AS4000 Wireless Local Loop System Demand Assignment Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning Preface 605-0000-453 Issue 1.2dr Date 7/02/00 Notice 1. This manual is subject to revision. 2. All rights reserved. 3. Right of modification reserved. 4. This manual is supplied without liability for errors or omissions. 5. No part of this manual may be reproduced or used except as authorised by contract or other written permission. 6.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning Preface 605-0000-453 Issue 1.2dr Date 7/02/00 Safety Instructions - Warnings and Cautions SAFETY 1. Read and follow all warning notices and instructions marked on the product or included in this manual 2. Do not allow anything to rest on any power cord and do not locate the product where persons could step or walk on a power cord. 3.
AS4000 Access Concentrator Installation and Commissioning Preface 605-0000-453 Issue 1.2dr Date 7/02/00 NOTE AS4000 products do not contain hazardous substances (as defined in UK ‘Control of Substances Hazardous to Health Regulations 1989’, and the ‘Dangerous Substances Regulations 1990’).
AS4000 Access Concentrator Installation and Commissioning Preface 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning ICL 001 605-0000-453 Issue 1.2dr Date 7/02/00 ISSUE CONTROL LIST Title Title Page ICL-001 IXL-001 GSI-001 GSI-002 GSI-003 DLP-001 DLP-002 DLP-003 DLP-004 DLP-005 DLP-006 DLP-007 DLP-008 DLP-009 DLP-010 DLP-011 Appendix 1 Appendix 2 Appendix 3 Appendix 4 Page 1 of 2 Issue 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning IXL 001 605-0000-453 Issue 1.2dr Date 7/02/00 INDEX TASK LIST PREFACE: Safety Instructions Warnings and Cautions User Response Form ACCESS: ICL, IXL Issue Control List ................................................................................................ ICL-001 Index Task List .................................................................................................... IXL-001 GENERAL SYSTEM INFORMATION: GSI Introduction. .......
AS4000 Access Concentrator Installation and Commissioning IXL 001 605-0000-453 Issue 1.2dr Date 7/02/00 1.3. Securing the rack using overhead Ironwork.........................................................3 1.4. Securing a Rack to a Wall ...................................................................................4 Access Concentrator Rack Cabling. ................................................................... DLP-003 1. DC Power ...............................................................
AS4000 Access Concentrator Installation and Commissioning IXL 001 605-0000-453 Issue 1.2dr Date 7/02/00 1.1. Test Equipment Calibration.................................................................................1 Site Acceptance ................................................................................................... DLP-011 1. Site Inspection ........................................................................................................1 2. Site Acceptance Forms...................
AS4000 Access Concentrator Installation and Commissioning IXL 001 605-0000-453 Issue 1.2dr Date 7/02/00 List of Figures Figures DLP-001 Figure 1. Packaging for AC Site DLP-002 Figure 2. Access Concentrator Rack. Figure 3. Securing Rack Base Figure 4. Typical Overhead Ironwork Support Figure 5. Securing Rack To Wall DLP-003 Figure 6. DC Termination on Combiner Shelf. Figure 7. Rack Earthing Figure 8. AS4000 Alarm Unit Connections Figure 9. Access Concentrator Interface Panel (1010 Board) Figure 10.
AS4000 Access Concentrator Installation and Commissioning IXL 001 605-0000-453 Issue 1.2dr Date 7/02/00 List of Tables Table GSI-003 Table 1. Physical Characteristics. Table 2. Environmental Specifications. Table 3. Power Requirements. DLP-001 Table 4. Required Test Equipment. DLP-003 Table 5. DC Power Cables. DLP-005 Table 6. . PSU Voltage Test DLP-006 Table 7. Access Concentrator Shelf PSU Voltages. DLP-009 Table 8. Access Concentrator Shelf Card LED Indications.
