Figure 5-1 LED Indicators The explanation of the indicator signal is given in Table 5-1. Table 5-1 mBS1100 Indicator Description Type PWR RUN ALM ACT Color Green Green Red Green Status Meaning ON Have power input OFF No power input Fast blink: 0.125s on, 0.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx Appendix A Additional Information A.1 Antenna Information The following is a list of antennas that are certified for use. Customers can choose different antennas according to the environment. Table 5-2 Antenna Information Antenna Type Antenna Max Gain(dBi) Manufacturer Model Number External Planar Antenna Dual Pole Kenbotong Technology Co., Ltd. KBT90DP16-3338 AT0 16 External Planar Antenna Dual Pole Kenbotong Technology Co.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx A.2 Maximum Output Power The maximum output power can be set as follows: Antenna Max Gain (dBi) 10Log(Number of antennas) Channel BW (MHz) Max output power (dBm) EIRP (dBm) 10 21 40 20 24 43 10 23 40 20 26 43 10 26 40 20 29 43 10 30 40 20 33 43 10 27 40 20 30 43 10 30 40 20 33 43 10 30 39 20 33 42 16 14 11 7 3 10 7 6 A.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference in a residential installation. This equipment generates uses and can radiate radio frequency energy and, if not installed and used in accordance with the instructions, may cause harmful interference to radio communications.
Baicells mBS1100 Base Station Installation Guide(V100R001C00,03).docx IC Compliance This device complies with Industry Canada licence-exempt RSS standard(s). Operation is subject to the following two conditions: (1) This device may not cause interference. (2) This device must accept any interference, including interference that may cause undesired operation of the device. Le present appareil est conforme aux CNR d'Industrie Canada applicables aux appareils radio exempts de licence.