AS4000 Access Concentrator Installation and Commissioning IXL 001 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning IXL 001 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning GSI 001 605-0000-453 Issue 1.2dr Date 7/02/00 INTRODUCTION 1. Purpose of Document This document describes the installation and commissioning of the ACC AS4000 Access Concentrator (AC) Rack and associated shelves to Release 5.0 specifications. 2.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning GSI 002 605-0000-453 Issue 1.2dr Date 7/02/00 OVERVIEW 1. Installation Tasks The installation procedures are arranged as a series of tasks and are generalised to cover the majority of applications and configurations.
AS4000 Access Concentrator Installation and Commissioning GSI 002 605-0000-453 Issue 1.2dr Date 7/02/00 2.2. ESD Electro-Static Discharge. Many circuits contain devices that are susceptible to damage from high impedance voltage sources. To avoid such risks always follow anti-static procedures.
AS4000 Access Concentrator Installation and Commissioning GSI 003 605-0000-453 Issue 1.2dr Date 7/02/00 TECHNICAL SPECIFICATIONS 1. Access Concentrator The following tables provide technical specifications for the AS4000 Access Concentrator. Physical Characteristics AC Rack Dimensions, (without brackets): Width 600mm Height 2175mm Depth 300mm Shipping Weight: Rack Frame 60 kg AC Shelf Card Set Table 1. Physical Characteristics.
AS4000 Access Concentrator Installation and Commissioning GSI 003 605-0000-453 Issue 1.2dr Date 7/02/00 POWER REQUIREMENTS DC Input Voltage Operating Range. (N.B. This supply to be a guaranteed SELV from an EN60950 approved source.) Maximum Range, -21.8V DC to -60.aV DC @ 540W DC Input Current (Fully populated AC Rack) 25 Amps max. @ -21V DC 11.5 Amps max. @ -48V DC 9 Amps max. @ -60V DC Recommended Power Distribution Fusing (With a readily accessible disconnect device which will isolate all poles.
AS4000 Access Concentrator Installation and Commissioning DLP 001 605-0000-453 Issue 1.2dr Date 7/02/00 PREPARATORY TASKS 1. Installation Tools and Equipment The following lists of tools and equipment are required to successfully install and test the AS4000 Access Concentrator Racks. 1.1. Required Tools • Combination Spanners: 8 mm, 13 mm, 17 mm, & 19 mm. • Spirit Level: 18 inch. • Pozidrive: No 1 x 75 mm. • No 2 x 100 mm • No 3 x 150 mm. • Screwdriver, flat blade: 3 mm x 100 mm.
AS4000 Access Concentrator Installation and Commissioning DLP 001 605-0000-453 Issue 1.2dr Date 7/02/00 1.2. Required Equipment Item Description Recommended Model Quantity 1 Digital Multimeter Fluke 77 or similar 1 2 3 4 5 6 7 Table 4. Required Test Equipment. 2. Site Readiness Verify that the site is ready for the installation of the AC Rack. This preparation will have been covered by a site survey conducted by ACC or by a survey form completed by the customer.
AS4000 Access Concentrator Installation and Commissioning DLP 001 605-0000-453 Issue 1.2dr Date 7/02/00 2.2. Site Earth Confirm the position of the grounding point using the site survey. 2.3. Flooring Ensure that flooring is substantial enough to support the rack and can provide a secure fixing. 2.4. Cable Trays Verify that cable trays are installed to provide routing to the proper destinations and are of adequate strength 2.5.
AS4000 Access Concentrator Installation and Commissioning DLP 001 605-0000-453 Issue 1.2dr Date 7/02/00 2.6. Unpacking Inspection The contents of each box must be checked against the relevant part lists provided with the box, for the correct part numbers and quantities, and for damage.
AS4000 Access Concentrator Installation and Commissioning DLP 002 605-0000-453 Issue 1.2dr Date 7/02/00 RACK INSTALLATION 1. Positioning and Securing Racks 1.1. Installing Rack in a Suite From the site survey, confirm the position of the AC Racks. If the racks are to be positioned in a suite, metalwork will be required to secure it to the overhead structure. Either a proprietary system or fabricated steelwork will be required - see site survey. Manoeuvre the racks into position. Figure 2.
AS4000 Access Concentrator Installation and Commissioning DLP 002 605-0000-453 Issue 1.2dr Date 7/02/00 1.2. Securing Rack Base Using the base of the rack as a template, mark the floor locating positions through the cut-outs in the Rack Frame. Using a 13mm diameter drill bit, drill four holes to a depth of approximately 25mm. Position the rack over the four holes and screw the four (supplied) M12 screws through washers to secure the rack base. Washer Fixing Screw Rack Base Figure 3.
AS4000 Access Concentrator Installation and Commissioning DLP 002 605-0000-453 Issue 1.2dr Date 7/02/00 1.3. Securing the rack using overhead Ironwork Assemble the overhead steelwork as required and secure the rack to the overhead structure using suitable fixings in compliance with local requirements. Remove all burrs and sharp edges. M16 Nut Tie Bar Clamps 50mm x15mm Tie Bar Plastic End Caps M16 Threaded Drop Rod (cut to length) M16 Washer and Securing Nut M16 Welded Nuts mm 415 mm 92 Figure 4.
AS4000 Access Concentrator Installation and Commissioning DLP 002 605-0000-453 Issue 1.2dr Date 7/02/00 1.4. Securing a Rack to a Wall If the rack is to be positioned against a wall, attach the two right-angled wall brackets (these brackets are part on the packaging) to the top of the rack and finger tighten with the provided M12 screws. Manoeuvre the racks into position against the wall.
AS4000 Access Concentrator Installation and Commissioning DLP 003 605-0000-453 Issue 1.2dr Date 7/02/00 ACCESS CONCENTRATOR RACK CABLING 1. DC Power The cables for the negative DC battery feeds, the 0V returns and the Rack Ground are detailed in Table 2. Should local requirements specify otherwise, it is acceptable for cables of other colours to be used, however, under no circumstances should the cable sizes be less than that specified in Table 2.
AS4000 Access Concentrator Installation and Commissioning DLP 003 605-0000-453 Issue 1.2dr Date 7/02/00 Remove clear plastic cover protecting the DC input terminals. Trim cables and strip 7mm. Crimp a spade terminal or terminal ring onto the wire and attach to terminals inside the Fuse and Alarm panel at the appropriate connection points. The negative supplies go to Termination Block 1 & 4. The positive battery returns go to 2 & 5. See Figure 6.
AS4000 Access Concentrator Installation and Commissioning DLP 003 605-0000-453 Issue 1.2dr Date 7/02/00 2. Rack Earthing Using the site survey, locate the building central [safety] grounding point. Run an earth cable rated at 30A to each rack and connect it to the centre earth stud located at the top or bottom (not both) of the rack. See Figure 7. These points are labelled with the IEC Earth symbol. . Earthing Point Earthing Point Rack Base Figure 7.
AS4000 Access Concentrator Installation and Commissioning DLP 003 605-0000-453 Issue 1.2dr Date 7/02/00 If a visual indication at the rack is all that is required, connect the alarm unit from the D-type connector on the AU55B to P9 in the Fuse and Alarm Panel. Airpan Alarm Unit Connections Receive Attention To Next Rack To Station Alarm Scheme Minor (Deferred) Major (Prompt) 1 2 3 4 5 0V Return - 48V 9 11 6 To Alarm Fuse Box Figure 8.
AS4000 Access Concentrator Installation and Commissioning DLP 003 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning DLP 003 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning DLP 003 605-0000-453 Issue 1.2dr Date 7/02/00 7. 2Mbit/s Cabling (Switch Link) From the site survey, confirm the location of the Digital Distribution Frame (DDF) if a DDF is to be used or the Switch if the 2Mbit/s feeds are fed direct to the equipment. The length of 2Mbit/s feeds should not exceed 250 metres. Note: This must be a SELV port of an EN 60950 approved product.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning DLP 004 605-0000-453 Issue 1.2dr Date 7/02/00 CARD INSTALLATION The AC rack is shipped with shelves fitted to customer requirements and internal cabling complete. Warning: Before handling any cards or modules, observe full anti-static precautions 1. Preliminary In a new installation Ensure that the AC Circuit on the Fuse and Alarm panel are switched are set to the OFF position (down) See Figure 12.
AS4000 Access Concentrator Installation and Commissioning DLP 004 605-0000-453 Issue 1.2dr Date 7/02/00 2. Card Insertion Insert the cards into the shelves, recording the serial numbers and revision status in the test form. See DLP007. The actual cards provided will depend upon the customer configuration. a) The load Sharing PSUs go in slots 1&2. b) The Shelf Controller goes in slot 3. c) All other slot positions are configurable via Sitespan. d) 3 CTUs are supported.
AS4000 Access Concentrator Installation and Commissioning DLP 004 605-0000-453 Figure 14. Typical card set for V5.2 Page 3 of 4 Sp TU8 Spare CU CU CU CU Spare Spare XTU XTU Spare CTU CTU CTU SC PSU2 PSU1 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning DLP 005 605-0000-453 Issue 1.2dr Date 7/02/00 SYSTEM TESTING This section sets up the parameters for the system and the connection to Sitespan. Refer to the Sitespan, document no. 605-0000-428 for the detailed configuration and set up procedures of the AS4000 System. 1.
AS4000 Access Concentrator Installation and Commissioning DLP 005 605-0000-453 Issue 1.2dr Date 7/02/00 2.1. PSU Voltage AC Shelves: (Test 2a) Using the DMM, measure and record the DC voltage at the front panel test points on each of the PSU’s on the AC Shelf. Card Fail PSU OK I/P A Fail I/P B Fail O/P Overload O/P Underload 5V 3.3V 2.1V 0V Figure 15. AC Shelf PSU Ensure that the voltages measured are within the limit shown in Table 6. Record the results in test form.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning DLP 006 605-0000-453 Issue 1.2dr Date 7/02/00 TURN-UP AND DC MEASUREMENTS STEP 1. PROCEDURE Rack Turn-Up and Measuring Input Voltage(Test 1a) This section describes the procedure for measuring and connecting DC to the rack, checking that the cards have the correct alarm indications on power-up and measuring the PSU output voltages. Unscrew retaining screws on the face of the Fuse and Alarm Panel.
AS4000 Access Concentrator Installation and Commissioning DLP 006 605-0000-453 Issue 1.2dr Date 7/02/00 Using the DMM check that the DC voltage supply across the input terminals (TB1(-); TB2+;.for Supply 1 and TB4(-); TB5(+) for supply 2). Ensure that the voltage measured complies with the site nominal voltage and is within the limits specified on the test results sheet. 3.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 SETTING UP SYSTEM USING SITESPAN Within Sitespan, both the racks and the shelves must be ‘built’before connecting to the Racks Do not connect Sitespan to the rack at this stage. This should be done prior to the commissioning of either the AC or CT racks. The following steps must be followed: STEP 1.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 6. If using the fixed network, select the name of the PC that Sitespan is running on. 7. Connect the server from the ‘edit menu’ 8.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.2dr Date 7/02/00 9. From the Object List, Site click right mouse button and select Site Properties 10. Enter Site Details 11. Repeat Steps 8-10 for each of the CT sites.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 2. Setting up CT Rack and Shelf configuration on Sitespan 1. Highlight the site, click right mouse button and select ‘Create Child Element’ 2. Select ‘Airspan DA CT rack’ 3.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.2dr Date 7/02/00 4. Select ‘1 (Top) ’(to set up modem shelf 1) 5. Highlight shelf, and edit ‘parent properties’ 6.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 7. Select Com port and unique TEI identifier to communicate with the AC shelf. 8. Set the reference clock source to the DTU connected to the CTU in the AC rack from where the clock source is derived. This is usually Slot 5 E1-1 for 75ohm Backhaul or Slot 5 E1-5 for 120ohm Backhaul.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 2. Highlight slot 5 for the DTU ( Slot 5 is the first slot available for assigning as a DTU) and click right mouse button select ‘Create Aux’ from the ‘edit menu’ 3. Select ‘Airspan DA DTU’ 4. Display the shelf view and select the DTU card. Click right mouse button and select ‘Airspan DA DTU Properties’. 5.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 4. Setting up AC Rack and Shelf configuration on Sitespan 1. Highlight the site, click right mouse button and select ‘Create Child Element’ 2.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 3. Highlight the rack in Object List, click right mouse button and select create ‘Airspan DA AC shelf’ 4. Select the position for the AC shelf. 5.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 6. Choose Airspan DA AC Shelf 7. Enter Shelf Name, Reference Clock Source to derive timing from the network. This is usually the first E1 on the first XTU card i.e slot 5 E1-1. The Com Port is the Sitespan PC port connected to the AC shelf. The TEI must be a unique number within the system. The shelf object list shows what TEIs have been allocated to each shelf. Leave the indirect box unchecked.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 5. Assign Access Concentrator Card Slots 1. From Object List, Shelf select Access Concentrator, click right mouse button and select Element View 2. Position mouse over Aux card position to insert card, click right mouse button and select Create AUX 3. Select the child type to create. 4. Repeat steps 1 to 3 for all cards to be installed in the shelf.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 6. Configure AC Cards 6.1. CTU 1. Position mouse over CTU card position to insert card, click right mouse button and select Airspan CTU Properties 2. Select the Impedance of the E1 connections to the Central Terminal. Repeat for other CTU cards. 6.2. CAS 1. With Shelf view displayed.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 6.3. DATA 1. With Shelf view displayed. Position mouse over the DATA Card (if DATA card installed) position to insert card, click right mouse button and select Airspan DATA Properties. Click left mouse button in the box alongside each E1 link provisioned to the Switch. Set the impedance of each link. If special signalling features are required, click the Configure button and enter the parameters.
AS4000 Access Concentrator Installation and Commissioning DLP 007 605-0000-453 Issue 1.2dr Date 7/02/00 6.4. V5.1 1. With Shelf view displayed. Position mouse over the V5.1 Card (if V5.1 card installed) position to insert card, click right mouse button and select Airspan V5.1 Properties. Click left mouse button on each E1 linkTab provisioned to the Switch. Enable Channel, set the impedance of each link. Enter Interface ID and Variant Number (these must match those provided at the switch).
AS4000 Access Concentrator Installation and Commissioning DLP 008 605-0000-453 Issue 1.2dr Date 7/02/00 SHELF CONTROLLER SOFTWARE DOWNLOADS STEP PROCEDURE The SC must be loaded with the latest Shelf Controller and TU software to ensure that the cards operate correctly. All the software for the cards in the shelf is downloaded and stored in the SC card. All of the software versions are downloaded to the SC irrespective of whether the SC is an AC SC or a CT SC. This is useful for fault finding 1.
AS4000 Access Concentrator Installation and Commissioning DLP 008 605-0000-453 Issue 1.2dr Date 7/02/00 5. ‘Double click’ item of software to download. 6. Check that the version for download is the latest version, select ‘download’. 7. Repeat steps 5 and 6 for all the software files to be loaded. Download progress is shown on the main software download screen. Files waiting to be downloaded will show Download pending in the object list.
AS4000 Access Concentrator Installation and Commissioning DLP 008 605-0000-453 Issue 1.2dr Date 7/02/00 8. Wait for the download to complete which could take several hours. 9. Once the software downloads are complete reset by ‘hot plugging’the Shelf Controller Card 10. All the cards on the modem shelf now boot-up. 11. The TU cards l display the following LED sequence: Note: The boot-up procedure for these cards takes approximately 15minutes. a) Red LED, amber LEDs & green surface mount LEDs all ON.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.2dr Date 7/02/00 15.
AS4000 Access Concentrator Installation and Commissioning DLP 009 605-0000-453 Issue 1.2dr Date 7/02/00 CONFIGURING THE ACCESS CONCENTRATOR STEP 1. PROCEDURE Configure the Access Concentrator 1. Select the Access Concentrator to be configured. 2. Connect the Access Concentrator shelf to Sitespan (ensuring the cable is connected to selected com port) SLOT 4 SITESPAN ! E1 IN E1 OUT SITESPAN 2 E2 IN E2 OUT Figure 19. Access Concentrator Shelf Backplane 3.
AS4000 Access Concentrator Installation and Commissioning DLP 009 605-0000-453 Issue 1.2dr Date 7/02/00 e) Red LED ON, green LED FLASHING, amber LEDs OFF & green surface mount LEDs showing download progress. f) Green LED ON, green surface mount LEDs indicate card configuration as shown below LED 1 Top 2 3 4 Bottom DTU OFF OFF ON OFF XTU ON OFF OFF OFF 7.
AS4000 Access Concentrator Installation and Commissioning DLP 009 605-0000-453 Issue 1.2dr Date 7/02/00 STEP 2. PROCEDURE Alarm and Status Indications (Test 3) 1. Verify that the alarms and status indications (LED’s) on the system comply with those detailed in the following tables. Note: The following tables are set in order of appearance on the front of the card reading from top to bottom.
AS4000 Access Concentrator Installation and Commissioning DLP 009 605-0000-453 Issue 1.2dr Date 7/02/00 PSU Position TOP 1 Colour Red 2 3 Green Red 4 Red 5 6 Red Red Description FUSE FAIL: Illuminated if either input fuse has blown. OK Card is Active. I/P A FAIL input voltage A (BATTNEG0) not present I/P B FAIL input voltage B (BATTNEG1) not present O/P OVERLOAD. O/P UNDERLOAD Status OFF ON OFF OFF OFF OFF Table 8. Access Concentrator Shelf Card LED Indications.
AS4000 Access Concentrator Installation and Commissioning DLP 009 605-0000-453 Issue 1.2dr Date 7/02/00 17. Click Self Test button to reset. Check that each card passes 18. This concludes the setting up at the access concentrator. The CT site can now be commissioned STOP. THIS PROCEDURE HAS BEEN COMPLETED.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning DLP 010 605-0000-453 Issue 1.2dr Date 7/02/00 COMMISSIONING TEST RESULTS 1. Commissioning Test Results Please photocopy test results sheet for use with each system 1.1.
AS4000 Access Concentrator Installation and Commissioning DLP 010 605-0000-453 Issue 1.2dr Date 7/02/00 CUSTOMER:..................................................... SITE LOCATION: ............................................. RACK ID: .......................................................... ENGINEER:....................................................... DATE:................................................................
AS4000 Access Concentrator Installation and Commissioning DLP 010 605-0000-453 Issue 1.2dr Date 7/02/00 Rack ID............................. PARA . TASK / TEST RESULT Site Inspection & Verification 2 Mbit/s AC Shelf 1 Cabling AC Shelf 2 System Commissioning Tests Test 1a Exchange DC Voltage Supply 1 Supply 2 Test 1b Exchange DC Voltage Supply 1 Supply 2 Test 2 AC Shelf 1 PSU1 Test 2 AC Shelf 1 PSU2 Test 2 AC Shelf 2 PSU1 Test 2 AC Shelf 2 PSU2 PARA. LIMIT -21.8 to -60.0V DC -21.8 to -60.
AS4000 Access Concentrator Installation and Commissioning DLP 010 605-0000-453 Issue 1.2dr Date 7/02/00 Rack ID… ............................ PARA.
AS4000 Access Concentrator Installation and Commissioning DLP 011 605-0000-453 Issue 1.2dr Date 7/02/00 SITE ACCEPTANCE 1. Site Inspection Check all work areas are free of debris i.e. cable off-cuts, braid, dust and packaging and that the site is as found. 2. Site Acceptance Forms ACC and customer copies of site acceptance forms are provided on the following pages.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.2dr Date 7/02/00 This page left blank.
AS4000 Access Concentrator Installation and Commissioning DLP 011 605-0000-453 Issue 1.2dr Date 7/02/00 AS4000- ACCESS CONCENTRATOR ACCEPTANCE FORM CONTRACT OR CUSTOMER'S REF. NO:................................................................. AS4000 COMMUNICATIONS CORPORATION LTD REF. NO:.............................. SITE IDENTITY:............................................................................................................
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.2dr Date 7/02/00 This page left blank.
AS4000 Access Concentrator Installation and Commissioning DLP 011 605-0000-453 Issue 1.2dr Date 7/02/00 AS4000- ACCESS CONCENTRATOR ACCEPTANCE FORM CONTRACT OR CUSTOMER'S REF. NO:................................................................. AS4000 COMMUNICATIONS CORPORATION LTD REF. NO:.............................. SITE IDENTITY:............................................................................................................
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Appendix 1 Issue 1.2dr Date 7/02/00 APPENDIX 1 Appendix 1 BNC Terminations to Coax 1. Slide metal crimp sleeve over cable,trim outer sheath from cable as shown. 16mm Sleeve Braid 2. Trim back braid and dielectric to the dimensions as shown. 8mm Dielectric Centre Conductor 4mm 3. Fit contact over the centre conductor to butt against the dilectric, then crimp. Male Contact Crimp Here 4. 5.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Appendix 2 Issue 1.2dr Date 7/02/00 PROCEDURE IN CASE OF CARD BOOT-UP FAILURE Procedure in case of card boot-up failure If the cards inserted into the shelf do not boot-up, the top red LED on the card will be either continuously ON or FLASHING. The following steps should be followed: 1. Check cards are properly inserted into the shelf, in the correct positions. 2. Reset the SC card using Sitespan, under the card view. 3.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Appendix 3 Issue 1.2dr Date 7/02/00 LAT SETTINGS 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Appendix 4 Issue 1.2dr Date 7/02/00 SITESPAN DATABASE TRANSLATION V2.5 TO V3.4 1. Close down all Sitespan Client/Server applications running on the network. 2. Ensure that the server25.olg & server25.svd files are located on the root C: drive of your PC. 3. Ensure that server34.olg & server34.svd files DO NOT exist on the root C: drive of your PC. 4. If there is a server34.olg or server34.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Appendix 4 Issue 1.2dr Date 7/02/00 6. Run the Sitespan Server for Sitespan V2.5 7. In the “Trans” program connect to the V2.5 Server by selecting “Create” and Select OK when asked to connect to the Remote Machine Name 8.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.2dr Date 7/02/00 9. Disconnect the Source Server (V2.5). 10. Shut down the Sitespan V2.5 Server program 11. Start the Destination Server V3.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Appendix 4 Issue 1.2dr Date 7/02/00 12.Connect to the Destination Server 1. The destination server will indicate that it is connected and ready 2. Click on the Transfer button. This will start converting the V2.5 database to the new V3.4 format 3.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.2dr Date 7/02/00 4. Close the V3.4 Server and exit the “trans” program. The files C:server34.olg & C:server34.svd should now be created on your PC. Your Database is now compatible with the new V3.4 Server & Client applications.
AS4000 Access Concentrator Installation and Commissioning 605-0000-453 Issue 1.